Resolved
Resolved That the Minutes of the meeting of the Committee, held on Friday 13 February 2026, be approved as a correct record and signed by the Chair.
Audit Committee approved this item on Friday 27 March 2026. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the Minutes of the meeting of the Committee, held on Friday 13 February 2026, be approved as a correct record and signed by the Chair.
Wychavon District Council
Minutes of a meeting of the Audit Committee held in the Council Chamber, Civic Centre, Queen Elizabeth Drive, Pershore on Friday 13 February 2026, commencing at 2.00 p.m.
Present: Councillor A Hardman – Chairman Councillor N Dawkes – Vice-Chairman
Members: Councillors
N Franks A Hartley E B Tucker
Independent Member:
G Moore
Executive Board Members: Councillors
Councillors:
Officers:
A Mason J Pickering
Azets:
K Jones
23. Apologies for Absence
There were no apologies for absence.
24. Declarations of Interest
There were no declarations of interest.
25. Minutes of the Previous Meeting
That the Minutes of the meeting of the Committee, held on Friday 21 November 16 AC. 13.02.26 2025, be approved as a correct record and signed by the Chair.
26. Statement of Accounts 2024/25
Jayne Pickering, Deputy Chief Executive, introduced the report and informed the Committee that it presented the final Statement of Accounts for 2024/25 following audit.
The Committee was informed that due to the circumstances outlined at previous meetings regarding the national audit backlog, the accounts would again be disclaimed.
Following a brief clarification regarding the timeline of some of the content within the Statement of Accounts it was
Resolved
(1) That the Audit Committee approve the Statement of Accounts for 2024/25.
(2) That the Audit Committee approve the delegation for the Chair of the Audit Committee, together with the S151 Officer, to approve the Letter of Representation for 2024/25. This being included as a template in Azets’ Audit Completion Report within the agenda.
27. Audit Completion Report
Karen Jones, Key Audit Partner at Azets, introduced the item and explained the reasons for the disclaimed audit, confirming that it had not been possible to undertake sufficient work to achieve the necessary assurances.
Karen thanked the Council’s Finance Team for their constructive work in helping Azets deliver its Audit Completion Report.
The Committee was advised that no material adjustments to financial statements had been identified.
The Committee was updated regarding work that Azets had been unable to conclude for the 2024/25 period, and the significant risk areas identified within the report, which included:
• Property, Plant and Equipment (PPE) and the valuations of PPE. The Committee was informed that the Council would carry out a full revaluation of its asset portfolio in 2025/26, which would allow Azets to continue with its “build-back” work to provide assurance.
• Pensions. It was explained that as the triennial pension valuation was due to be completed in 2025/26, Azets would wait to audit this from the next financial year.
The Committee was then given details of Azets’ programme of “build-back” work that had started in 2024/25. This work was focused on three key areas: 17 AC. 13.02.26 • The preparation of a risk assessment for the Council that had taken into consideration a number of risk factors from the previous four years. The Committee was assured that the risk assessment had determined that the Council was at the lower end of the risk spectrum.
• The analysis of movements in useable and unusable reserves in order to ensure reserves had been appropriately stated. It was confirmed this work was ongoing.
• Testing of the disposals and additions of the Council’s Property, Plant and Equipment, which had not identified any matters that required reporting.
The Committee was advised that work was on track for Azets to report a clean audit opinion by 2027/28.
The Committee was asked to note that Azets required the approved Letter of Representation, the template of which was included with report, and that Azets expected to meet the 27 February back-stop date for the work relating to the 2024/25 audit.
In addition, the Committee was informed that the back-stop date for the 2025/26 accounts would move forward one month, to January 2027.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the Previous MeetingMinutes | 5 pages | DownloadRead as text |
Follow Audit Committee at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Sep 2026 | Minutes of the Previous MeetingResolved That the Minutes of the meeting held on Friday 26 June 2026, be approved as a true and fair record and signe... | Approved | Open |
| 11 Sep 2026 | Corporate Risk Register 2026/27 - six month reviewIt was agreed that officers would consider this point. With no further comments, questions or discussion it was Resol... | Agreed | Open |
| 26 Jun 2026 | Minutes of the Previous MeetingResolved That the Minutes of the meeting of the Committee, held on Friday 27 March 2026, be approved as a correct rec... | Approved | Open |
| 27 Mar 2026 | Corporate Risk Register 2026/27Resolved That the Corporate Risk Register for 2026/27 be approved by the Committee. | Approved | Open |
| 27 Mar 2026 | Accounting Policies for 2025/26 AccountsResolved That the Accounting Policies to be used in preparing the Council’s 2025/26 Statement of Accounts be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.