Access York Phase 1 Park & Ride Development - Procurement of a Lead Design Consultant
AgreedExecutive1 paper
Executive - for meetings from 03/06/00 to 26/04/11 agreed this item on Tuesday 19 January 2010. Below is the council's own wording, with the papers it was decided on.
That Halcrow Group Ltd. be nominated as the preferred bidder for the Leader Design Consultant for the Access York Phase 1 Park & Ride development, subject to the DfT decision on Programme Entry and subsequent funding agreements. REASON: To enable the Access York Phase 1 project to proceed as planned, by following the procurement process in the nomination of a preferred bidder for the Lead Design Consultant. That Halcrow Group Ltd. be nominated as the preferred bidder for the Leader Design Consultant for the Access York Phase 1 Park & Ride development, subject to the DfT decision on Programme Entry and subsequent funding agreements. 1 REASON: To enable the Access York Phase 1 project to proceed as planned, by following the procurement process in the nomination of a preferred bidder for the Lead Design Consultant.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 19 January 2010
Report to the Director of City Strategy
Access York Phase 1 Park & Ride Development – Procurement Of a Lead Design Consultant
Summary 1. This report provides a summary of the evaluation of the external consultants following the submission of tenders for Lead Design Consultant for the Access York Phase 1 Park & Ride Project. The report also includes a history of the procurement process and the subsequent recommendations regarding the above appointment.
2. Following an OJEU process utilising the restricted procedure, 29 initial expressions of interest were assessed and reduced to a short list of 6 consultants through a pre-qualification questionnaire (PQQ) exercise, to follow through to the main tender process. Of the 6 consultants, 2 declined to tender mid-way through the process due to commercial reasons. The 4 consultants that remained have been assessed both commercially and on a quality basis, split 40:60 respectively. After a full evaluation this report recommends that Halcrow be selected as preferred bidder for the provision of the service.
3. The final appointment of Halcrow is subject to the award of Programme Entry by the Department for Transport (DfT), a final ratification of funding arrangements by the Regional Transport Board and confirmation of the City of York Council (CYC) element of the funding. Programme Entry was originally anticipated in December 2009, however, this may slip to January / February 2010. No formal appointment will be entered into until this award and confirmation of the funding arrangements is confirmed.
Background 4. Scheme progress is currently in the planning stages of this capital project to design, procure and construct 3 new Park and Ride facilities. The works will include car-parking facilities; terminal buildings and highways work incorporating new junctions, access roads and alterations to roundabouts.
5. DfT approval for funding is anticipated in early 2010. Planning application outcomes are currently programmed to be obtained by May 2010 for all sites, with the planning consent for Askham Bar P&R already in place. 6. The lead consultant will manage and co-ordinate the complete project from the planning stages, to completion and handover of the 3 Park & Ride facilities.
7. The lead consultant will enter into a direct contract with the Council for the services and will report to the Project Manager on a frequent basis within an agreed and acceptable reporting structure.
8. A summary of the services provided by the Lead Design Consultant to deliver the Park & Ride developments is as follows:
• Civil engineering design • Highways Design • Architectural Design (Nominated to CYC architects) • Cost Management • Construction Supervisor – as defined within the NEC3 Contract • Contractor Procurement • Landscape Design • Drainage Design • Traffic Modelling • Traffic Management • Traffic Signals • Mechanical and Electrical Design • Lighting Design • Acoustician • Ground Remediation / Geotechnical • CDM Co-ordinator (Nominated to Halcrow) • Barrier Systems • CCTV • Stakeholder liaison • Project Administration
9. The consultant will be required to co-ordinate and manage the above services, and any other services required to achieve the project deliverables, within their multi-disciplinary team. This includes the nominated services of the Council’s Architects and Halcrow CDM Co-ordinators.
10. The OJEU restricted procedure was used in selecting this consultant for the future delivery of the project. Previous reports to the Executive have detailed the process of evaluation. This process has been followed and a summary is as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.