Decision Session - Executive Member for City Strategy agreed this item on Tuesday 2 June 2009. Below is the council's own wording, with the papers it was decided on.
That the Executive Member agrees to: i) Note the progress achieved delivering schemes in the Capital Programme as indicated in the Annexes. ii) Approve the proposed carryovers in the sum of £204k, as outlined in paragraph 20, subject to the approval of the Executive. iii) Approve the proposed funding of the virement to Neighbourhood Services in the sum of £661k, as outlined in paragraph 21, subject to approval by the Executive. REASON: To enable the effective management and monitoring of the council’s capital programme That the Executive Member agrees to: i) Note the progress achieved delivering schemes in the Capital Programme as indicated in the Annexes. ii) Approve the proposed carryovers in the sum of £204k, as outlined in paragraph 20, subject to the approval of the Executive. 1. iii) Approve the proposed funding of the virement to Neighbourhood Services in the sum of £661k, as outlined in paragraph 21, subject to approval by the Executive. 2. REASON: To enable the effective management and monitoring of the council’s capital programme
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for City Strategy
Decision Session – Executive Member for 2 June 2009 City Strategy
City Strategy Capital Programme – Outturn Report
Summary 1. The purpose of this report is to:
• Inform the Executive Member of the outturn position for schemes in the 2008/09 capital programme, including budget spend to 31 March 2009, and the progress of schemes in the year;
• Inform the Executive Member of any variations between the outturn and budget, and seek approval for funding to be carried forward to 2009/10 subject to the approval of the Executive.
Recommendations 2. The Executive Member is requested to:
i) Note the progress achieved delivering schemes in the Capital Programme as indicated in the Annexes. ii) Approve the proposed carryovers as outlined in paragraph 20, subject to the approval of the Executive. iii) Approve the proposed funding of the virement to Neighbourhood Services as outlined in paragraph 21, subject to approval by the Executive. Reason: To enable the effective management and monitoring of the council’s capital programme
Background 3. The 2008/09 – 2010/11 capital programme was approved by Council on 21 February 2008. Since then a number of amendments have taken place, as reported to Executive Members in the 2007/08 Capital Outturn report, Consolidated report (July), Monitor 1 report (September), Monitor 2 report (December), and Monitor 3 report (March). These changes have resulted in a current approved capital programme for 2008/09 of £8,479k, financed by £6,898k of external funding, leaving a cost to the council of £1,581k. Table 1 illustrates the movements from the original budget to the currently approved position. Table 1 Current Approved Capital Programme Gross External Capital Budget Funding* Receipts £000s £000s £000s Original Budget Approved 7,943 6,441 1,502 by Council at 21 Feb 2008 Re-profiling to 09/10 & 10/11 from 07/08 outturn n/a n/a n/a report Additions/ reductions from 07/08 outturn report +496 +243 +253 approved at Monitor 1
Additions/ reductions from 07/08 outturn report +219 +219 approved at Monitor 2
Additions/ reductions from 07/08 outturn report -179 -5 -174 approved at Monitor 3 Current Approved 8,479 6,898 1,581 Capital Programme *External funding refers to government grants, non government grants, other contributions, developers contributions and supported capital expenditure.
Consultation 4. The capital programme was developed under the Capital Resource Allocation model (CRAM) framework and agreed by the council on 21 February 2008. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals do follow a consultation process with local councillors and residents in the locality of the individual schemes.
Summary of Key Issues Against the Monitor 3 approved budget of £8,479k in 2008/09, there is an outturn of £8,270k, a net underspend of £209k (2.5%). The outturn spend comprises: • Integrated Transport Schemes: £3,913k spend against a budget of £3,993k (£80k underspend (1.98%)).
• Highway Structural Maintenance Schemes: £4,264k spend against a £4,409k budget (£145k underspend (3.2%)).
• City Walls: £92k spend against a £76k budget (£16k overspend).
5. The overall spend is within the target tolerance of +2.0%/-5% which is used to assess the performance of the management of the City Strategy Capital Programme. Over 160 schemes have been progressed in the year ranging from £1k up to £520k value, with 15 schemes accounting for approximately 75% of the programme value. For many schemes feasibility studies and other preparatory works had to be undertaken within the year, leading to an expectation that many of the projects would be delivered towards the end of the year. In fact over 50% of the budget was spent in the final three months of the year despite the poor weather experienced in January and February.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for City Strategy at York and we tell you when its next papers are published, before the meeting rather than after it.
Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.