City Strategy Capital Programme - 2010/11 Budget Report
ApprovedExecutive2 papers
Decision Session - Executive Member for City Strategy approved this item on Tuesday 2 March 2010. Below is the council's own wording, with the papers it was decided on.
That the Executive Member approves the scheme allocations set out in Annex 1 of the report subject to the following modification: · That the allocation for the purchase of Dial and Ride vehicles be increased from £80k to £97k to enable two vehicles to be purchased. This to be accommodated by increasing the level of overprogramming across the programme by £17k. REASON: To implement the council’s transport strategy identified in York’s second Local Transport Plan and deliver schemes identified in the Council’s Capital Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for City Strategy
Decision Session 2 March 2010 – Executive Member for City Strategy
Report of the Director of City Strategy
City Strategy Capital Programme – 2010/11 Budget Report Summary 1. This report sets out the funding sources for the City Strategy Capital Programme and the proposed schemes to be delivered in 2010/11. The report covers the Integrated Transport and City Walls restoration allocations. Progress on the Accommodation Review and Community Stadium projects are presented in separate reports.
Recommendations 2. The Executive Member is requested to approve the scheme allocations indicated in Annex 1.
Reason: To implement the council’s transport strategy identified in York’s second Local Transport Plan and deliver schemes identified in the Council’s Capital Programme.
Background 3. Subject to approval at Full Council on 25 February 2010, the City Strategy Capital Programme budget for 2010/11 is anticipated to be £7,000k, which includes £2,986k of Local Transport Plan (LTP) funding, plus other funding from the Cycling City grant, Road Safety grant, Regional Funding Allocation (RFA) Supplementary Grant, developer contributions and council resources. This represents the budget available to spend and is therefore net of the over-programming built into the Local Transport Plan element of the programme. The overprogramming seeks to address the problem of schemes being delayed due to unforeseen circumstances arising.
4. The full City Strategy Capital Programme also includes funding from council resources for maintenance of the City Walls. The funding allocated to the 2010/11 Programme Budget and the comparable 2009/10 Monitor 2 Programme is indicated in the following table. Funding 2009/10 (M2) 2010/11 £000s £000s LTP funding 3,374 2,986 Cycling City 1,120 1,055 RFA Supplement 450 2,327 Developer Contributions 375 500 Road Safety Grant 43 42 City Walls Restoration (CYC) 143 90 PROW River Bank Repairs (CYC) 81 Total Budget 5,586 7,000
Proposed Programme 5. The proposed budget has been split into a number of main blocks across the objectives of the Local Transport Plan. More details of the proposed allocations are included in the following paragraphs and Annex 1. The allocations indicated in the table below include schemes committed in previous years and an allowance for overprogramming.
6. The level of overprogramming £1,167k (16.5%) has been kept to a lower proportion than previous years (19.5% in 2009/10) in recognition of the much reduced budget allocations anticipated in 2011/12. The LTP settlement has not yet been advised for the next five year period but the RFA supplement and the Cycling City Grant will not be available.
Proposed 2010/11 Programme £000s Access York Phase 1 550 Access York Phase 2 inc. 1,750 A19/A1237 Roundabout Multi-Modal Schemes 1,075 Air Quality & Traffic Management 250 Park & Ride 50 Public Transport Improvements 530 Walking 710 Cycling Schemes 2,352 Safety and Accessibility Schemes 460 School Schemes 250 Previous Years Transport Scheme 100 Costs City Walls Restoration 90 Total City Strategy Programme 8,167 Over Programming 1,167 Total City Strategy Budget 7,000
7. The budget has been allocated to ensure that the objectives of the Local Transport Plan and Local Area Agreement, which has targets for safety and congestion, are achieved. In addition the programme has been prepared to ensure that the allocations are in accordance with the constraints imposed by the various funding sources. The RFA supplement has been allocated to a number of the larger schemes across the programme (A19/A1237 Roundabout, Access York Phase 1 & 2, Haxby Station, Access Ramps to Station). LTP and developer contributions have been used to match fund the Cycling City grant. The programme also takes account of the anticipated progress delivering schemes in 2009/10.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for City Strategy at York and we tell you when its next papers are published, before the meeting rather than after it.
Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.