Access York Park & Ride Development - Update Report Following Programme Entry
ApprovedExecutive1 paper
Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 13 April 2010. Below is the council's own wording, with the papers it was decided on.
(i) That the City of York Council contributions for the Access York Phase 1 project, as set out in the anticipated spend / funding profile in paragraph 11 of the report and the potential funding sources in paragraph 14, be approved. (ii) That the procurement of Halcrow as the Lead Design Consultant be approved. REASON: To enable the Access York Phase 1 project to proceed as planned by providing the required funding and approving the procurement of a Lead Design Consultant. (i) That the City of York Council contributions for the Access York Phase 1 project, as set out in the anticipated spend / funding profile in paragraph 11 of the report and the potential funding sources in paragraph 14, be approved. 1 (ii) That the procurement of Halcrow as the Lead Design Consultant be approved. REASON: To enable the Access York Phase 1 project to proceed as planned by providing the required funding and approving the procurement of a Lead Design Consultant. 2
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 13 April 2010
Report of the Director of City Strategy
ACCESS YORK PHASE 1 PARK & RIDE DEVELOPMENT – UPDATE REPORT FOLLOWING PROGRAMME ENTRY
Summary 1. The Major Scheme Business Case (MSB) for Access York Phase 1 has now been approved for Programme Entry by the Department for Transport (DfT). This long awaited decision now creates the opportunity for the majority of the funding for this project to become available from the government. The £25 million investment will increase the number of park and ride spaces from 3,750 to 5,350. However, to achieve this a considerable amount of further progress is required and this report seeks approval to continue.
2. An essential requirement for progress is the identification of the CYC funding element of the project and this is set out in the Financial Information section of the report.
3. The other essential requirement is the appointment of the Lead Design Consultant so that the detailed design, leading to the procurement of the construction contractor, can be carried out as quickly as possible. At the meeting of the Executive in January 2010, Members approved that Halcrow would be nominated as the preferred bidder, subject to the DfT decision on Programme Entry and approval is now sought to confirm the appointment of Halcrow.
Background 4. The Access York Phase 1 project has continued to make good progress, as summarised below:
• Planning approval for the Askham Bar site was granted in September 2009. • Planning approval for the Poppleton Bar site was very recently granted in March 2010. • The planning application for the Clifton Moor site will be considered by the Planning Committee at the end of April 2010. • The agreements to purchase land at Askham Bar and Poppleton Bar have been completed and land negotiations elsewhere are progressing well. • The procurement of the Lead Design Consultant is complete with Halcrow being the preferred bidder subject to the favourable decision on Programme Entry and then confirmation from Members of the funding arrangements and Halcrow’s appointment. The Lead Design Consultant will manage and co-ordinate the majority of the project, within their multi-disciplinary team, from the planning stages to completion and handover of the 3 Park & Ride facilities. • Confirmation on 22 March 2010 from the DfT and the Minister that the Access York Phase 1 project now has Programme Entry.
Financial Information
5. There are a number of financial implications to consider before progressing with the Access York Phase 1 project, including:
a. Approvals b. Total Scheme Cost c. Local Contribution d. Preparatory Costs e. Cost Increases f. Revenue Implications
Approvals 6. Programme Entry approval by the DfT indicates the Department's present intention to provide funding towards the construction of the scheme, provided there are no significant changes to it, and subject to a satisfactory MSBC being provided at each subsequent approval stage.
7. Programme Entry is not a commitment that funding will be provided, nor to the timing of any agreed contribution, either of which may be subject to further consideration of affordability within Regional Funding Allocations. Funding commitment is confirmed at the receipt of Full Approval when the tenders for the scheme have been received.
8. Subject to detailed clarification the acceptance of the business case by the DfT confirms the maximum funding which could be received from Central Government for the scheme. This figure will remain fixed throughout the project. Further business cases will have to be presented to the DfT for approval at Conditional Approval (planning consent granted) and Final Approval (tenders received) stages to confirm that the value for money of the scheme and policy fit remains compliant.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.