Harewood Whin Landfill Site Tinker Lane Rufforth York YO23 3RR (09/00460/FUL)
DeferredPlanning3 papers
West & City Centre Area Planning Sub-Committee deferred this item on Thursday 16 July 2009. Below is the council's own wording, with the papers it was decided on.
That the application be deferred. 1 REASON: In order that a screening opinion can be undertaken as required by the Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 1999 to establish whether an Environmental Impact Assessment is required.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to West & City Centre Area Planning Sub-Committee
COMMITTEE REPORT
Committee: West/Centre Area Ward: Rural West York Date: 16 July 2009 Parish: Parish Of Rufforth With Knapton
Reference: 09/00460/FUL Application at: Harewood Whin Landfill Site Tinker Lane Rufforth York YO23 3RR For: Retention of Existing Compost Pad Extension. By: [name removed] Type: Full Application Target Date: 12 May 2009
1.0PROPOSAL
1.1Harewood Whin comprises a substantial waste disposal by landfill operation located in an area of open countryside within the designated York Green Belt to the west of the City Centre. The site, which also encompasses a range of recycling and green waste composting activities, operates under a series of permissions dating back from the mid 1980s , the current principal permission being given in 2003. A proposal was submitted in late 2007 to construct a composting area comprising three concrete pads at the southern edge of the complex but a decision has not been issued on this proposal due to an outstanding unresolved objection from the Environment Agency in relation to bio-aerosols. The current proposal envisages the retention of an extension to the existing concrete composting pad to the north of the recycling building at the north western edge of the site to handle the current throughput of green waste material suitable for composting whilst the issues surrounding bio-aerosols in relation to the application site at the southern edge of the complex are resolved.
3.1Highway Network Management raise no objection to the proposal;
3.2Structures and Drainage Consultancy raise concerns in respect of the lack of information relating to drainage of the application site submitted with the application;
3.3Environmental Protection Unit express some concern with respect to the proposal on the grounds of the impact of odours and bio-aerosols generated by the composting activity. They suggest that in view of the level of complaint being received in relation to composting activity at the site that a change be seriously considered to the method of working at the site to one incorporating forced aeration in line with the recommendations of the DEFRA Good Practice and Regulatory Guidance on Composting and Odour Control for Local Authorities(2009).This is justified on the basis of the need to follow the "precautionary principle" as outlined in PPS 23 "Planning and Pollution Control". Conditions attached to any approval should be used to ensure that the applicant uses an intensive method of odour abatement with suitable management controls.
EXTERNAL:
3.4Marston Moor Internal Drainage Board were consulted with regard to the proposal on 25th March 2009. No response has been forthcoming.
3.5Rufforth with Knapton Parish Council object to the proposal on the grounds that the work has been undertaken in advance of planning permission being granted ; the environmental safeguards put forward for the composting proposal at the southern edge of the site would not be put into place noise and smell nuisance for nearby residents would significantly increase and the proposal would facilitate a substantial increase in industrial activity on what is a Green Belt location.
3.6One letter of objection has been received on the grounds that work has been undertaken in advance of planning permission being given.
4.0APPRAISAL
4.1KEY CONSIDERATIONS:
Application Reference Number: 09/00460/FUL Item No: Page 2 of 7 Impact of the proposal on the open character and purposes of designation of the York Green Belt;
Impact of the proposal upon the amenity of neighbouring properties by virtue of noise and traffic generation and the generation of bio-aerosols;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow West & City Centre Area Planning Sub-Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.