(i) That the results of the work completed to date by Internal Audit to prepare the 2006/07 be noted; (ii) That the results of the follow up review of the 2005/06 action plan be noted. REASON:(i) To enable Members to consider the adequacy and effectiveness of the Council’s control environment; (ii) To ensure Members are aware of the progress which has been made to address previously reported significant control issues.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Assistant Director (Audit and Risk Management)
2006/07 Statement of Internal Control
Summary 1 The purpose of this report is to provide Members with details of the progress which has been made;
• to prepare the 2006/07 Statement of Internal Control (SIC) (which is to be published with the Statement of Accounts).
• to address the significant control issues identified in the 2005/06 SIC;
• by each Directorate to date to rectify control weaknesses, as declared in their individual control self assessments.
Background 2 As reported to the last meeting of this Committee (on 31 January 2007), the Accounts and Audit Regulations 2003 imposed a legal requirement on all local authorities to publish a SIC as part of their Statutory Accounts. The purpose of the SIC is to demonstrate and/or provide;
a) openness and accountability to the public;
b) assurance to stakeholders;
c) a framework for improving the adequacy and effectiveness of corporate governance arrangements;
d) evidence for CPA.
3 CIPFA has previously issued guidance on the process which needs to be followed to prepare the SIC (including the need to establish, maintain and review the systems of internal control). The guidance also prescribes the form and content of the SIC. The Council’s 2005/06 SIC fully complied with the CIPFA guidance and the process which was followed resulted in ten significant control issues being identified. 2006/07 SIC
4 There is now a well established process within the council to prepare the SIC. A key element of the process is the review of the Council’s governance arrangements and systems of internal control. This review includes a requirement for each Directorate to complete a self assessment of the key controls within their respective areas. Each Director must then complete and sign a Directorate Assurance Statement, using the information obtained from the review of key controls and associated evidence. The S151 Officer and Monitoring Officer must also complete and sign disclosure statements. The review process will also take account of the Chief Internal Auditor’s opinion on the overall adequacy and effectiveness of the Council’s internal control environment. In addition, Internal Audit will review other documentary evidence to identify possible control weaknesses (for example, internal and external audit reports and other inspection reports).
5 The Officer Governance Group will evaluate any control issues identified through the review process and consider which should be disclosed in the SIC as significant control weakness. A control weakness will be considered to be significant where;
a) the issue has seriously prejudiced or prevented achievement of a principal Council aim or objective;
b) the issue has resulted in a need to seek additional funding to allow it to be resolved, or has resulted in a significant diversion of resources from another aspect of the Council’s services;
c) the issue has led to a material impact on the accounts;
d) the Audit and Governance Committee has advised that it should be considered significant for this purpose;
e) the Chief Internal Auditor has reported on it as significant in the annual opinion on the Council’s internal control environment;
f) the issue, or its impact, has attracted significant public interest or has seriously damaged the Council’s reputation;
g) the issue has resulted in formal action being taken by the S151 Officer and/or the Monitoring Officer.
6 At the last meeting of this Committee it was agreed that;
a) the period of time allowed for consulting on the draft SIC, prior to it being reported to Members, should be extended (see the list of key dates below). b) Members should be invited to contribute to the review process itself by identifying control weaknesses and other governance issues for possible inclusion in the SIC.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.