Waste PFI – Updated Outline Business Case

Noted Executive 2 papers

Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 27 March 2007. Below is the council's own wording, with the papers it was decided on.

Item194

Resolved

(i) That it be confirmed that the Council is committed to finding the additional resources required to make the project affordable over its life, as set out in paragraphs 14 to 28 of the report, subject to any further obligations and financial parameters that may be directed by DEFRA or any other government department. REASON: To progress the PFI application for funding to DEFRA. (ii) That the revised timescales identified in paragraph 10 of the report be noted. REASON: For information. (iii) That the substantial savings that have been achieved due to the dramatic increase in recycling rates in the last four years, and the successful waste minimisation campaigns run by City of York Council, be noted, and that the Council’s commitment to reducing the need for residual disposal through the waste hierarchy be re-affirmed. REASON: To recognise the achievements already made in this area, as well as the need for continued action. (iv) That the Executive’s support for Mechanical Biological Treatment as the preferred residual waste treatment process for York’s waste be re-affirmed. REASON: In view of the need to take proactive steps to treat residual waste. (vi) That the Local Government Association campaign to have Landfill Tax rises returned to local government in full be supported. REASON: To reduce the burden on local authorities and boost the minimal support grant received for recycling services. (vii) That the Retail Packaging Bill before Parliament, presented on 6 March 2007, be supported. REASON: In order to support efforts to address the problem of excess packaging, which cannot easily be re-used or recycled. (i) That it be confirmed that the Council is committed to finding the additional resources required to make the project affordable over its life, as set out in paragraphs 14 to 28 of the report, subject to any further obligations and financial parameters that may be directed by DEFRA or any other government department. REASON: To progress the PFI application for funding to DEFRA. (ii) That the revised timescales identified in paragraph 10 of the report be noted. REASON: For information. (iii) That the substantial savings that have been achieved due to the dramatic increase in recycling rates in the last four years, and the successful waste minimisation campaigns run by City of York Council, be noted, and that the Council’s commitment to reducing the need for residual disposal through the waste hierarchy be re-affirmed. REASON: To recognise the achievements already made in this area, as well as the need for continued action. (iv) That the Executive’s support for Mechanical Biological Treatment as the preferred residual waste treatment process for York’s waste be re-affirmed. REASON: In view of the need to take proactive steps to treat residual waste. ... view the full minutes text for item 194.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Executive 27 March 2007

Report of the Director of City Strategy

Waste PFI – Updated Outline Business Case Summary 1. This report provides updated financial information on the waste pfi project, and identifies a revised affordability position for the Council. Members are requested to confirm they are committed to finding the additional resources required to make the project affordable over the life of the project.

Purpose of report 2. 1) To advise the Executive of reduced costs and revised timescales for the proposed PFI procurement project for future waste services, and;

2) To satisfy DEFRA requirements for commitment to the affordability of the proposed project.

Background 3. The Executive approved the submission of an Outline Business Case (OBC) to DEFRA for joint procurement of future waste treatment services with North Yorkshire County Council on 12 September 2006.

4. DEFRA have subsequently revised and further clarified the requirements for PFI projects in relation to sites and planning consents, necessitating the OBC to be updated accordingly. The opportunity has also been taken to revise predicted waste flows and costs using up to date estimates.

5. The Councils have also recently set their budgets for 07/08, and Medium Term Financial Strategies (MTFS) covering 08/09 and 09/10. The base budget information used in the OBC has therefore been revised, with a consequential impact on the affordability of the project.

6. Changes to waste flows and financial information are a consequence of external factors such as waste growth and market prices, and will need continual monitoring to ensure project estimates remain up to date. 7. In addition to these changes, DEFRA have specifically requested that Members are fully aware of the affordability of the project relevant to each Authority, including appropriate sensitivity analysis.

Waste Volumes and Growth

8. Estimates of future waste flows and growth have been revised to reflect the latest information available. The most significant changes result from increases in recycling and composting performance in 2005/06 and 2006/07 compared to that predicted in the OBC, and reduced waste growth.

9. Estimates of future growth in waste have been revised downwards to more accurately reflect recent experience and trends. The consequence of this reduction is that the total amount of waste predicted to be handled in the period from 2008 to 2033 across York and North Yorkshire has reduced by approximately 370,000 tonnes to 13,255,000 tonnes. Biodegradable waste sent to landfill in the same period is also predicted to reduce from 2,209,700 to 1,946,300 tonnes . The reduction in estimated waste has had implications on the costs of the project, reducing the size of the treatment plants and thus operating costs. Other costs have also been updated, including taking into account price and interest rate changes since submitting the OBC.

Programme changes

10. As a consequence of the changes to the procurement strategy, key dates have now changed. Acquisition of sites and planning consents have become critical activities to delivery of the overall programme. Any slippage in tasks associated with this work stream will delay the whole programme. Revised key dates are:

OBC Revised Key Issue/Event Date Date PFI Procurement PRG approval of OBC Jan 07 May 07 Prepare Planning Application for Treatment Plants Jul 09 Sept 07 Issue OJEU Feb 07 June 07 Issue Tenders July 07 Aug 07 Contract Award Nov 08 Mar 10 Consent Granted Apr 11 Sept 09 Construction Period - Efw Apr 11 – Mar 10 – Apr 13 Mar 13 Status as at 05/03/07 Consultation 11. As this report is an update on the process and financial information relating to the project no consultation has been undertaken on these aspects.

Corporate Priorities 12. This project is critical in delivering Improvement statement 1, to decrease the tonnage of biodegradable waste and recyclable products going to landfill, enabling the diversion of waste from landfill to treatment facilities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Waste PFI UpdateAppendix 1 17 KB Download
PDF
Waste PFI: Updated Outline Business CaseReport 68 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
SG
Councillor Steve GallowayChair, present
SG
Councillor Susan GallowayCommittee Member, present
CJ
Councillor Ceredig Jamieson-BallCommittee Member, present
QM
Councillor Quentin MacdonaldCommittee Member, present
KO
Councillor Keith OrrellCommittee Member, present
AR
Councillor Ann Reid MBECommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
SS
Councillor Susan SunderlandCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. Waste PFI – Updated Outline Business CaseThis decision
  2. Waste PFI UpdateNoted
  3. Waste PFI UpdateDecided
  4. Waste PFI - Update on Approach to Procurement and Sites PlanningApproved
  5. Waste PFI - Update on Approach to Procurement and Sites PlanningDecided
  6. Waste PFI - Updated Outline Business CaseDecided

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies