Called-in Item: Traffic Congestion Final report Part 1
ApprovedScrutiny6 papers
Corporate Services, Climate Change and Scrutiny Management Committee (Calling In) approved this item on Tuesday 4 May 2010. Below is the council's own wording, with the papers it was decided on.
That Option B be approved and the matter be referred back to the Executive with a recommendation that they either accept, reject or amend the Scrutiny Committee’s recommendations rather than simply noting them. REASON: In accordance with the requirements of the Council’s calling-in procedure and the reasons given for the calling-in.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Corporate Services, Climate Change and Scrutiny Management Committee (Calling In)
Background
2. An extract from the decision list published after the relevant Executive Meeting is attached as Annex 1 to this report. This sets out the decisions taken by the Executive on the called-in item, together with a list of Executive comments on the Scrutiny Committee’s report. The original report to the Executive is attached as Annex 2.
3. Councillors D’Agorne, Hudson and Merrett have called in the Executive’s decisions for review by the Scrutiny Management Committee (SMC) (Calling-In), in accordance with the constitutional requirements for post-decision call-in. The reasons given for the call-in are that:
“Just noting the Traffic Congestion Ad Hoc Scrutiny's (interim) final report on the terms stated is not an appropriate or adequate response and the Executive should consider the various recommendations and say yes or no to them, or make amended argued decisions as appropriate.” Consultation
4. In accordance with the requirements of the Constitution, the Calling-In Members will be invited to attend and/or speak at the Calling-In meeting, as appropriate.
Options
5. The following options are available to SMC (Calling-In) in relation to dealing with this call-in, in accordance with the constitutional and legal requirements under the Local Government Act 2000:
(a) To confirm the decisions of the Executive, on the grounds that the SMC (Calling-In) does not believe there is any basis for reconsideration. If this option is chosen, the decisions will take effect from the date of the SMC (Calling-In) meeting.
(b) To refer the matter back to the Executive, for them to reconsider their original decisions. If this option is chosen, the matter will be re-considered at a meeting of the Executive (Calling-In) to be held on 5 May 2010.
Analysis
6. Members need to consider the reasons for call-in and the basis of the decisions made by the Executive and form a view on whether there are grounds for reconsideration of those decisions.
Corporate Priorities
7. An indication of the Corporate Priorities to which the Executive’s decisions are expected to contribute is provided in paragraph 11 of Annex 2 to this report.
Implications
8. There are no known financial, HR, Legal, Property, Equalities, or Crime and Disorder implications in relation to the following in terms of dealing with the specific matter before Members; namely, to determine and handle the call-in:
Risk management
9. There are no risk management implications associated with the call in of this matter. Recommendations
10. Members are asked to consider the call-in and reasons for it and decide whether they wish to confirm the decisions made by the Executive or refer the matter back for re-consideration at the scheduled Executive Calling-In meeting.
Reason:
11. To enable the called-in matter to be dealt with efficiently and in accordance with the requirements of the Council’s Constitution.
Contact details: Author: Chief Officer Responsible for the report: Dawn Steel Democratic Services Manager Head of Civic, Democratic and Legal Services 01904 551030 email: [email protected] Report Approved √ Date
Specialist Implications Officer(s) None
Wards Affected: All √
For further information please contact the author of the report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Services, Climate Change and Scrutiny Management Committee (Calling In) at York and we tell you when its next papers are published, before the meeting rather than after it.
Called-in Item: Advertising ContractThat the call-in be postponed. Reason: In order that the committee can be assured that it is acting on the most curre...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.