City of York Council
Planning Main, Thursday 27 August 2009 at 4.30pm

Planning Performance Agreements - Draft Charter for Consultation

Agreed Planning 2 papers

Planning Main agreed this item on Thursday 27 August 2009. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

i) That the Committee agree to Option A, to approve the charter for public consultation over a 6 week period, subject to the amendment of drafting errors, to include:- · Consultation with planning agents and consultants · Consultation with community groups and amenity bodies · Consultation with statutory and the main non statutory consultees · Placement of the charter document on the Council’s website and in the Council Offices . ii) That Members receive any comments arising from the consultation at the November Planning Committee meeting . REASON: To aim to provide a project management framework for handling large scale or complex major planning applications which will provide certainty for all development partners.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Planning Main

Annex A

DRAFT

PLANNING PERFORMANCE AGREEMENTS (PPA) CHARTER INTRODUCTION

1 This document (the “PPA Charter”) sets out the approach of City of York Council to Planning Performance Agreements (PPA). The Department for Communities and Local Government (CLG) consultation publication: ‘Planning Performance Agreements: a new way to manage large-scale major planning applications’ (May 2007) defines a PPA as an ‘agreement between a local planning authority and an applicant to provide a project management framework for handing a major planning application’. It also follows further guidance published by the Advisory Team for Large Applications (ATLAS)1, which recommends that if PPAs are to be used regularly, a Local Planning Authority is encouraged to establish a formal process document (“Charter”) to set out their broad methodology for dealing with large complex development projects.

2 The establishment of this PPA charter is consistent with the Council’s commitment to collaborate with developers/applicants to deliver major and complex developments that address Planning and Sustainable Development Service Plan objectives:

• To provide effective stewardship of the City's historic and natural environment alongside the complimentary objective of economic growth within the City. • To influence development schemes, to ensure the highest quality of design and appearance, which enhances the unique character and future well being of York.

3 The Planning Service also has strategic objectives to improve planning application performance without compromising the quality of development.

4 The objective of this Charter is to clarify the Council’s expectations of the PPA process, summarised as:

Commitment: The commitment of City of York Council, statutory agencies and service providers to the PPA process and the approach and actions that developers/applicants are expected to commit;

1 Annex A

Engagement: Expectations for community involvement and the method of engagement with Members; Resources: The expectations of the Local Planning Authority with regard to the delivery of the PPA process and support from the developer/applicant; Process: The key requirements of the statutory application process and the expected content of a PPA.

PPA APPLICATIONS

5 Inclusion within the PPA process will be determined by complexity of the project at both pre-application and application phase rather than its scale, albeit that the DCLG definition of a small scale major application forms the minimum threshold. Where a sufficiently complex major development proposal has the potential to accord to the provisions of the relevant Development Plan, or in the case of a Departure from the Plan, to meet any of the City Council’s broader regeneration or community objectives, the management of the application through the PPA process will be promoted

6 Any planning application for which a PPA is in place at the pre- application stage will be exempted from the Best Value performance indicator N157a (formerly 109a) (13-weeks determination period) if the agreed PPA timescale is subsequently met, to allow applicants and the Local Authority to negotiate a flexible timescale that reflects the complexity and requirements of the individual application.

7 CYC anticipates promoting a PPA for strategic and very complex projects and other significant proposals which have one or more complex planning issues that need careful and well planned consideration with the assistance of a statutory consultee.

COMMITMENT TO THE PPA PROCESS

City of York Council

8 An initial approach regarding any large-scale development project should be directed towards City Strategy officers in either Development Control or City Development (Major Projects Team). As the project evolves towards the PPA process, a Project Team will be created involving relevant officers from other Council departments to ensure a unified and consistent approach.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PPA Charter draft (CYC) 13.8.09Report 43 KB DownloadRead as text
PDF
Planning Performance Agreements: Draft Charter for ConsultationReport 44 KB Download

At this meeting

Whole meeting

Who was there

16 of 21 attended
RW
Councillor Richard WatsonChair, present
AD
Councillor Andy D'AgorneCommittee Member, present
PF
Councillor Paul FirthCommittee Member, apologies
CF
Councillor Christina FunnellCommittee Member, apologies
DH
Councillor David HortonCommittee Member, present
BH
Councillor Ben HudsonCommittee Member, apologies
KH
Councillor Keith HymanCommittee Member, present
CJ
Councillor Ceredig Jamieson-BallCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
JM
Councillor Jonathan MorleyCommittee Member, present
RP
Councillor Roger PierceCommittee Member, apologies
RP
Councillor Ruth PotterVice-Chair, apologies

All 21 on the meeting page

On this subject at York

Search all
  1. Planning Performance Agreements - Draft Charter for ConsultationThis decision
  2. Planning Appeal Performance and Decisions (5.48 pm)Noted
  3. Planning Appeal Performance and Decisions (6.36 pm)Noted
  4. Planning Appeal Performance and Decisions (6.18 pm)Noted
  5. Planning Appeal Performance and Decisions (6.32 pm)Noted
  6. Planning Appeal Performance and Decisions (8.02 pm)Noted

More from York Planning Main

All decisions
MeetingDecisionOutcome
5 May 2022 MinutesThat subject to the addition of Cllrs Melly and Ayre to the list of apologies, the minutes of the last meeting held o... Approved Open
7 Apr 2022 Minutesi. That the minutes of the meeting held on 3 February 2022 be approved and then signed by the chair as a correct reco... Approved Open
3 Mar 2022 MinutesThat the minutes of the last meeting held on 3 February 2022 be approved at the next meeting. Approved Open
3 Mar 2022 Lindum Group Limited, York Road, Elvington, York YO41 4EP [21/01709/REMM]That the application be approved subject to the conditions listed in the report and the addition of an informative in... Approved Open
3 Feb 2022 MinutesThat, subject to the amendment stated above, the minutes of the last meeting held on 6 January 2022 be approved and s... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies