Derwenthorpe - Amendments to the 'Agreement for Sale' and 'Framework Agreement'
ApprovedExecutive1 paper
Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 11 March 2008. Below is the council's own wording, with the papers it was decided on.
That Option 3 be approved, as set out in paragraph 5 of the report, and the necessary amendments be made to the ‘Agreement for Sale’ and the ‘Framework Agreement’ between the Council and Joseph Rowntree Trust. REASON: In order to make progress on this important project. That Option 3 be approved, as set out in paragraph 5 of the report, and the necessary amendments be made to the ‘Agreement for Sale’ and the ‘Framework Agreement’ between the Council and Joseph Rowntree Trust. 1 REASON: In order to make progress on this important project.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 11 March 2008
Report of the Director of City Strategy
Derwenthorpe – Amendments to the “Agreement for Sale” and “Framework Agreement” Summary 1. In October 2002 the council entered into an “Agreement for Sale” and an accompanying “Framework Agreement” with the Joseph Rowntree Housing Trust (JRHT) relating to land in the council’s ownership at Osbaldwick. In the intervening period and following a public inquiry JRHT have gained planning permission for 540 homes on the site and have recently had a reserved matters application approved on phase 1 of the development.
2. As a result of the length of time it has taken to progress this development a number of issues have arisen which require amendments to be made to the original agreements, both from the council’s and JRHT’s points of view. The purpose of this report is to seek Member approval for these proposed changes to allow the sale to go ahead and the development to proceed.
Background 3. The council and JRHT have been working together to realise the development of a highly sustainable community focussed development at the land north of Osbaldwick village for over 10 years. Planning permission for the development of 540 homes was granted in May 2007 on the site now named Derwenthorpe. The proposed development has been subject to widespread public consultation and participation throughout with an informal three way partnership between JRHT, the council and the community. Within this partnership the relationship between JRHT and the council was formalised by means of a Framework Agreement which sets out the responsibilities of the partners and the vehicle for involving the community.
4. Alongside the above agreement there is also an Agreement for Sale between the council and JRHT in which JRHT contracts to buy the council’s land subject to gaining access to the site from the required four directions and also subject to gaining planning approval. In return the council is guaranteed a payment of £5.575 million and 100% of the next £2 million of overage (assuming there is overage) and 50% of all subsequent overage. Proposals 5. There have been a number of issues that have arisen over the period since the Agreement for Sale and the Framework Agreement were signed by the council and JRHT in October 2002. These have resulted in the need to amend the current agreements and it is proposed to do this by supplemental agreements which will address the following:-
Changes requested by JRHT
• Changes of terminology in relation to the Community Consultative Panel and the New Osbaldwick Committee being replaced by the Partnership Committee as required under the terms of the Section 106 Agreement.
• Extending the period for the satisfaction of the conditions precedent to allow for the Village Green application to be resolved (the original period ran out in October)
• Adding a new condition precedent to the sale agreement, namely that the Village Green application would be disposed of without there being a Village Green registered (or if part of the site was registered only a part that JRHT are willing to accept).
• Altering the terms of the Sale Agreement so it permits JRHT to “self develop” individual phases rather than requiring them to tender each phase for sale to housebuilders.
Changes that the council wish to be addressed
• A tightening of the agreement to ensure that there is a clear and express obligation on JRHT to seek to maximise the profits made from the development and thus to maximise the overage paid to the council.
• Further revision to the structure of the overage provisions to:
o Be prescriptive in requiring a sale or development and imposing a timetable for it.
o Provide a mechanism whereby the council may elect to call for an interim payment after sales of parts of the site and for a final payment at a defined longstop date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.