Resolved
Resolved That this application be approved subject to: 1. The development hereby permitted shall be begun before the expiration of three years from 17 September 2013 (the date of permission ref. no. W/13/01345/PN). Reason: In accordance with the requirements of Section 91 (1) of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. 2. Prior to the commencement of development hereby approved, details of a 1 metre high acoustic barrier to be erected above the 1.8 metre brick boundary wall along the northern boundary between units 3 & 4 and 7 & 8 shall be submitted to and approved by the local planning authority. The approved fencing shall be erected in accordance with the approved details prior to any of the units being first occupied/used and the fencing shall remain in place for perpetuity. Reason: To safeguard the amenities of the occupiers. 3. The development hereby permitted shall be carried out in accordance with the following approved plans: 2010.48 04, 2010.48 03C, 2010.48 02, 2010.48 01, 2010.48 05 Reason: To define the permission. 4. The materials shown on the plans approved under permission ref. no. W/14/00142 shall be used and no others substituted without the approval, in writing, of the Local Planning Authority before work on the site commences. Reason: To ensure that the development is visually satisfactory. 5. In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’ and where remediation is necessary a remediation scheme must be prepared and approved in writing by the Local Planning Authority in advance of the scheme commencing. Following completion of measures identified in the approved remediation scheme a verification report must be prepared which shall be submitted to and approved in writing by the Local Planning Authority prior to development commencing other than works required to be carried out as part of an approved scheme of remediation. Reason: To ensure that the risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecosystems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other off-site ... view the full minutes text for item 253.
Word for word from the decision Wychavon published for this meeting.
Source: mgov.wychavon.gov.uk