(i)That the comments received on the Issues and Options documents be noted and their consideration in informing the Preferred Options stage for the Area Action Plan be supported; (ii) That the progress made to date on production of the Area Action Plan be noted and the approach for the development of the Preferred Options stage of work be agreed. (iii) That officers be thanked for all the work done during the consultation process on the Issues and Options report. REASON: To ensure that the Area Action Plan could be progressed to the next stage of work, in accordance with the Local Development Scheme. To ensure that Members views were included in the generation of Preferred Options put forward.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of the Local Development Framework 13 May 2008 Working Group Report of the Director of City Strategy
YORK NORTHWEST AREA ACTION PLAN Progress Report, incorporating Issues and Options Consultation Summary Summary
1. This report reviews progress to date on the York Northwest Area Action Plan, and gives an overview of comments and headline results arising from consultation on the Issues and Options Report between November 2007 and January 2008. Members are asked to note the progress to date and the use of the consultation findings to inform the preparation of the Preferred Options. Members are further asked to agree the approach and programme for the preparation of the Preferred Options, which are also set out in this report.
Background 2. The Area Action Plan (AAP) for York Northwest will be one of a suite of Development Plan Documents in the Local Development Framework. The AAP will be used to guide and control the development of this major area of change. The timetable for preparation of the AAP was agreed at a meeting of the Executive on 27 February 2007 and has been incorporated into the Local Development Scheme (LDS).
3. At a meeting of the Executive on 25th September 2007 Members agreed the content of the Issues and Options report, the preparation of associated documents and for public consultation to take place.
Progress Report Progress to Date
4. Good progress has been made on the initial Issues and Options stage of producing the Area Action Plan. Programme milestones identified in the Local Development Scheme have been met, with issues and options consultation carried out between November 2007 and January 2008.
5. A range of evidence base documents, including both city wide studies and specific York Northwest studies have informed the preparation of the Area Action Plan to date. Outstanding evidence base studies are now also well advanced; it is anticipated that the councils Retail Capacity Study will be reported to members in June, the PPG17 Open Space Study in July, and the Employment Land Review in September 2008. Other work, including transport modelling, specific retail work and a specific York Northwest Open Space Study is also being progressed. Viability assessment work will be required on the emerging Preferred Options to ensure deliverability considerations are addressed.
6. Transport modelling will look at the infrastructure required to accommodate general growth in the city and the additional infrastructure needed to deliver development of York Northwest. The work will inform the development of a tool to allocate costs of infrastructure to different stakeholders and mechanisms for securing funding. The Council is also progressing a number of transport initiatives which will inform the transportation requirements and funding for the Area Action Plan, including, Access York (park and ride and outer ring road projects), new growth point infrastructure bid, cycling city status, tram train and the Hopgrove roundabout.
Stakeholder Activity
7. York Central stakeholders are making progress in a number of areas in anticipation of seeking approval from their various boards to enable the site to be marketed. It is hoped that a developer will be appointed in advance of the Councils Preferred Options consultation, which will enable developer involvement in the plan making process as early as possible. Preferred Options Consultation is scheduled in the Local Development Scheme for January 2009.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.