Item1
Resolved
The Corporate Director Communities submitted a report asking the Resources Portfolio Holder to approve the re-roofing works at Units 11, 12, 14, 17 and 18 Croft Court, Butts Close, Redmarsh Industrial Estate, Thornton Cleveleys and to include the scheme in the Council’s 2023/24 Capital programme. Decision The Resources Portfolio Holder agreed: · That approval is given for re-roofing works at Units 11, 12, 14, 17 and 18 Croft Court, Butts Close, Redmarsh Industrial Estate. · That the scheme, costing £131,488 is added to the Council’s 2023/24 Capital Programme.
Word for word from the decision Wyre published for this meeting.
Source: wyre.moderngov.co.uk