Reserve list of Highways Schemes

Approved Executive 2 papers

Decision Session - Executive Member for Neighbourhoods and Housing. approved this item on Tuesday 21 July 2009. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

That the Executive Member: · Approve the split in funding between footways and roads. · Approve the provisional reserve list of possible schemes listed in Annex 1 of the agenda report. Reason: To ensure the Highway Maintenance budget is expended in the most cost effective way based on the Council's assessed priorities and approved policies. It will not be evident until the latter end of the financial year as to how much money will be available to allocate to the reserve schemes, it is not anticipated that all of the schemes will be undertaken. The list is much larger than any anticipated budget availability; this is to ensure some flexibility in the number of schemes to be completed with the finances available. That the Executive Member: · Approve the split in funding between footways and roads. · Approve the provisional reserve list of possible schemes listed in Annex 1 of this report. Reason: To ensure the Highway Maintenance budget is expended in the most cost effective way based on the Council's assessed priorities and approved policies. It will not be evident until the latter end of the financial year as to how much money will be available to allocate to the reserve schemes, it is not anticipated that all of the schemes will be undertaken. The list is much larger than any anticipated budget availability; this is to ensure some flexibility in the number of schemes to be completed with the finances available.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Neighbourhoods and Housing.

Decision Session - Executive Member for 21st July 2009 Neighbourhood Services Report of the Director of Neighbourhood Services

Reserve List of Highways Schemes

Summary 1. This report identifies additional highways schemes, some of which could be undertaken this financial year 2009/10, funded from within the service area. It is requested that the Executive Member for Neighbourhood Services approve the proposed list.

Background 2. Elements of City Strategy merged with the Civil Engineering Department within Neighbourhood Services in January of 2009. This merger has created efficiencies within a number of areas, the main area being the design and procurement of resurfacing and reconstruction schemes. It is the intention of Highways Maintenance Services to use the savings created within the design team along with pay back money from the Moor Lane roundabout to fund additional resurfacing and reconstruction schemes this financial year.

Consultation 3. Due to the nature of this report no consultation has taken place.

Options 4. Option 1 to approve the list of schemes, the works on the approved list be carried out towards the latter end of the financial year when a clearer indication on the amount of funding available can be made.

Option 2 to reject the list of schemes and make alternative recommendations for the financial savings.

Analysis 5. In order to produce the reserve list of highway works a number of surveys have been carried out throughout the year, these being :

• Visual safety survey of all our roads and footways

• Detailed condition surveys of our roads and footways • UK PMS visual and machine surveys of all roads and approx 22% of the footway network.

The roads and footways have been graded into three categories, grade 1 (good), grade 2 (average) and grade 3 (poor). The roads and footways identified in this reserve list all fall in to the category of grade 3.

A detailed condition survey has been undertaken of all the following highways.

• Streets listed in our LTP 5 year programme of structural maintenance

• Streets identified as grade 3 by June 2009 survey

• Streets where the UK PMS survey showed that sections of them breached national intervention levels

• Requests by Members

• Requests by residents

• Recommendations of the Council's Safety and Area Highway Reactive Inspectors along with other officers of the Council.

Each road and footway is assessed and given a condition rating (score) based on engineering criteria and experience, with a treatment solution determined. The detailed condition survey is compiled into a listing.

To augment all those other surveys and also identify areas for treatment, machine surveys to identify the skid resistance value and other highway defects of all principal roads and most other classified roads is undertaken on an annual basis to identify other highways requiring attention.

With this highway condition information we are in a better position to identify where we should direct our maintenance activities and develop the programmes of work.

Economic designs will be used as much as possible ensuring standards of quality are maintained and value for money consistent with a whole life costing approach. We would expect that full thickness surfacing of the footways should last for at least 20 - 30 years depending on whether it is a bituminous surface or cementitious and that renewal of binder course and running course for roads should last around 20 years with only minimal repair work necessary provided they have not suffered damage from third parties in the intervening period.

The priorities for selection are based on a number of weighting factors:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Reserve List of Highways Schemes Annex 1Appendix 14 KB Download
PDF
Reserve list of Highways SchemesReport 38 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
AR
Councillor Ann Reid MBECabinet Member, present

More from York Decision Session - Executive Member for Neighbourhoods and Housing.

All decisions
MeetingDecisionOutcome
15 Mar 2011 MinutesThat the minutes of the meeting held on 15 February be approved and signed by the Chair as a correct record. Approved Open
15 Mar 2011 Update on Private Sector Strategy.That the Executive Member noted the overall progress made to date in delivering the Private Sector Housing Strategy. ... Noted Open
15 Mar 2011 Removal of Private Sector Renewal Funding - Impact on the York Home Improvement Agency.(i)That the Executive Member noted the impact of the private sector renewal funding on service delivery both within t... Noted Open
15 Mar 2011 Achieving the Decent Homes Standard.(i)That the Executive Member noted that the Council has met the decent homes standard in line with the Governments De... Noted Open
15 Mar 2011 Decoration Voucher & Disturbance Allowance Scheme Allowances.That the Executive Member approved Options 1 & 2 as set out in the report to change the way Decorations and Disturban... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies