Childcare Sufficiency Assessment 2011 to 2014 Update and Proposals for Action Planning
ApprovedExecutive2 papers
Decision Session - Executive Member for Children and Young People's Services approved this item on Tuesday 11 January 2011. Below is the council's own wording, with the papers it was decided on.
(i) That options a to e, as detailed in paragraph 17 of the report, be approved. (ii)That, in addition to the options detailed in paragraph 17 of the report, consideration be given to including information in the “Your City” and “Your Ward” publications. REASONS: (i) To meet a statutory requirement of the local authority. (ii)To ensure that there is an open discussion of key messages from the Childcare Sufficiency Assessment and that action planning on a partnership basis is commenced to address identified gaps. (i) That options a to e, as detailed in paragraph 17 of the report, be approved. (ii)That, in addition to the options detailed in paragraph 17 of the report, consideration be given to including information in the “Your City” and “Your Ward” publications 1 . REASONS: (i) To meet a statutory requirement of the local authority. (ii)To ensure that there is an open discussion of key messages from the Childcare Sufficiency Assessment and that action planning on a partnership basis is commenced to address identified gaps.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Children and Young People's Services
Executive Member Decision Session for 11 January 2011 Children and Young People Report of the Director of Adults, Children and Education
Childcare Sufficiency Assessment 2011-2014 update and proposals for action planning
Summary 1. York is currently part way through completing its second full Childcare Sufficiency Assessment (CSA). This paper and its annex provide initial findings to date and will be accompanied by a more detailed presentation delivered at the decision session itself.
2. The Executive Member is asked for a decision and feedback on options for developing the CSA into the final assessment document alongside developing a robust and achievable action plan for addressing any identified gaps in childcare provision.
Background 3. The Childcare Act (2006) requires Local Authorities to carry out an assessment of the sufficiency of childcare in their area. Sufficient childcare is defined as ‘sufficient to meet the requirements of parents in the local authority area who require childcare in order to enable them:
a. to take up, or remain in, work
b. or to undertake education or training which could reasonably be expected to assist them to obtain work”
4. As well as the overall availability of places in childcare attention should also be paid to assessing if the childcare is flexible, good quality, affordable and inclusive in a way that meets local families’ needs.
5. A full Childcare Sufficiency Assessment (CSA) involves gathering data around the supply of childcare and also consulting families and a wide range of partners to judge levels of demand. A Childcare Sufficiency Assessment (CSA) is carried out in full once every three years with lighter refreshes on an annual basis.
6. In 2010-2011 York is carrying out its second full CSA that will cover 2011- 2014. This assessment will be accompanied by an action plan highlighting key steps to be taken locally to address identified gaps in childcare provision. A summary of the timeline for the assessment and action planning is shown below.
a. November 2009 – February 2010: Establishing the project approach and consultation materials.
b. March 2010 – May 2010: Produce consultation materials and set up data systems.
c. June 2010 – August 2010: Public consultation
d. September 2010 – December 2010: Childcare providers audited and consulted. Data analysis work carried out on public consultation responses initially to identify any groups that may be under-represented.
e. December 2010 – January 2011: Draft Childcare Sufficiency Assessment produced. Any groups not fully picked up as part of the consultation exercise engaged for feedback.
f. January - February 2011: Consultation on draft Childcare Sufficiency Assessment and action planning.
g. February – March 2011: Final Childcare Sufficiency Assessment and action plan produced.
h. 31st March 2011: Childcare Sufficiency Assessment and Action Plan published.
7. Due to the required timings for submitting this report the full draft assessment has not yet been completed. However the full draft assessment and proposed next steps will be presented and discussed at the decision session itself. Initial headline messages from the consultation exercise have been provided as annex A. It is very important to note though that these figures only represent the responses to the written consultation. Far more information from face to face work and consultation with other groups will be drawn together to form the final sufficiency assessment.
Consultation 8. Effective consultation is a core element of the Childcare Sufficiency Assessment. To ensure an open and inclusive consultation a variety of different channels have been used to gather responses. The methods used for each of the target consultation groups is shown below
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Children and Young People's Services at York and we tell you when its next papers are published, before the meeting rather than after it.
Capital Programme 2010/11 and 2011/12That the allocation of funding to schemes for 2011/12, as detailed in Annex A – Column A of the report, be approved. ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies