It was agreed that the inclusion of the two dates be made. It was noted that there were two Paragraphs 9. Paragraph 11. It was confirmed that this was the Council’s response. It was also agreed that a change to the wording be made in Paragraph 11: “on the basis of the evidence available...” and that earlier “negative comments from English Heritage had not been restated at the meeting on 20 December 2007”. It was agreed that the exact wording would be left to the Chair and the Scrutiny Officer. Paragraph 12. A query was raised with regard to the use of “both instances”. And that with regard to the 10%, the wording should be changed to: “ Members noted that this figure was …” Members also raised concerns about the role of the Project Board and whether senior officers had been substituted by lower level officers at some meetings. For example, whether at the meeting on 25 April 2008 the Project team had received clear direction. The Chair noted that ... view the full minutes text for item 11.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Background 1. In early July 2008, the Council decided to withdraw its planning application for the proposed development of its new office accommodation at Hungate, following receipt of a formal written response from English Heritage that although the proposed building was a very impressive, sustainable and fit for purpose civic building, they were concerned that the building, by virtue of its height and massing could not be developed without harming the setting of the cluster of historic buildings and spaces around it. In summary, they objected to the proposal.
2. Members of the public commented on this decision and previous decisions taken in regard to the Hungate development and as a result of the concerns expressed, Cllr Brooks submitted this topic for scrutiny review in order to fully understand those decisions and the costs involved to date.
3. A feasibility report was presented to Scrutiny Management Committee (SMC) on 15 September 2008, and having agree to proceed with the review, an Ad- hoc Scrutiny Committee was formed and the following remit was agreed:
4. Aim To clarify whether the correct strategy for the accomodation project was set and adhered to, in order to ensure any future council projects are delivered on time and on budget.
Objectives i. In light of the overall budget, to identify whether the initial budget set was correct i.e. that all the relevant factors had been identified and included for, including the volume of all fees both agreed and incurred
ii. To understand the decision taken in respect of agreeing which part of CYC would act as internal ‘client’ and to understand the relationship between Planning and the client.
5. On 10 November 2008 the Ad-hoc Scrutiny Committee met for the first time and agreed a timetable of meetings and a methodology for carrying out this review. Consultation 6. The Ad-hoc Scrutiny Committee held an informal information gathering event on 26 November 2008 and the following internal and external consultees attended:
Assistant Director of Property Services CYC - Project Management Team & Accommodation Project Director
Maddy Jago English Heritage
Assistant Director of Planning & Design CYC – Planning & Conservation
Head of Risk Management & CYC – Risk Management Accommodation Project Manager
Information Gathered
7. Information gathered at the informal meeting on 26 November 2008 was recorded and considered in detail at a formal meeting of this Committee on 10 December 2008. At that time, Members agreed a number of amendments and the revised information and an analysis of it, is shown at Annex A.
8. As a result of the information gathered, Members recognised the need to meet with other key senior officers who were members of the Project Board. A second informal information gathering session was therefore arranged for immediately prior to this meeting, and the Chief Executive, Director of City Strategy and Director of Resources were requested to attend.
9. Members also requested the following additional information for this meeting:
• a summary of all the consultation that took place throughout the life of the project, showing the timeline involved (Annex B) • evidence of the design changes which officers have stated represent the project boards efforts to address the concerns of English Heritage (Annex C) • a revised version of the budget history which clearly identifies the elements of budget that are now fully committed etc (Annex D)
Options 10. Having considered the information contained within this report and its annexes, Members may choose to carry out further consultation by calling on additional witnesses or agree that no further information is required.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hungate Review - Draft Final Report(i) That it be agreed that every effort had been made to seek all the relevant information and that all the available...
Hungate Review - Interim ReportIt was agreed that a second informal information gathering session would be held prior to the next formal meeting of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.