Wychavon District Council
Council, Wednesday 30 September 2026

Recommendations from Executive Board

Approved Committee 6 papers

AI summaryWychavon Council approved a £777,500 plus VAT refurbishment of Pershore Leisure Centre's health suite under the preferred Option 2, funded from the Building Enhancements budget and Regeneration reserves.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedIncluded in 2026/27 capital programme, funded gap from reserves
Money£777,500 plus VATPlus £182,500 capital budget, £595,000 from reserves
What happens nextFinal scoping delegatedDeputy Chief Executive with Resources Portfolio Holder
Who it affectsPershore Leisure Centre usersAnd Wychavon Leisure Community Association Ltd

What was decided

Council agreed to include the cost of the preferred scheme, Option 2, in the 2026/27 capital programme and approved the funding gap from reserves as set out in section 5 of the report. Report 2.2, 5.3

Council delegated to the Deputy Chief Executive, in consultation with the Portfolio Holder for Resources, Investment and Innovation, authority to agree the detail on how the facility will be finally scoped within budget. Report 2.3

Why

The health suite is nearly 25 years old, beyond its expected service life, with a delaminating spa pool and worn-out plant, and many members choose not to use it.

Wychavon Leisure Community Association Ltd preferred Option 2, expecting increased footfall and revenue at a centre that is only just covering costs, with April 2025 to April 2026 visits at 12,816 against a potential of close to 20,000. Report 4.7

The site is on a floodplain so the building cannot be extended, making the re-use of underused male dry changing space the practical route to a larger health suite. Report 4.6

What happens next

The scheme will move into technical design (RIBA stage 3 to 4), with a further report to members if estimated costs cannot be covered. Report 5.3

A separate report in November will cover renewal and updating of the leisure centre and lido leases with a profit share agreement between the council and Wychavon Leisure. Report 4.8

The money

  • £777,500 plus VAT Option 2 estimated project cost Report P20
  • £575,570 plus VAT Option 1 estimated project cost Report P19
  • £182,500 Building Enhancements capital budget allocation for Option 2 Report P25, P27
  • £595,000 Regeneration reserves for Option 2 Report P26

Options considered

  • Rejected: Option 1: refurbish within the existing health suite room, replicating a jacuzzi, steam room, sauna, shower and relaxing area. Limited by room size, no additional spa amenities, and not expected to lift footfall Report 4.4, 4.5
  • Chosen: Option 2: knock through into part of the adjoining male changing room to create a larger health suite with additional heat and cold treatment amenities. WLCA preferred option, expected to improve user experience and increase revenue, with the male changing area judged larger than needed Report 4.5, 4.6, 4.7

Implications

  • Financial: £595,000 will need to be drawn from Regeneration reserves to fund the funding gap on top of the £182,500 capital allocation. Report P25, P26
  • Risk: Estimated costs may prove insufficient after technical design; a further member report will follow if value engineering cannot close any gap, and all contracts will follow the council's contract procedure rules. Report 5.3
  • Equalities: No equality issues have been identified around the project. Report 6.3
  • Other: The refurbishment supports the council's We are Wychavon Plan aim of helping people live healthier lives through quality leisure facilities. Report 6.2

Who and where

  • Users and members of Pershore Leisure Centre Report 4.7
  • Wychavon Leisure Community Association Ltd, which manages the centre Report 4.7

Timeline

  • 12th February 2025: Members received a report on the Building Enhancements Budget and acknowledged that the health suite scope and budget needed review. Report 3.2
  • April 2025 to April 2026: Pershore Leisure Centre recorded 12,816 visits against a potential of close to 20,000. Report 4.7
  • 2026/27: Preferred scheme (Option 2) to be included in the capital programme. Report 2.2
  • November: Separate report to members on renewing and updating leisure centre and lido leases with a profit share agreement. Report 4.8

Plain English for the jargon

  • RIBA stage 2: Concept feasibility design stage used by the architect appointed for the project.
  • WLCA: Wychavon Leisure Community Association Ltd, the body that manages Pershore Leisure Centre for the council.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item49

Resolved

Resolved That Council approve the budget parameters for the 2027/28 budget, as set out in 3.20 of the report. Health Suite Pershore Leisure Centre. Councillor E Stokes introduced the report and expressed pleasure in the opportunity to provide an enhanced user experience at Pershore Leisure Centre. Councillor Stokes proposed the recommendations. Executive Board Member for Wellbeing, Social Mobility and Transformation, Councillor D Birch, noted the need for improvements and explained that Wychavon Leisure have been calling for them for a long time. The improvements to all three Wychavon Leisure sites were noted by Councillor Birch. These improvements will allow the leisure centres to compete with high-end private companies. Councillor Birch noted that despite the investments, customer prices have only gone up in line with inflation. Councillor Birch seconded the recommendations. Councillor J Arnold expressed her view that investing in leisure facilities for residents is very important, and money well spent, and encouraged all members to work with Councillor Birch to ensure that the facilities remain affordable for all residents. Councillor Birch agreed with Councillor Arnold and stated that he raises the cost of memberships in his meetings with the Managing Director of Wychavon Leisure. It was noted that a programme of free swimming has been rolled out and improvements to the environmental stability of the sites will bring a reduction in running costs. Councillor D Boatright-Greene expressed pleasure that this item was coming forward and noted that smaller pop-up gyms had previously appeared in Pershore as the facilities in the leisure centre had not been good enough. A vote was taken and it was unanimously Resolved That Council agree to include the cost of the preferred scheme (option 2) in the 2026/27 capital programme and approve the funding gap from reserves as set out in section 5 of the report. And To delegate to the Deputy Chief Executive in consultation with the Portfolio Holder for Resources, Investment and Innovation authority to agree the detail on how the facility will be finally scoped within budget. Fixed Penalty Notices for Fly Tipping and Littering. Councillor E Stokes introduced the report and explained that the ability to increase the listed fines had been put in place at the start of September. The increased level ... view the full minutes text for item 49.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Council

Council 30th September 2026

Pershore Leisure Centre Health Suite Relevant wards: Pershore Portfolio holder: Cllr Emma Stokes

Head of Service: Jayne Pickering, Deputy Chief Executive Contact officer: Janette Becket, Head of Property and Development If you have any questions about this report, please contact the portfolio holder or the contact officer.

