Members received a report which was an update on the progress of the Housing Repairs Partnership Agreement and sought approval to deliver the council adaptations, on a 12 month pilot, through the Partnership. The contract for the delivery of adaptations work to council homes for older and vulnerable tenants was won by Commercial Services (Neighbourhood Services) in 1998. This contract had now expired, although the current contractual arrangements had been extended and prices renegotiated to ensure continuity of service. However procurement options for the future now needed to be agreed and considered in line with other arrangements in place for the delivery of work to council properties. It was proposed that the adaptations work be delivered within the already agreed principles of the repairs partnership and benefit from the advantages and improvements that partnership working had already delivered for the responsive repairs service, and that this arrangement be reviewed in 12 months time. The service would continue to be delivered by the teams in Housing and Neighbourhood Services however the same issues of efficiency and duplication would be reviewed as with the repairs service. The Executive Member for Housing offered her congratulations to staff of the Housing Repairs Partnership on the fantastic results achieved and the improved performance. Advice of the Advisory Panel That the Executive Member for Housing be advised to (i) Note the progress and achievement of the Housing Repairs Partnership; (ii) Agree the recommendation that the Adaptations work to the Councils HRA housing stock be delivered within the already agreed principles of the Housing Repairs Partnership, on a 12 month pilot with the out come reported back to Members. Decision of the Executive Member for Housing
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Housing and Adult Social Services Advisory Panel
Meeting of the Executive Members for 30th October 2006 Housing and Adult Social Services and Advisory Panel Report of the Director of Housing and Adult Social Services Report of the Director of Neighbourhood Services
Housing Repairs Partnership - Update
Summary 1. This report is an update on the progress of the Housing Repairs Partnership Agreement and seeks approval to deliver the council adaptations, on a 12 month pilot, through the Partnership.
Background 2. In September 2003 the Executive approved in principle, the procurement of housing repairs, from Commercial Services (Neighbourhood Services), and the implementation of a partnering agreement between Community Services (Housing and Adult Social Services) and Commercial Services (Neighbourhood Services).
3. The details of the Partnership were agree in November 2004 and replaced the R10 contract, tendered under CCT in 1996, for the delivery of the repairs service to council homes in July 2005.
4. A Service Level Agreement was developed which outlined the basis of partnership working together in a culture of cooperation, openness and trust to deliver the best possible service to our customers. The principles of this agreement are:
Delivery of a high quality repairs and maintenance service;
Maintain customer satisfaction;
Continuous Improvement;
Joint control and responsibility for costs, and provide the service customers want within the agreed budget;
Work towards reducing the actual cost of delivering the service;
Eradicate duplication, bureaucracy and waste; Promote ‘right first’ time;
Ensure value for money;
Reduce disputes;
Be motivated.
It is against these broad principles that the success of the Partnership should be judged.
5. The contract for the delivery of adaptations work to council homes for older and vulnerable tenants was won by Commercial Services (Neighbourhood Services) in 1998. This contract has now expired, although the current contractual arrangements have been extended and prices renegotiated to ensure continuity of service. However procurement options for the future now need to be agreed and considered in line with other arrangements in place for the delivery of work to council properties.
Consultation 6. The update on the partnership is for information only therefore there has been no specific consultation, however the Annual Housing Service Monitor, which is an annual survey of satisfaction of council tenants with the service they receive, reported in 2005 that seventy-seven per cent of respondents were satisfied with the way the Council deals with repairs. This is a reduction in satisfaction on the previous year but it should be highlighted that the survey was carried out only a few months after the partnership was established and therefore any improvements in satisfaction levels as a result of the change in working should be reflected in the 2006 AHSM. Recent customer satisfaction of P2 repairs (those which were un appointed and/or non urgent during July show an improved level of overall satisfaction across all areas of the service from initial reporting of a repair to quality of workmanship and completion.
Options 7. This report is an update on the progress of the Partnership, the specifics of which have already been agreed by Executive. The options for the council adaptations work will be dealt with later in this report
Analysis 8. Prior to the establishment of the Partnership the responsive repairs service to council homes was independently bench marked against comparator organisations. This bench marking exercise concluded that:
the costs of the service were competitive;
a higher than average number of repairs were carried out by appointment;
that there was a clear commitment to continuous improvement; there was a genuine desire by the management team to succeed;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing and Adult Social Services Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Former Tenants Arrears – Write offAdvice of the Advisory Panel That the Executive Member be advised to approve Option 2, which involves writing off FTA...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.