Resolved
Advice of the Advisory Panel That the Executive Member be advised: (i) That the proposed move of the project completion date be accepted. Decision of the Executive Member
Corporate Services and Advisory Panel decided this item on Tuesday 12 December 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Advice of the Advisory Panel That the Executive Member be advised: (i) That the proposed move of the project completion date be accepted. Decision of the Executive Member
2. The 2004/05 IT Development Plan recognised the need for a replacement Financial Management System (FMS). The current system was implemented in 1994 and since then the functionality and technology platform that it uses has become dated. FMS is a critical system that holds the financial data that is used by the Council to operate as a business. The dependency on this system is very high as it is used for financial reporting and management information purposes as well as running the Councils purchasing, payments and sundry income collection operations. Although continued supplier support has been guaranteed for the system, the number of other local authority users is diminishing, meaning that future development will be limited.
Timescale
3. The original timescale of the project was based on a phased implementation with the new system implemented by April 2008.
Phase 1 Procurement March 2006 - March 2007
Phase 2 Implementation April 2007 - April 2008
Phase 3 Rollout Programme April 2008
Objectives
4. A number of Corporate Objectives have been agreed for the Project and are included in Appendix A together with the Scope, however, primarily the Project aims are:
‘To implement a Financial Management System, whereby current systems and processes will be simplified to achieve an efficient and effective delivery of financial information to the Council1, it's customers and ongoing development of partnership working’.
5. Key stakeholders within the organisation have been consulted during the procurement stage of the project with workgroups established to specify the requirements of the replacement system. A communications strategy has been developed, an intranet bulletin board has been set up along with a newsletter updating stakeholders of progress to date.
Options and Analysis
6. This report is to update the Executive Member on the progress of the FMS project and associated timescales to implementation. Analysis on the project progress to date is included in the sections below.
Project Progress
7. The progress achieved to date is:
A Project Communication Structure
a) Established a Project Board to capture representation across the Directorates.
b) Identified a number of personnel across all directorates who have a broad understanding of systems and processes common to the Financial Management System. These members of staff will provide a key communication channel to ensure the project achieves its aims and is implemented with minimal disruption to operations.
c) Draft communication strategy identified and methods and timelines for communicating information within the Project and CYC.
B Agreed the Approach - Stage 1 Procurement March 06 – April 07
a) The expected cost of the replacement system will be in excess of EU thresholds for public procurements. The advice received by the Project Board is that the most appropriate route for the Council to use in procuring the system will be the ‘Restricted’ procedure. Unlike the ‘Open’ procedure, the restricted procedure limits the number of tenders advancing to full evaluation through pre-qualification assessment without compromising the competitive process. This helps allows for a transparent, streamlined and efficient evaluation process that nonetheless ensures compliance with EU Directives.
1 Assumes those that are users of or recipients of Financial Management Information C Project Support Recruited
a) At the beginning of June two Project Support staff were recruited onto the Project Team, their role to assist the Project Manager with administrative duties and co-ordination of specific activities in line with the Project plan.
D Project Objectives and Scope Agreed
a) See Appendix A
E Site Visits to Local Authority
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 46 KB | Download |
PDF |
Appendix BAppendix B | 16 KB | Download |
PDF |
FMS Replacement Project: Progress ReportReport | 54 KB | DownloadRead as text |
Follow Corporate Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jan 2009 | MinutesThat the minutes of the meeting held on 9 December 2008 be approved and signed by the Chair and Executive Member as a... | Approved | Open |
| 20 Jan 2009 | Forward Plan Update(i) That the arrangements for dealing with write-offs be delegated to the Head of Finance in consultation with the Ex... | Decided | Open |
| 20 Jan 2009 | Resources Budget ProposalsAdvice of the Advisory Panel That the Executive Member be advised: (i) That the budget proposals were in line with th... | Noted | Open |
| 20 Jan 2009 | Resources Directorate PlanAdvice of the Advisory Panel That the Executive Member be advised: (i) That the for 2009-2010 be approved. (ii) That ... | Approved | Open |
| 9 Dec 2008 | MinutesThat the minutes of the meeting held on 21 October 2008 be approved and signed by the Chair and Executive Member as a... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.