Neighbourhood Services Capital Programme Monitor 3

Approved Executive 1 paper

Decision Session - Executive Member for Neighbourhoods and Housing. approved this item on Wednesday 24 March 2010. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

(i)That the Executive Member approved the 2009/10 revised budget of £5.041m as set out in Table 2 on page 67 of the Agenda. (ii)That the additional grant of £46k received for Contaminated Land Investigations was noted. (iii)That the Executive Member approved the overspend on the Silver Street Toilets £24k. (iv)That the Executive Member approved the slippage of £246k into 2010/11 on the Waste Infrastructure Capital Grant. (v)That the Executive Member approved the slippage of £112k on the EcoDepot Gatehouse/Reception. REASON: To enable the effective management and monitoring of the Council’s capital programme. (i)That the Executive Member approved the 2009/10 revised budget of £5.041m as set out in Table 2 on page 67 of the Agenda. (ii)That the additional grant of £46k received for Contaminated Land Investigations was noted. (iii)That the Executive Member approved the overspend on the Silver Street Toilets £24k. (iv)That the Executive Member approved the slippage of £246k into 2010/11 on the Waste Infrastructure Capital Grant. (v)That the Executive Member approved the slippage of £112k on the EcoDepot Gatehouse/Reception. REASON: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Neighbourhoods and Housing.

Executive Member Decision Session – 24 March 2010 Neighbourhood Services Report of the Director of Neighbourhood Services

NEIGHBOURHOOD SERVICES CAPITAL PROGRAMME MONITOR 3 Summary 1. The purpose of this report is to:

• Inform the Executive Member of the likely outturn position of the 2009/10 Capital Programme based on the spend profile and information to December 2009;

• To notify of any resulting changes to the programme;

• Inform the Executive Member of any slippage and associated funding to be slipped between the relevant financial years to reflect this.

Background 2. The 2009/10 – 2013/14 capital programme was approved by Council on 26th February 2009. The current approved capital programme for 2009/10 is £4.657 m, financed by £2.248 m of external funding*, leaving a cost to the Council of £2.409 m. Table 1 illustrates the movements from the original budget to the currently approved position. Gross External Capital Budget Funding* Receipts £m £m £m

Original Budget 4.657 2.248 2.409 Approved by Council at 26 Feb 2009 Additions/reductions 1.780 1.778 0.002 approved at monitor 1 Slippage approved at (0.008) 0 (0.008) monitor 1 Additions/reductions 0 0 0 approved at monitor 2 Slippage approved at (1.100) (1.000) (0.100) monitor 2 Current Approved 5.329 3.026 2.303 Capital Programme *External funding refers government grants, non-government grants, other contributions, developer’s contributions and supported capital expenditure.

Table 1 Current Approved Capital Programme

3. The capital receipts column above implies receipts generated from the sale of Council assets will be used to fund the difference between the gross budget less all other specified funding sources. Due to the current economic climate not being favourable to achieving maximum receipt value from asset disposals, consideration will be given to the use of prudential borrowing to fund the capital programme as a temporary measure. When the economic climate returns to a more favourable state assets will be sold with the receipts being applied to finance the programme thus replacing the temporary borrowing.

Consultation 4. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 26th February 2009. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals do follow a consultation process with local Councillors and residents in the locality of the individual schemes.

Summary of Key Issues 5. Against the current approved budget of £5.329m, there is a predicted outturn of £5.041m, a net decrease of £0.288m.

6. The net decrease is composed of:

• Additional grant of £46k received for Contaminated Land Investigations

• An overspend on Silver Street Toilets of £24k

• Slippage of £246k into 2010/11 on the Waste Infrastructure Capital Grant

• Slippage of £112k on the EcoDepot Gatehouse/Reception. Table 2 highlights scheme specific information: Gross Neighbourhood 2009/10 2010/11 2011/12 Total Para Services Capital Ref Programme £m £m £m £m Current Approved Capital 5.329 5.326 5.555 16.210 Programme Additional: Contaminated Land 0.046 0.005 0 0.051 Investigations Silver Street Toilets 0.024 0.001 0 0.025 Re-profiling: Waste Infrastructure (0.246) 0.246 0 0 Capital Grant EcoDepot gatehouse (0.112) 0.112 0 0

Revised Capital 5.041 5.690 5.555 16.286 Programme Table 2 Capital Programme Forecast Outturn 2009/10 – 2011/12

7. The main highlights of this report are:

• Additional grant of £46k received for Contaminated Land Investigations

• An overspend on Silver Street Toilets of £24k

• Slippage of £246k into 2010/11 on the Waste Infrastructure Capital Grant

• Slippage of £112k on the EcoDepot Gatehouse/Reception.

Scheme Specific Analysis Air Quality Management 09/10 Budget: £50k (DEFRA Grant) 09/10 Forecast: £50k

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Neighbourhood Services Capital Programme Monitor 3Report 122 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 4 attended
AR
Councillor Ann Reid MBECabinet Member, present
AB
Andy BinnerOfficer, expected
GD
Geoff DerhamOfficer, expected
SM
Stephen MouldsOfficer, expected

On this subject at York

Search all
  1. Neighbourhood Services Capital Programme Monitor 3This decision
  2. Year End Finance and Performance Update for Communities and Neighbourhood Services, Environment Services and Public ProtectionNoted
  3. Monitor 3 Finance and Performance Update for Communities and Neighbourhoods Environment ServicesNoted
  4. Monitor 3 Finance and Performance Update for Communities and Neighbourhoods Environment ServicesDeferred
  5. Finance and Performance Update for Communities and Neighbourhoods Environmental Services - Quarter 2Noted
  6. Neighbourhood Services Budget for 2010/11.Noted

More from York Decision Session - Executive Member for Neighbourhoods and Housing.

All decisions
MeetingDecisionOutcome
15 Mar 2011 MinutesThat the minutes of the meeting held on 15 February be approved and signed by the Chair as a correct record. Approved Open
15 Mar 2011 Update on Private Sector Strategy.That the Executive Member noted the overall progress made to date in delivering the Private Sector Housing Strategy. ... Noted Open
15 Mar 2011 Removal of Private Sector Renewal Funding - Impact on the York Home Improvement Agency.(i)That the Executive Member noted the impact of the private sector renewal funding on service delivery both within t... Noted Open
15 Mar 2011 Achieving the Decent Homes Standard.(i)That the Executive Member noted that the Council has met the decent homes standard in line with the Governments De... Noted Open
15 Mar 2011 Decoration Voucher & Disturbance Allowance Scheme Allowances.That the Executive Member approved Options 1 & 2 as set out in the report to change the way Decorations and Disturban... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies