Peckitt Street and Friar's Terrace Flood Protection Scheme

Agreed Executive 2 papers

Decision Session - Executive Member for City Strategy agreed this item on Tuesday 7 July 2009. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

That the Executive Member agrees the principle of implementing the Peckitt Street and Friar’s Terrace flood protection scheme. REASON: To provide the most reliable protection against flooding and significantly reduce the resources required. That the Executive Member agrees the principle of implementing the Peckitt Street and Friar’s Terrace flood protection scheme 1 . REASON: To provide the most reliable protection against flooding and significantly reduce the resources required.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for City Strategy

Decision Session - Executive Member for City 7 July 2009 Strategy

Report of the Director of City Strategy

Peckitt Street and Friar’s Terrace Flood Protection Scheme

Summary 1. This report provides details of a proposed flood protection scheme to reduce flood risk from the River Ouse to four properties in York and maintain access during floods to thirteen more, and to the rear access to the fire station.

Recommendation 2. The Executive Member is recommended to agree the principle of implementing the Peckitt Street and Friar’s Terrace flood protection scheme.

Background 3. During a River Ouse flood event the Council installs temporary sandbagging and pumping to protect 8 Peckitt Street and 1 – 3 Friars Terrace (plan in Annex 1). Sandbags are also used at Tower Place to provide some protection to 1 – 9 Tower Place. It is not possible for the residents to protect their properties individually.

4. This procedure, developed since the 2000 flood, has proved to be effective on three occasions against events up to 4.42m (14’6”) above summer level (ASL). It has also been partially installed on some ten other occasions when forecasts predicted a higher peak than was actually reached.

5. The Council and residents acknowledge that the procedure will not be effective above that level, but because of its success residents expect that it will be carried out whenever there is a risk of the properties flooding.

6. There are resourcing and health and safety implications for the Council. It is expensive and the cost of the response to the flood in September 2008 was £31,844 of which approximately £25,000 could be attributed to the works at Peckitt Street and Tower Place. 7. Although the temporary installation uses sandbags, it is also dependent on the stability and integrity of the existing walls. These are in varying states of repair and the quality of the sandbagging can vary depending on the time available for erection. These factors decrease the certainty of being able to provide protection to the properties.

Proposal 8. A scheme has been designed which is more effective and reliable and less resource dependant. The height of the parapet wall in front of the four affected properties will be raised and a new wall constructed across the end of Peckitt Street. The existing railings will be remounted at the higher level.

9. Two pedestrian openings in the raised wall at the top of the steps from the riverside walk up to Peckitt Street will be closed at times of flooding with removable handstops. A third opening, with steps up to No. 3 Friar’s Terrace from the riverside will be walled up and backfilled. Minor works will be carried out on the frontage of Tower Place.

10. Discussions with Yorkshire Water Services will establish whether it will be possible to install valves to control backflow through the local sewerage system. This is not essential to the scheme but will enhance its reliability. It will still be necessary to provide temporary pumping during flood events.

11. This scheme has the same limitations as the temporary procedure and will only protect the properties against events up to a maximum level of 4.70m (15’5”) ASL. This occurred twice in 2008 and the 2000 flood peaked at 5.4m (17’7”) ASL.

Operation

12. Currently sandbagging operations commence on receipt of a warning of forecast river level in excess of 2.5m ASL.

13. In future, on receipt of a warning of forecast river level in excess of 3.9m ASL, resources will be mobilised to:

• Install the two handstops at the top of the Peckitt Street steps. • Provide pumps to handle seepage and supervise during operation. • Provide pumps and sandbags to Tower Place.

This will significantly reduce revenue costs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 21 KB Download
PDF
Peckitt Street and Friar's Terrace Flood Protection SchemeReport 44 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 4 attended
SG
Councillor Steve GallowayCabinet Member, present
KA
Councillor Keith AspdenAttendee, in attendance
TS
Councillor Tracey Simpson-LaingAttendee, in attendance
PF
Councillor Paul FirthAttendee, in attendance

On this subject at York

Search all
  1. Peckitt Street and Friar's Terrace Flood Protection SchemeThis decision
  2. Mudd and Co, 5 Peckitt Street, York, YO1 9SF [22/02604/LBC] (6.16 pm)Refused
  3. Bailey And Gildeners Solicitors 1 Peckitt Street York YO1 9SF (10/01688/ADV)Refused
  4. Bailey And Gildeners Solicitors 1 Peckitt Street York YO1 9SF (10/01689/LBC)Refused
  5. 8 Peckitt Street York YO1 9SF (09/00102/FUL)Approved
  6. 8 Peckitt Street York YO1 9SF (09/00106/LBC)Approved

More from York Decision Session - Executive Member for City Strategy

All decisions
MeetingDecisionOutcome
1 Mar 2011 MinutesThat the minutes of the last Decision Session – Executive Member for City Strategy, held on 1 February 2011 be approv... Approved Open
1 Mar 2011 Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto... Decided Open
1 Mar 2011 Evening and Sunday Bus Services to Rawcliffe and SkeltonThat the Executive Member for City Strategy agrees: i) That the level of service proposed to the affected areas follo... Agreed Open
1 Mar 2011 A19 Fulford Road Corridor Improvements - Request for 20 mph Speed Limit fronting Fishergate and St George's SchoolsThat the Executive Member for City Strategy agrees to: i) Option 1 to implement the 20mph speed limit as proposed and... Agreed Open
1 Mar 2011 Traffic Arrangements at York Railway StationThat the Executive Member for City Strategy agrees to: i) Note the outcome of the discussions with East Coast and Net... Agreed Open