1) That the progress in consultation with young people on the facilities they would like to see be noted, along with the difficulties faced in bringing forward a suitable site in the timescales available. 2) That officers look into an alternative plan of action, including the possibility ... view the full minutes text for item 14.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report of the Assistant Director, Partnerships and Early Interventions
MYPLACE Summary 1. This report provides an update on progress in identifying suitable city centre facilities that could be developed for young people’s use and made the subject of a bid for myplace Government funding.
Background 2. Members will recall that Aiming High for young people: a ten year strategy for positive activities set out the Government’s vision for improving youth facilities in response to clear ongoing demand from young people, parents and communities for more and better places for young people to go. The first tranche of funding available under this strategy has been branded myplace and is being administered by the Big Lottery Fund on behalf of the Department for Children, Schools and Families (DCSF). £190m is available in capital grants of between £1m and £5m. There are two funding rounds at this stage: the first, with a deadline for bids of 30 September, and a second round with a deadline of 31 March 2009.
3. At YPWG’s last meeting in July, Members recommended that the Executive be advised to support a bid for myplace funds. They also advised officers to carry out a wide consultation, to propose two or three alternative sites, and to ensure that the Council develops and maintains partnerships with other organisations to support the bid.
Consultation 4. Over the summer period, extensive consultation was conducted with young people using a variety of techniques. A representative focus group was formed to advise us of the facilities that young people want. Members of this group visited the sites under consideration, and conveyed their views to the Executive Member for Children & Young People's Services and Advisory Panel in September.
5. What rapidly became clear as a result of this consultation was that to be inclusive and available to all young people in the city, any such facilities needed to be located in the city centre, and as close as possible to transport hubs. The young people felt strongly on this point, and this very much influenced our selection of sites on which to focus.
Options 6. After extensive discussions with a wide range of partners, officers were able to identify a possible site close to York Station and on the fringes of the major “York Northwest” development site. Young people confirmed that this site met a number of their “essential” criteria. We were also able to identify a number of suitable partners with whom to pursue the idea.
7. Frustratingly, however, and perhaps inevitably in central York, the site in question also presented a formidable range of difficulties. These included the presence of some existing tenants who would need to be redeployed, as well as a series of planning issues (the site being in a conservation area). For this reason, officers with experience of making successful bids through the Big Lottery Fund advised us that we would be unlikely to be able to submit a compliant bid in time for the first deadline of 30 September. In the end the clinching factor was a communication from the current landowners to the effect that, while they were supportive in principle, they would need more time before they could contemplate putting their own resources into the project, or granting a long lease on the facilities (an essential prerequisite).
8. After due consideration, and with some reluctance, officers decided that it would be better to keep our powder dry for the second bidding deadline of 30 March, rather than submitting a bid now which was likely to be rejected on technical grounds. Bill McCarthy wrote formally to the Big Lottery Fund to this effect. The risk, of course, is that the majority of funds available in the first tranche will have been allocated in the first round of bidding – although we believe that a later bid would increase our chances of attracting private investment into the project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.