English Martyrs RC Primary School, Hamilton Drive, York, YO24 4JW (10/01460/FULM)
ApprovedPlanning2 papers
West & City Centre Area Planning Sub-Committee approved this item on Thursday 16 September 2010. Below is the council's own wording, with the papers it was decided on.
That the application be approved subject to the conditions listed in the report, the removal of condition 23 as listed in the report and the amended and additional conditions listed below. Amended Condition All areas used by vehicles shall be surfaced, sealed and positively drained within the site, in accordance with a timescale to be submitted to and approved in writing by the Local Planning Authority. Reason: To prevent the egress of water and loose material onto the public highway. Additional Condition The development hereby permitted shall be carried out in accordance with the School Travel Plan Framework Revision B received 9 July 2010. The submitted travel plan shall be implemented in accordance with the timescale within the travel plan. Within 12 months of occupation of the site ... view the full minutes text for item 21a
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to West & City Centre Area Planning Sub-Committee
COMMITTEE REPORT
Date: 16 September 2010 Ward: Holgate Team: Major and Commercial Parish: No Parish Team
Reference: 10/01460/FULM Application at: English Martyrs RC Primary School Hamilton Drive York YO24 4JW For: Erection of school building with associated parking and landscaping, construction of multi-use games area following demolition of existing school building (resubmission) By: [name removed]: Major Full Application (13 weeks) Target Date: 11 October 2010 Recommendation: Approve
1.0PROPOSAL
1.1The application is for the erection of school building with associated parking and landscaping, construction of multi-use games area following demolition of existing school building. The proposed school would be sited to the side/east of the present building. The site of the existing school would be used for vehicle parking and a fenced Multi Use Games Area (MUGA). Playing fields will be retained to the rear of the school, and landscaping to the east of the site is intended to increase the habitat potential of the site in addition to the outside classrooms. There would be landscaping to the front of the building including a sensory garden and two access points to the school, one for the pupils and one for visitors. The car park would be extended, and cycle parking for 90 cycles would be proposed. The existing school is a single storey building built in the 1960s with a recent extension. The extension would be retained to provide ancillary teaching space, a pastoral suite and music room.
1.2The proposed two storey building would face onto Hamilton Drive and would be set further forward that the existing building. The proposed school would be built up in height to accommodate a void underneath the building. The undercroft is part of the flood mitigation measures of the site as the site is within a Flood Zone 3.
1.3The site is set within a suburban residential area with dwellings to the east and west boundaries (there is also open space to the eastern boundary) and allotments to the north boundary. The existing school building is set back from Hamilton Road and partially screened by a row of mature trees and a hedge. The other boundaries are also marked by a mixture of fencing, matures trees and deciduous hedging. Holgate Beck runs parallel to the eastern boundary of the site. The existing building has been constructed on a plinth and is raised above the level of the playing fields and street, the rest of the site is level.
Application Reference Number: 10/01460/FULM Item No: 4a Page 1 of 24 1.4 The intention is that the building will be constructed in a single phase and the existing buildings will be in use as school building during the construction process.
1.5This application is a resubmission of a previous scheme that was withdrawn 2 July 2010. This application differs from the previous application in that compensatory flood measures have been submitted.
1.6In addition to the plans and elevations the application is supported by the following documentation: -
§ Community Involvement Statement § Design and Access Statement § Drainage Strategy and SUDS Statement § PPS25 Sequential Test and Exception Test Report § Flood Risk Assessment § Acoustics Report § Sustainability Report § Site Waste Management Plan § Ecological Appraisal for BREEAM Education § Site Investigation Report § Watching Brief Report on Geotechnical Trial Pits § Bat Survey and Assessment § Thermal Modelling Analysis and Compliance Report § Archaeological Scheme of Investigation: Watching Brief § Tree Survey Report § Transport Assessment § School Travel Plan Framework
2.0POLICY CONTEXT
2.1Development Plan Allocation:
City Boundary GMS Constraints: York City Boundary 0001
DC Area Teams GMS Constraints: West Area 0004
Floodzone 2 GMS Constraints: Flood zone 2
Floodzone 3 GMS Constraints: Flood zone 3
Schools GMS Constraints: English Martyrs' RC Primary 0196
Follow West & City Centre Area Planning Sub-Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.