Progress/Performance Report for the Building Control Shared Service
NotedCommittee1 paper
South Worcestershire Shared Services Partnership Joint Committee noted this item on Monday 11 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved 1. That the Progress/Performance Report to the end of March be noted. 2. That the carry forward of £5,000 from the current year projected underspend to meet ongoing costs associated with the implementation of the new single Building Control system be approved.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
Report to South Worcestershire Shared Services Partnership Joint Committee, 7 pages
Summary
1.1The shared service continues to maintain performance in excess of targets. Performance for registration and acknowledgement of applications within 2 working days for January and February has exceeded the target of 92% and for plan checking within 10 days is above the target of 90%. These results have been achieved despite the service still using three IT system arrangements and working towards implementation of the single IT system.
1.2Expenditure this year against budget suggests a significant under spend, primarily due to not recruiting to the full staffing levels set out in the business case in the light of the current economic downturn. Both Wychavon and Worcester City’s incomes are in line with income targets. Malvern Hills continues to suffer poor income against the current year forecast although there has been a slight improvement in the end of year projected income..
Recommendations
2.1That the Progress / Performance Report to the end of March is noted by the Joint Committee.
2.2Approve the carry forward of £5,000 from the current year projected underspend to meet ongoing costs associated with the implementation of the new single Building Control system
3. OPERATIONAL UPDATE
3.1Update on IT Implementation:
• MIS systems, the provider of the single IT system for the shared service have successfully completed creating the routines to import data from the existing systems at Wychavon (Plantech) and Worcester City (OCELLA). This means that from the 21st March they provided a test data base for Building Control to start testing.
Page 1 of 7 • The system that updates the new web site is also ready to go, and subject to staff training, the system can be updated by the Building Control admin team. The website will be the central platform for customer information and interaction including the Building Control Register and on-line submission of applications.
• The new MIS Building Control system will integrate with Wychavon land charges (SwiftLG) through a live view of building control applications mapped in the GIS and directly incorporated into the Swift system.
• Worcester land charges will receive new applications, passed directly into Northgate on a regular basis using a component of Northgate. Existing applications information will either be delivered using GIS or by address using LLPG integration as the means of passing data. The decision on which process will be used is yet to be decided as some work (data matching or data capture) will have to be undertaken by Worcester.
• As the implementation of the single system is now well in progress, an updated plan and timetable has been agreed to which shows ‘go live’ process to start from the 4th of May and to be completed by the 16th of June. The actual ‘go live on the new system’ is anticipated to take place on the 13th of May 2011.
3.2Update on Marketing:
• Marketing work and initiatives are progressing and are in line with the Service’s five year marketing forward plan.
• The market share by number of applications remains at 90%
• Preparation is in progress for the first SWBCP Building excellence awards which is to take place on the 27th April. All nominations have been considered and three have been shortlisted in each of the six categories. There will be one winner and two runners up in each category.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow South Worcestershire Shared Services Partnership Joint Committee at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingResolved That the Minutes of the meeting of the Joint Committee held on Monday 24 January 2011 be approved as a corre...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.