Leisure, Culture and Social Inclusion and Advisory Panel agreed this item on Friday 19 October 2007. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised to: · Note and comment upon the performance of the York Museums Trust · Agree to the application of the Council’s capital as set out in paragraph 15 of the report · Recommend that the Executive considers the trust’s request for £250k of prudential borrowing in order to fund the balance of the Hospitium scheme Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Leisure, Culture and Social Inclusion and Advisory Panel
Meeting of the Executive Member for Leisure and 19 October 2007 Culture and Advisory Panel
Report of the Assistant Director (Lifelong Learning and Culture)
YORK MUSEUMS TRUST PARTNERSHIP DELIVERY PLAN: PERFORMANCE UPDATE
Summary 1. This report updates members on the progress of the York Museums Trust (YMT) towards meeting the targets agreed in the Partnership Delivery Plan.
Background 2. The Partnership Delivery Plan (PDP) approved by members in December 2002 outlined the key targets and objectives which the Council requires YMT to work towards over the next five years. Members have asked for regular updates on progress. Reports are brought to EMAP at the half-year point and also in May, to report on full year performance. This report covers the period April 2007 to September 2007.
3. The update report is set out in Annex 1.
Capital Issues 4. Issues have arisen concerning the application of the agreed capital programme. The Art Gallery Roof: 5. A serious problem has arisen at the Art Gallery with the roof over the south gallery. Significant amounts of plaster from the original ceiling have fallen onto the top of the modern suspended ceiling. Fortunately, the suspended ceiling has held, containing the fallen material, although the lighting has been put out of action. The gallery has had to be closed in the interests of health and safety. A survey has been undertaken of the three bays within the south gallery and it is understood that the effects of age and condensation mean that the entire ceiling will need to be renewed.
6. In the property leases, including that for the Art Gallery, the Council retains liability for any major failures to roofs and external walls. Major failures are defined as those where the cost of the repairs is greater than £25k and which prevent YMT from reasonably carrying on their business at the premises. (All other categories of repair and maintenance are the responsibility of the Trust.) 7. YMT have engaged architects to draw up a scheme to replace the ceiling. The cost is likely to be in the region of £200k. This will be a call on the Council’s allocated capital programme.
8. YMT will progress the scheme as rapidly as possible having first obtained landlord’s approval for the detailed scheme once it is drawn up.
The Hospitium: 9. The cost of the Hospitium project is now estimated to be £450k. The Council has already agreed to contribute £200k of this through the agreed capital programme. YMT had originally intended to borrow the balance from its bank. However, it is now proposed that the Council should use its prudential borrowing facility in order to borrow the balance on behalf of YMT. This will ensure that YMT obtains the necessary capital at the lowest possible interest rate.
10. The business plan for operating the Hospitium as a conferencing facility shows that it has the potential to generate income of £130k p.a. which will comfortably support the proposed level of borrowing and annual repayments, which are estimated at £35k-£40k pa over a 5 year period. The benefit to the Council lies in improvement to one of its capital assets as well as in the improvement to the financial position of YMT. YMT aim to begin the work at the end of this month.
11. It is proposed to transfer the risk of the borrowing to YMT by deducting the cost of the loan repayments from the Council’s grant to YMT.
The Heritage Lottery Fund Bid 12. Discussions have taken place with the Heritage Lottery Fund (HLF) regarding YMT’s bid in respect of the Yorkshire Museum and Gardens. On the advice of the HLF YMT has decided to resubmit its bid in March next year. The effects of this on the profiling of the capital are set out below. The revised submission will need to take account of the reduced Council capital available in the light of the need to repair the Art Gallery roof.
Consultation 13. This report is for information and there is no consultation to consider.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Leisure, Culture and Social Inclusion and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Explore York - Library Learning Centre.Advice of the Advisory Panel That the Executive Member be advised to: (i) Agree to the budget subject to the approval...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.