Resolved
Advice of the Advisory Panel That the Executive Member be advised to: (i) defer the report to the meeting in October Decision of the Executive Member
Corporate Services and Advisory Panel deferred this item on Tuesday 11 September 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Advice of the Advisory Panel That the Executive Member be advised to: (i) defer the report to the meeting in October Decision of the Executive Member
1 The purpose of this paper is to inform Members of the progress made in implementing and deploying the Supplier and Contract Management System (SCMS) at City of York Council in particular:
a. an overview of the purpose and functionality of the system
b. progress in its delivery across the organisation
c. the development and project plan
Background 2 SCMS is a regional (Yorkshire & Humberside) web based supplier and contract management system. Funding for the system has been provided by the Regional Centre of Excellence for the five year period 2006 – 2011. The system is currently available to all 22 Councils in the region with future plans to extend it to other public service contracting bodies i.e. Police and Fire Service.
3 The system is designed to replace any existing procurement information systems/registers that may be in use across the region. While the system is not mandatory all Council’s are being encouraged to use it.
4. The introduction of SCMS at York provides for the first time the opportunity to have a fully populated contracts register providing both inward and outward facing information. This will encourage a more strategic view to be taken on how goods, works, and services are procured across the organisation helping us to achieve the aspirations of the National Procurement Strategy and Gershon efficiency agenda. The public access element of the system should also reduce the number of FOI (Freedom of Information) enquiries dealt with by the team on an annual basis. The system once fully embedded should be complementary to the new FMS (Financial Management System) and ensure a fit for purpose 21st century procurement environment at the Council.
SCMS Overview and functionality 5. The system comprises three separate but interrelated modules:
Supplier Management: The supplier management module allows suppliers to self-register with one, many or all Council’s. Suppliers can maintain their own company profiles and an on-line generic prequalification questionnaire (PQQ) is under development, which will allow suppliers to apply for approved list status with all Council’s. The flexibility of the system allows administrators to inform Client officers of actions they may need to take with registered suppliers i.e. provision of insurance renewal documents. Equally the module enables the Council to recruit, administer, monitor & report on suppliers. All relevant documentation with regard to suppliers can be held against their profile. The holding of all supplier information in a single database should deliver efficiencies to the Council in terms of supplier administration
Tender Management: The tender management module is an electronic tendering system that can be used for tenders both above and below the EU thresholds. It allows for the creation of workflow tasks with assigned actions and reminders. This module provides a platform for the buyer to manage a procurement exercise that is compliant with best practice, financial regulations and OJEU (Official Journal of European Union) requirements. This module will allow us to make administrative efficiencies across the organisation through the use of the resource planning tool, standard documentation and at the same time facilitate statutory compliance.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SCMS Annex 1 SCMS Project PlanAppendix | 16 KB | Download |
PDF |
Supplier & Contract Management System (SCMS)Report | 51 KB | DownloadRead as text |
Follow Corporate Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jan 2009 | MinutesThat the minutes of the meeting held on 9 December 2008 be approved and signed by the Chair and Executive Member as a... | Approved | Open |
| 20 Jan 2009 | Forward Plan Update(i) That the arrangements for dealing with write-offs be delegated to the Head of Finance in consultation with the Ex... | Decided | Open |
| 20 Jan 2009 | Resources Budget ProposalsAdvice of the Advisory Panel That the Executive Member be advised: (i) That the budget proposals were in line with th... | Noted | Open |
| 20 Jan 2009 | Resources Directorate PlanAdvice of the Advisory Panel That the Executive Member be advised: (i) That the for 2009-2010 be approved. (ii) That ... | Approved | Open |
| 9 Dec 2008 | MinutesThat the minutes of the meeting held on 21 October 2008 be approved and signed by the Chair and Executive Member as a... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.