1. Purpose and summary 1.1 To seek approval for the refurbishment of the health suite at Pershore leisure centre and for members to identify their preferred option.

2. Recommendations 2.1 That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and the feasibility design options and costs and identify a preferred scheme to proceed to the next stages of technical design and delivery.

2.2That the Executive Board recommends to Council to include the cost of the preferred scheme in the 2026/27 capital programme and approve the funding gap from reserves as set out in section 5 of the report.

2.3To delegate to the Deputy Chief Executive in consultation with the Portfolio Holder for Resources, Investment and Innovation authority to agree the detail on how the facility will be finally scoped within budget. 2.4 To delegate to the Deputy Chief Executive in consultation with the Portfolio Holder for Resources, authority to enter into any appropriate contracts and legal agreements associated with the refurbishment works.

3. Background 3.1 The health suite within Pershore leisure centre is nearly 25 years old being the original from when the centre was rebuilt in 2003. It has come to the end of its life and in need of replacement, being uneconomic to repair the existing sauna and steam rooms and associated equipment. The spa pool construction is delaminating, the spa plant is worn out, and the general area has deteriorated with time and use. These items are all well beyond their expected service life and are not providing a quality experience for users with many members choosing not to use it as a consequence. It is the Council’s responsibility to replace.

3.2There are allocated funds for works to the health suite included in the Building Enhancements Budget which was approved to cover capital cost for maintaining and replacing building elements where the Council is responsible. On 12th Feb 2025 members received a report on the update to the progress and spend against this budget and within the report advised that the scope of works and budget identified for the health suite needed to be reviewed to provide updated costs for member approval for a whole refurbishment and planned installation in 2026/27. This was acknowledged.

4. Feasibility Outcome 4.1 Following a procurement exercise Quattro Design Architects were appointed to work with both Wychavon Leisure Community Association Ltd who manages the centre (WLCA) and the Council to produce concept feasibility designs ( RIBA stage 2).

4.2For context Appendix 1 shows the current layout of the leisure centre’s ‘wet’ side’ changing and shower rooms and the location of the current health suite.

4.3After several iterations and meetings bringing together the designer’s expertise and WLCA’s operational knowledge, it was narrowed down to 2 options to present to members.

4.4Option 1 as shown in Appendix 2 uses the existing health suite room but has redesigned the space to maximise the use and flow of the area although this is limited due to the size. There wouldn’t be space for additional spa amenities so would just replicate the existing namely, a jacuzzi, steam room, sauna, shower and a relaxing area.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 241 KB Download
PDF
Appendix AAppendix A 183 KB Download
PDF
Revenue Money Plan post EBBAppendix B 853 KB Download
PDF
Capital ProgrammeAppendix C 199 KB Download
PDF
Pershore LC Health Suite: EBB report 020926Report 138 KB DownloadRead as text
PDF
Recommendations from Executive BoardReport 203 KB Download

At this meeting

Whole meeting

Who was there

0 of 44 attended
RA
Councillor Rob AdamsMember, expected
JA
Councillor Jodi ArnoldMember, expected
DB
Councillor Daniel BirchMember, expected
JB
joe bloggsOfficer, expected
DB
Councillor Dan Boatright-GreeneMember, expected
LB
Lawrence BoltonSecretary, expected
EB
Councillor Eric BowdenMember, expected
JC
Councillor Jenny ChaudryMember, expected
JC
Councillor Judith CiottiMember, expected
JC
Councillor John ClatworthyVice-Chairman, expected
AC
Councillor Angie CrumpMember, expected
ND
Councillor Nick DawkesMember, expected

All 44 on the meeting page

On this subject at Wychavon

Search all
  1. Recommendations from Executive BoardThis decision
  2. Recommendations from Executive BoardApproved
  3. Recommendations from Executive BoardApproved
  4. Recommendations from Executive BoardNoted
  5. Recommendations from Executive BoardApproved
  6. Recommendations from Executive BoardApproved

More from Wychavon Council

All decisions
MeetingDecisionOutcome
30 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the Council meeting, held on 15 July 2026, be approved as an accurate record of proceedi... Approved Open
30 Sep 2026 Community Governance Review - Defford & Besford Parish CouncilResolved That Council approves the following changes to Defford & Besford Parish Council and recommend that a Reorgan... Approved Open
30 Sep 2026 Community Governance Review - Impney Parish CouncilResolved That Council approves the following changes to the border between Dodderhill Parish Council and Droitwich To... Approved Open
30 Sep 2026 WDC response to the Regulation 19 Publication consultation on the Cotswold Local Plan being prepared by Cotswold District CouncilResolved That the Council endorse the representations from Wychavon District Council to the Cotswold District Local P... Decided Open
15 Jul 2026 Minutes of the Previous MeetingResolved That the minutes of the Ordinary Council meeting held on 15 April 2026, the Annual Council meeting held on 1... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies