Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 6 May 2008. Below is the council's own wording, with the papers it was decided on.
That Option 1, which involves in-sourcing the gas servicing work, be approved and that the Housing Repairs Partnership be amended to include the whole of the gas servicing for the City. REASON: To secure service quality and value for money on behalf of the Council’s tenants. That Option 1, which involves in-sourcing the gas servicing work, be approved and that the Housing Repairs Partnership be amended to include the whole of the gas servicing for the City. 1 REASON: To secure service quality and value for money on behalf of the Council’s tenants.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Meeting of the Executive 6th May 2008
Report of the Director of Housing and Adult Social Services
Gas Servicing - Future Procurement.
Summary 1. To provide the Executive with details of the recent procurement exercise undertaken and suggested future direction for the gas servicing and maintenance works to council dwellings.
2. To agree the amended repairs partnership Service Level Agreement (SLA) which details the framework and performance standards of the partnership ensuring that this approach will improve the quality, productivity and cost of the service to customers and the Council.
Background 3. In November 2003 the Housing Executive Member agreed a two-fold approach for gas servicing with an external contractor undertaking all works in the City area and Neighbourhood Services (NS) undertaking all works in the Acomb area under a partnering agreement based on the contract specification for the external contract. The external contract expired on March 31st 2008 and hence this report presents the future direction.
4. The vast majority of all other responsive maintenance type repairs are carried out by NS under the Housing Repairs Partnership agreed by the Executive in November 2004. This partnership was established to remove the traditional adversarial roles of client and contractor and promote a joint responsibility by both parties for the success of the partnership. This change has fostered a close working relationship that has made significant strides of improving performance to customers whilst reducing duplication in processes and also the management structure. This Partnership is based upon a charging mechanism of the actual cost to the authority of the works and does not include any profit.
Procurement Hierarchy 5. The procurement options for the gas servicing works have been assessed against the Council’s Service Procurement Hierarchy, as set out in the Rollo Report ‘A Strategy for Assessing Service Procurement Options’ which members have previously approved as the procurement framework for the council, with a recommendation on placement of the service at Level Two – existing provider with Improvement Plan.
6. The strategy for assessing this procurement option not only reflects Best Value principles but also looks beyond individual reviews and services to consider an overall view in order to obtain the best possible result for the Council and its customers. Based upon this strategy compliance with the ‘Rollo’ Report was sought in its guiding principles of transparency, robustness, control and ownership, customer focus, flexibility, affordability, deliverability, and corporate issues.
7. In line with the policy, if the recommended option is approved, the council will be choosing not to either, renew the current external contract for the provision 60% of this service, or undertake a fresh tendering process, or procure services from the existing framework, choosing instead to develop its own existing in-house service to provide 100% of the supply required. If the recommendation is approved, the councils will not be tendering the works therefore there is no legal obligation to competitively tender the service, however we must be mindful of best practice/VFM issues when satisfying ourselves of the 'competitiveness' of our in- house provision.
8. When considering the predicted future level of service, the gas servicing works have been evaluated against a range of key service criteria; acceptable price, acceptable quality, high customer satisfaction and capacity for continuous improvement. In addition to these service criteria consideration has been given to the number of contractors / service providers to engage to deliver this vital service. Officers have reached the view that it would be in the interests of the council and its customers to have a single service provider.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.