Housing and Adult Social Services Capital Programme 2007/08 Monitor 2

Approved Committee 3 papers

Housing and Adult Social Services Advisory Panel approved this item on Monday 10 December 2007. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

Advice of the Advisory Panel That the Executive Members be advised to: i) Note progress on the various schemes; ii) Approve the variations listed in tables 1,2,3, and 4 of the report; iii) Note the minor variations made under officers delegated authority; iv) Agree to the Buy-Back and disposal of 2 Barmby Close as recommended in paragraphs 13 to 15 of the report; v) Recommend the variation in table 1 (Repairs to Local Authority Properties) to the Executive. Decision of the Executive Members
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Housing and Adult Social Services Advisory Panel

Meeting of the Executive Members for Housing and Adult Social Services and 10th December 2007 Advisory Panel Report of the Director of Housing and Adult Services

Housing and Adult Social Services Capital Programme 2007/08 Monitor 2

Summary 1. This report presents the second quarter review of the 2007/08 Housing and Social Services Capital Programmes and the resources available to support them. The report also recommends that the Executive Members approve the variations.

Background 2. The approved Housing Capital Programme for 2007/08 is £9,453k with £4,656k funded through the MRA, the approved Social Services Capital Programme for 2007/08 is £646k of which £311k is funded from grant income to give a net programme of £335k. Annexes 1 and 2 set out the relevant detailed cost centres

3. Staff have reviewed the programme of investment projects during the first half of 2007/08 and the resources needed to fund them. Any minor variations have been agreed within delegated powers.

Consultation 4. There has been no consultation carried out to produce this report.

Options 5. As this report is for information, no options have been included.

Analysis – Housing Capital Programme 6. Modernisation of Local Authority Homes, there have been minor variations resulting in an underspend of £18k, this is due to underspends of £13k on asbestos and £5k on demolition. 7. Table 1. Repairs to Local Authority Properties,

Scheme Approved Revised (Under)/Overspend Slippage into Budget Costs 2007/08 2008/09 2007/08 2007/08 £k £k £k £k Re roofing 521 192 (329) 329 works Installation and 1,204 1,571 367 Replacement of Heating Systems Total 1,725 1,763 38 329

8. There is a major variation resulting in a projected increase in expenditure of £367k within the Installation and Replacement of Heating Systems project. This is resulting due to large numbers of predominantly old Back Boiler units failing their annual gas service. This issue has increased since first quarter review however the servicing project is now in the latter stages. These boilers are predominantly due for replacement within the current 4 year capital programme and hence this work is not additional to the programme but is simply being brought forward into a larger 2007/08 project. A number of additional operational processes have been brought into place to monitor and manage this process to its optimal minimum.

9. To fund this increase in heating costs it is recommended to reduce the roofing budget within 2007/08 to balance this years capital programme with a complimentary increase in the roofing project next year so that the 2 year roofing spend remains balanced. In practical terms as the roofing contract has not begun this will mean running it between January and June rather than January and March.

10. There is also a minor variation resulting in a reduction of projected expenditure of £51k, this is the affect of reductions of £15k on Structural Works and £38k on Communal Access Flooring and an increase Security Lighting of £2k.

11. Table 2 Assistance to Older and Disabled People,

Scheme Approved Budget Revised Costs (Under)/Overspend 2007/08 2007/08 2007/08 £k £k £k Discus Bungalows 120 10 (110) Total 120 10 (110)

12. The Discus Bungalow budget was to provide disabled adaptations for those customers relocating permanently from the bungalows, less residents have currently relocated than the budget provision predicted hence an underspend of £110k has arisen.

13. Table 3. Miscellaneous,

Scheme Approved Budget Revised Costs (Under)/Overspend 2007/08 2007/08 2007/08 £k £k £k Buy-Back Scheme 0 100 100 Total 0 100 100

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme MonitorAppendix 1 46 KB Download
PDF
Capital Programme MonitorAppendix 2 22 KB Download
PDF
Housing and Adult Social Services Capital Programme 2007/08 Monitor 2Report 50 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
CH
Councillor Christopher HoggChair, present
SG
Councillor Susan GallowayCabinet Member, present
SS
Councillor Susan SunderlandCabinet Member, present
DB
Councillor Denise BowgettCommittee Member, present
SF
Councillor Sandy FraserCommittee Member, present
DH
Councillor David HortonCommittee Member, present
DT
Councillor Dave TaylorCommittee Member, present
SW
Councillor Sian WisemanCommittee Member, present
MG
Mrs Mildred GrundyCo-opted Non-Statutory Member, absent
PH
Ms Pat HolmesCo-opted Non-Statutory Member, absent

On this subject at York

Search all
  1. Housing and Adult Social Services Capital Programme 2007/08 Monitor 2This decision
  2. Appointment of the Interim Corporate Director for Health, Housing and Adult Social CareApproved
  3. Appointment of Interim Corporate Directors for Health, Housing & Adult Social Care and Children's, Education and Communities. Appointment of Permanent Corporate Directors for Health, Housing & Adult Social Care and Children's, Education and Communities.Approved
  4. Attendance of the Cabinet Member for Health, Housing and Adult Social Services.Noted
  5. Attendance of the Cabinet Member for Health, Housing and Adult Social ServicesNoted
  6. Attendance of the Cabinet Member for Health, Housing and Adult Social Services.Noted

More from York Housing and Adult Social Services Advisory Panel

All decisions
MeetingDecisionOutcome
16 Mar 2009 Exclusion of Press and PublicThat the Press and public be excluded from the meeting during consideration of Annex 1 to agenda item 10 (External Pa... Decided Open
16 Mar 2009 MinutesThat the minutes of the meeting held on 27 January 2009 be approved and signed by the Chair and Executive Member as a... Approved Open
16 Mar 2009 2008/9 Service Plans and Budget 3rd Monitor ReportAdvice of the Advisory Panel That the Executive Member be advised to note and comment on the content of this report D... Noted Open
16 Mar 2009 Housing and Adult Social Services Capital Programme – Monitor 3Advice of the Advisory Panel That the Executive Member be advised to note the progress on schemes and approve the var... Noted Open
16 Mar 2009 Former Tenants Arrears – Write offAdvice of the Advisory Panel That the Executive Member be advised to approve Option 2, which involves writing off FTA... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies