That the Draft Development Brief be approved for consultation for the mixed-use development of the Nestle South site, subject to the following amendments : 1)Para 2.25 Reference to the East Coast Main line amended to York to Scarborough line 2)Para 2.20 Addition to sentence describing Clarence Gardens as “well used” 3)Para 2.22 Check whether the Nestlé Rowntree sports pitches are member only facilities for Nestlé employees 4)Para 2.23 Add Nestlé Rowntree allotments at Mille Crux 5)Para 2.21 - Check whether Clifton Ings is nearest Open Access Land and add reference to Clifton Backies (Local Nature Reserve) 6)Chapter 5 – Amend ‘sympathetic manufacturing’ to ‘light industry’ 7)Para 5.6 Delete first sentence and rephrase second sentence re. feasibility of older buildings on site 8)Para. 5.7 Delete ‘innovative live / work units’ from second sentence 9)After para 5.10 add paragraph to properly define a live / work unit and rationalize the use of the term ... view the full minutes text for item 43.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. Introduction 1 Site History 1 Why a Development Brief now? 1 Purpose of Brief 2 Vision 3 Key Objectives 3
2. Site and Surroundings 5
3. Policy Context 9 National Planning Policy 9 Regional Planning Policy 9 Local Planning Policy 11
4. Sustainable Development 14
5. Development Opportunities 17
6. Design and Landscape Principles 21 Understanding the Site 21 Heritage 21 Links and Spaces 23 Scale, Height, Massing and Character 25 Landscape Treatment 26 Trees 27
7. Open Space, Recreation and Public Art 28
8. Safety and Security 31
9. Archaeology 32
10. Sustainable Transport 34
11. Highways and Parking 38
Nestlé South Draft Development Brief Chapter Page
12. Accessibility 41
13. Environmental Issues 42 Air Quality 42 Contaminated Land 44 Noise and Other Amenity Issues 45 Ecology 46 Flood Risk 47
14. Services / Public Utilities 48
15. Developing Proposals 49 Public Consultation on this Draft Development Brief 49 Public Consultation on Development Proposals 49 Masterplanning 50 Planning Applications and Conditions 50 Planning Obligations 51 Environmental Impact Assessment 53
Appendices 1. Summary of the History of Nestlé Rowntree 54
2. List of Documents 56 3. City of York Council Contacts 57
Plans Plan 1 – Site Location Plan 2 – The Site Plan 3 – Development Control Local Plan Proposals Plan Extract Plan 4 – Existing Buildings Plan 5a – Existing Cycle Paths and Footpaths Plan 5b – Existing Bus Routes and Stops Plan 5c – Potential Areas of Traffic Improvement Plan 6 – Buildings of Special Character Plan 7 – Local Service Provision
Nestlé South Draft Development Brief Chapter 1: Introduction
1. I N T R O D U C T I O N
History 1.1 The site is historically associated with the manufacture of confectionary and cocoa, being the main production site for Nestlé Rowntree (and its previous companies in York) since 1890 when it was first developed by Joseph Rowntree as the “Cocoa Works”.
1.2The works have progressively expanded from the south to the north over the last century, and this can be seen through the various building styles and materials. Appendix 1 summarises the history of Nestlé Rowntree from the 18th century.
1.3The most intensive period of development at the site was between 1890 and 1940. This was characterised by the erection of large, multi storey blocks constructed in reinforced concrete or built in steel frames clad in brick and ashlar York stone dressings.
1.4Between 1940 and 1970 development on the site slowed considerably, as Rowntrees sought to establish a global network of manufacturing bases. The company acquired UK and international companies and invested in new build factories around the UK, which were more ideally suited to automation and modern manufacturing techniques.
1.5The next phase of major development occurred in the 1980’s, particularly after the acquisition of Rowntree PLC by Nestlé in 1988. This period included the construction of new, large single storey production and warehousing buildings.
1.6The area that is subject of this Development Brief contains the core of the original factory, built between 1890 and 1940, at the southern margin of the Nestlé Rowntree site.
Why a Development Brief now ?
1.7As part of the plans announced by Nestlé Rowntree in September 2006, there was a clear commitment to stay in York, to safeguard the long- term employment of the 1,800 remaining employees.
1.8A massive capital investment is needed in order to upgrade and improve facilities on the more modern northern part of the site, leaving redevelopment opportunities on the older, southern part of the site closest to the city centre.
1.9This southern area (referred to as Nestlé South in the rest of this brief) represents around 40% (7.9 hectares/ 19.5 acres) of the overall site plant and
Nestlé South Draft Development Brief 1 Chapter 1: Introduction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.