Executive - for meetings from 03/06/00 to 26/04/11, Tuesday 4 December 2007 at 2.00pm

Reducing the Maintenance Backlog

Agreed Executive 4 papers

Executive - for meetings from 03/06/00 to 26/04/11 agreed this item on Tuesday 4 December 2007. Below is the council's own wording, with the papers it was decided on.

Item117

Resolved

(i) That Option A be agreed and the 10-year Corporate Repair and Maintenance Strategy with performance indicators, detailed at Annex 1 to the report, be approved. REASON: So that a co-ordinated approach to dealing with a backlog of maintenance and future repair and maintenance, based upon need and the viability of the assets, is followed. (ii) That, during the annual budget build process, the appropriate level of annual revenue and capital repair and maintenance resources to assign, in order to ensure the achievement of the objectives and priorities set out in the Strategy, be considered. REASON: To ensure that the Strategy is effective and achievable within the 10-year timescale. (i) That Option A be agreed and the 10-year Corporate Repair and Maintenance Strategy with performance indicators, detailed at Annex 1 to the report, be approved. REASON: So that a co-ordinated approach to dealing with a backlog of maintenance and future repair and maintenance, based upon need and the viability of the assets, is followed. (ii) That, during the annual budget build process, the appropriate level of annual revenue and capital repair and maintenance resources to assign, in order to ensure the achievement of the objectives and priorities set out in the Strategy, be considered. REASON: To ensure that the Strategy is effective and achievable within the 10-year timescale.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Executive 4 December 2007

Report of the Corporate Landlord

Reducing the Maintenance Backlog

Summary 1 This report sets out a strategy for using the limited revenue and capital resources available to deal with the substantial repair and maintenance backlog of the council’s corporate land, buildings and highways by basing decisions on future investment on the need and viability of the asset.

2 Members are asked to

• Note the contents of the report

• Approve the 10 year Repair and Maintenance Strategy summarised in the report and detailed at Annex 1

• Agree the proposed performance indicators contained in the strategy

• Consider the appropriate level of annual revenue and capital repair and maintenance budgets to ensure the objectives and priorities set out in the Repair and Maintenance strategy are achieved.

Background 3 Annex 2 sets out the current levels of outstanding repair and maintenance for the main service areas within the council. Although these have reduced slightly from the levels of a few years ago they are still very high.

4 The main reason for this is that repair revenue budgets are limited and often only sufficient to deal with urgent repairs on a needs basis rather than an overall co-ordinated and planned programme.

5 In recent years, following the production of Corporate and Service Asset Management Plans, Capital budgets have been allocated to deal with this issue. Examples of these include

• Decent homes/modernisation funds

• LTP Structural Maintenance

• Funding to replace/modernise schools • Council’s Capital Programme – over £1.5m to address repairs and accessibility

6 These capital funds have been allocated by an audit of condition, consultation with service managers and expenditure on those assets which are needed to continue to deliver the service. However there has been no overall structured approach across the Council.

7 With limited revenue and capital funds the Council has nevertheless been active in seeking to reduce the outstanding repair backlog by adopting a variety of approaches in addition to the ongoing repair and maintenance programmes. Annex 3 details a selection of the major projects that have been undertaken in recent years, are being done currently and that which is planned for the future. These can be grouped as follows (with a few examples of each)

Externally funded projects

- The provision of new schools through the PFI project

- The Housing Modernisation Programme

- The major schemes at York High School, Manor School and Joseph Rowntree School

Re-provision of services/accommodation in self-funded new buildings

- The Administrative Accommodation Project replacing the existing portfolio with a new Council Headquarters at Hungate.

- The swimming pools programme for replacement and refurbishment of facilities

- New starter business units replacing unsuitable existing facility at Parkside

Rationalisation of buildings as a result of Service Asset Management Planning

- The sale of De Grey House and Rooms

- Future sale of Yearsley Bridge and Huntington Road Day Centres

- Disposal of Hebden Rise Day Centre

Other

- Transfer of assets to community groups etc. on full repairing leases

- Ensuring commercial and other tenants comply with repairing terms in leases 7 There is now a need to develop a strategy which provides overarching principles to deal with all council land and property assets which can then be applied to service and corporate revenue and capital budgets to ensure Best Value is obtained.

Why is a Repair and Maintenance Strategy Needed?

8 • To assist the council in delivering its corporate priorities – e.g. improve the condition appearance of streets and buildings, quality of affordable homes, and deliver efficiencies.

• To meet CPA requirements.

• To reduce Corporate Risks - prevent unsustainable spending - reduce backlog - reduce risk of service failure - improve image and reputation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 53 KB Download
PDF
Appendix 2Appendix 2 25 KB Download
PDF
Appendix 3Appendix 3 17 KB Download
PDF
Reducing the Maintenance BacklogReport 50 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
SG
Councillor Steve GallowayChair, present
KA
Councillor Keith AspdenCommittee Member, present
SG
Councillor Susan GallowayCommittee Member, present
CJ
Councillor Ceredig Jamieson-BallCommittee Member, present
AR
Councillor Ann Reid MBECommittee Member, apologies
CR
Councillor Carol RuncimanCommittee Member, present
SS
Councillor Susan SunderlandCommittee Member, present
CV
Councillor Christian VassieCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. Reducing the Maintenance BacklogThis decision
  2. Reducing the Maintenance BacklogDecided

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies