CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council

Planning Enforcement - Feasibility Report

Agreed Scrutiny 6 papers

Customer and Corporate Services Scrutiny Management Committee agreed this item on Monday 28 July 2008. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

(i) That it be agreed to proceed with the review, commencing in autumn 2008; (ii) That the remit at Annex G of the report be agreed with the following amendments: a) To add the words, “including Section 106 Agreements,” to the end of key objective i.; b) To reword key objective iv. to read, “To review the Council’s processes and procedures to improve the handling of planning enforcement cases”; (iii) That examining the impact of the Powers of Enforcement – Takeaways Scrutiny Review be included in the review; (iv) That the offer of attending a training course, as set out in paragraph 17 of the report, be accepted; 1 (v) That an ad-hoc Scrutiny Committee be established on a 2:2:1 basis, with a Liberal Democrat chair, and nominations be sought from Group Secretaries; 2 (vi) That the timeframe for the review be agreed as 3-6 months. REASON: To progress with a review of the topic.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Customer and Corporate Services Scrutiny Management Committee

Scrutiny Management Committee 28 July 2008

Planning Enforcement – Feasibility Report

Summary 1. This report asks Members to consider a scrutiny topic registered by Councillor Wiseman to scrutinise the resources available to the Planning Enforcement Team and to look at the timescales for completion of enforcement cases. A copy of the topic registration form is attached at Annex A.

Criteria

2. Councillor Wiseman believes that this topic fits with the following eligibility criteria as set out in the topic registration form:

• Public Interest (i.e. in terms of both proposals being in the public interest and resident perceptions) • Under Performance/Service Dissatisfaction. • Service Efficiency

3. The Assistant Director of Planning and Sustainable Development and the Head of Development Control also agree that the topic fits with the above criteria.

4. The portfolio holder for City Strategy did not have any particular comments but believed that most of the questions proposed in this topic could be answered by other means than a scrutiny review and a review would only be necessary if a process issue existed.

Background to Proposed Review 5. Councillor Wiseman wishes this review to explore the possibilities of speeding up the period from opening to closing planning enforcement cases and achieve a reduction in the number of outstanding cases. She has raised concerns that a lack of resources within the Planning Enforcement Team may be contributing to delays in cases being brought to a timely conclusion. As part of the review she also proposes that the Council’s approach to court action is reviewed to investigate concerns that enforcement by City of York Council has little threat of further legal action being taken.

6. Members are presented with information on both ongoing and completed cases at Planning Sub-Committees on a quarterly basis and it is noticeable that the number of ongoing cases is not being reduced. Some cases have been open for a very long time without resolution. There do not appear to be any timescales for completing a case. Whilst Councillor Wiseman is aware that some cases are very complex and need a lot of time there are still too many minor cases (Category C cases [see Annex E]) ongoing and as part of this review she would like to explore possible ways of completing these in a timelier manner.

Consultation 7. Between September 2004 and May 2005, City of York Council’s Environment and Sustainability Scrutiny Board conducted a detailed review into the subject of ‘Powers of Enforcement – Take-Aways’. The findings of this review were signed off by the Scrutiny Management Committee (SMC) at a meeting on 24 October 2005. These findings were subsequently recommended for implementation by the Executive Member for Environment and Sustainability at a meeting held on 9 November 2005.

8. SMC receive regular updates on whether the recommendations of scrutiny reviews have been implemented. Once SMC are happy that all the recommendations have been fully implemented then they will sign them off as complete. An update in relation to the scrutiny review ‘Powers of Enforcement – Take-Aways’ was presented to SMC on 22 October 2007 and again on 26 November 2007 when the Assistant Director (Planning and Sustainable Development) attended to answer questions. The minutes of this meeting record that the recommendations had been implemented and were therefore signed off subject to additional information in relation to recommendations 1 and 2 being provided to Members by e-mail. Recommendations 1 and 2 are set out below.

Recommendation 1 The Environment and Sustainability Scrutiny Board would welcome the positive contribution that the success of the penalty notice support bid would make to addressing these issues.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Topic Registration FormAppendix A 42 KB Download
PDF
Part VII of Town and Country Planning Act: EnforcementAppendix B 73 KB Download
PDF
PPG18Appendix C 24 KB Download
PDF
Enforcement Benchmarking Results 2006: 2007Appendix D 11 KB Download
PDF
Guidelines in realtion to City of York Council's Plannign EnforcementAppendix E 32 KB Download
PDF
Planning Enforcement: Feasibility ReportReport 55 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
JG
Councillor John GalvinChair, present
KA
Councillor Keith AspdenCommittee Member, present
PB
Councillor Paul BlanchardVice-Chair, apologies
DS
Councillor David ScottCommittee Member, apologies
TS
Councillor Tracey Simpson-LaingCommittee Member, present
DT
Councillor Dave TaylorCommittee Member, present
RW
Councillor Richard WatsonCommittee Member, present
IW
Councillor Irene WaudbyCommittee Member, apologies
RM
Councillor Richard MooreSubstitute, present as substitute
CF
Councillor Christina FunnellSubstitute, present as substitute
SW
Councillor Sian WisemanAttendee, in attendance

On this subject at York

Search all
  1. Planning Enforcement - Feasibility ReportThis decision
  2. Planning Enforcement Cases Update (10:14)Noted
  3. Planning Enforcement Cases Update (10:12am)Noted
  4. Planning Enforcement UpdateNoted
  5. Update report on Planning EnforcementNoted
  6. Planning Enforcement Cases - UpdateNoted

More from York Customer and Corporate Services Scrutiny Management Committee

All decisions
MeetingDecisionOutcome
6 Mar 2023 Minutes (5.32 pm)That the minutes of the meeting of the committee held on 9 January 2023 be approved and signed as a correct record. T... Approved Open
6 Mar 2023 City Centre Access (5.41 pm)i. that the ongoing work to improve access to the city centre be noted. ii. That the change to the rules relating to ... Noted Open
6 Mar 2023 Customer Centre Telephone Performance Update (6.48 pm)i. That the report be noted. ii. Call data relating to Housing, Adult Social Care and direct dial calls to officers b... Noted Open
6 Mar 2023 York and North Yorkshire Devolution Update (7.10 pm)that the update be noted. Reason: to ensure the Committee had oversight of the Devolution process. Noted Open
6 Mar 2023 Work Plan (7.29 pm)i. That the Work Plan be noted. ii. That s106 agreements be added to the future Work Plan. Reason: To ensure the Comm... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies