Customer and Corporate Services Scrutiny Management Committee agreed this item on Monday 22 October 2007. Below is the council's own wording, with the papers it was decided on.
That it be agreed not to proceed with a review of the topic on drainage in York at the present time, and Cllr Moore be advised that a new registration form could be submitted following the consideration of the officer review report at Neighbourhood Services EMAP. REASON: Given that any scrutiny review of this topic would be premature, pending the findings emerging from the existing officer review and the work being done to respond to the Council motion.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Customer and Corporate Services Scrutiny Management Committee
Scrutiny Management Committee 22 October 2007
Drainage in York– Feasibility Study
Summary 1. In September 2007 Cllr Richard Moore registered a proposed new scrutiny topic on the subject of drainage in York. A copy of the topic registration form is enclosed at Annex A.
Criteria
2. Public Interest – there was media interest after the heavy rain in June 2007, but not the concentrated reporting that followed serious flooding in other parts of Yorkshire. Members must consider whether or not there is still strong public interest in the subject.
3. Corporate Priorities for Improvement -This topic does not obviously fit with any of the Corporate Priorities for Improvement – members need to consider what their view is on this.
4. National, local or regional significance – incidences of flooding, if severe, could be considered to be of local and regional significance.
5. Under performance or service dissatisfaction – after the heavy rains of 25 June there were 46 reports of flooding on the highway, 42 reports of blocked gullies, 12 cases of sandbags being required, 13 reports of flooding almost entering properties and 5 reports of flooding entering properties. There were also reports from seven elected members of incidences of flooding or blocked drains from residents in their wards.
6. Level of risk – so far as is known there are no risks which could be alleviated by the investigation of this topic,
7. Service efficiency –so far as is known there are no aspects of service efficiency which would benefit from this review being carried out. Consultation
Relevant Member Consultation
8. Political group leaders and relevant officers were asked to comment on the feasibility of carrying out this scrutiny review.
9. The Leader of the Liberal Democrat Group had not responded at the time of writing.
10. The Leader of Labour Group wants to register his sympathy with York residents who have suffered as a result of the flooding, but does have concerned that this scrutiny topic can achieve its objectives. His main concerns are:
a. Much of the Scrutiny involves organisations which CYC have no ability to question or influence. They may not co-operate with us productively or even not at all.
b. The information he has indicates that the flooding was of such a nature that no matter how good the drainage was it could not have been sufficient to meet the demands that were called upon it on this occasion.
c. The proposed scrutiny does not take matters much further than the motion approved at Council on 4 October (see below).
11. The Leader of the Conservative Group is of the opinion that the motion agreed at Council (see below) on 4 October 2007, and the programme of work being carried out by the Drainage Team, already commits CYC to the issues requested in this scrutiny topic registration. There is therefore no requirement for a scrutiny review to be commissioned.
12. The Leader of the Green Group, Cllr Andy d’Agorne, welcomes this proposal.
13. If any further responses are received from the Leaders these will be reported at the meeting.
Relevant Officer/External Consultation
14. The supporting Scrutiny Officer has held discussions with the Head of Engineering Consultancy and his colleagues in City Strategy.
15. They report that the request in this topic registration for an examination of the events of June 2007 is already taking place. In June 2007 the rainfall was above the design criteria for the sewerage system – it was recorded as the wettest June on record. In many of the weather stations in Yorkshire the rain that fell in June this year was between 300 and 450 per cent of the average rainfall that had fallen in the last 30 years.
16. The exceptionally heavy rain of 24-25 June fell onto ground that was already exceptionally wet. This would affect the ability of the ground to absorb the water and mean more was attempting to enter the sewerage system.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customer and Corporate Services Scrutiny Management Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.