(i) That the responses provided to Members’ questions be accepted. (ii) That, nevertheless, the Committee remains concerned about the relatively small retention sum for the project and the arrangements for business continuity in the event of the loss of any senior members of the project team. 1 REASON: In the interests of effective management of one of the Council’s major projects.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Assistant Director (Property Services)
The New Council HQ – response to questions posed by the A&G Committee
Summary 1 This report responds to a number of questions raised by the A&G Committee relating to the contract management arrangements for this major council project.
Background 2 At its meeting 13 May 2008 members of the Audit & Governance meeting agreed that the Assistant Director: Property Services should be invited to the June meeting of the committee to answer specific questions of concern regarding the contract management of the New Council HQ project. These are:
a. the form of contract.
b. the provisions for variations, claims, arbitration and bonding;
c. the extent of nominated suppliers and nominated sub-contractors;
d. business continuity in the event of business failure by the main stakeholders;
e. business continuity in the event of the loss of the project leader
f. arrangements for member steering and the regularity of reports.
g. re-confirmation that the project still meets the governance criteria of the best solution, at the right time and at the best cost for residents
Information 3 The response to each question is as follows:
4 a) the form of contract.
The form of contract will be the Engineering Construction Contract Option D (Target Contract will Bills of quantities). This form of contract is endorsed by the (Office of Government Commerce) as the contract satisfies the Achieving Excellence in Construction (AEC) principles.
The contract was developed in the late 1980s to stimulate a fundamental change in the civil engineering design and construction. The second edition was published as a response to Sir Michael Latham’s report ‘Constructing the Team’ (1994). Recently, this form of contract has become widely used by employers, contractors and consultants wishing to embrace the principles of partnering envisaged in ‘Constructing the Team’.
The current version of the contract embraces good project management tools such as:
risk registers
collaborative discussions to mitigate problems and risk
clear division of function and responsibility
and key performance indicators.
This should result in reduced risk to an employer of cost and time overruns and of poor performance of the completed project. It should also lead to a much increased likelihood of achieving a profit for the contractor and his subcontractors and suppliers.
In addition, prior to selecting this contract we held a workshop with constructors and consultants who CYC have engaged with recently to discuss the merits of this form of contract and alternatives. The workshop agreed that the NEC suite of contracts were appropriate for this and other major projects.
A formal contract will be completed following agreement of the Target Price this autumn. The tendering process completed in late 2006 identified a suitable construction partner who would support the designers in the development of the scheme.
5 b) the provisions for variations, claims, arbitration and bonding?
Clauses do exist within the contract for the above.
The focus of the contract is to resolve disputes before they escalate. If a dispute arises the parties are referred to Adjudication for settlement. Referral to an Adjudicator can occur at anytime during the contract with the emphasis on parties to settle disputes as they arise. Arbitration procedures can only be undertaken following completion of adjudication and is the last result to the settlement of disputes.
Bonds
Currently we do not propose to have a performance bond, though discussions are ongoing to incorporate a parent company guarantee. Some elements of the construction (piling, structural floors – Cobiax, curtain waling) have significant design input from the contractor and his supply chain. Collateral warranties will be agreed with each subcontractor or supplier.
Retention
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.