Decision Session - Executive Member for City Strategy agreed this item on Tuesday 1 February 2011. Below is the council's own wording, with the papers it was decided on.
That the Executive Member for City Strategy agrees to: i) Approve the proposals for the preparation and submission of the Best and Final Funding Bid as set out in paragraphs 16 to 19 of the report. ii)Approve a revised budget for the Access York Phase 1 scheme in 2010/11 as proposed in paragraphs 22 to 24 of the report. REASON: To ensure that the Access York Phase 1 project continues to progress satisfactorily and to maximise the potential for DfT funding. That the Executive Member for City Strategy agrees to: i) Approve the proposals for the preparation and submission of the Best and Final Funding Bid as set out in paragraphs 16 to 19 of the report. ii)Approve a revised budget for the Access York Phase 1 scheme in 2010/11 as proposed in paragraphs 22 to 24 of the report. 1. REASON: To ensure that the Access York Phase 1 project continues to progress satisfactorily and to maximise the potential for DfT funding.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for City Strategy
Decision Session 1 February 2011 Executive Member for City Strategy Report of the Director of City Strategy
ACCESS YORK PHASE 1 – UPDATE REPORT
Summary 1. The Access York Phase 1 scheme aims to expand the existing and successful Park & Ride mass transit system whilst assisting with traffic congestion and reducing emissions in the city centre. The improved transport infrastructure will help York to realise its economic growth potential.
2. In support of the above, this report provides an update on the current situation regarding the Access York Phase 1 scheme. It confirms the submission of the Expression of Interest (EoI) to the Department for Transport (DfT) on 4 January 2011 and sets out the ongoing issues associated with the preparation and eventual submission of the Best and Final Funding Bid (B&FFB) in summer 2011, prior to the autumn 2011 deadline.
3. Proposals for preparation of the B&FFB are outlined and information gained in the process of completing the EoI document will assist with this. The report also examines the costs of continuing with the DfT bidding process, both in the remainder of 2010/11 and 2011/12.
Recommendation 4. The Executive Member for City Strategy is recommended to:
• Approve the proposals for the preparation and submission of the B&FFB as set out in paragraphs 16 to 19. • Approve a revised budget for the Access York Phase 1 scheme in 2010/11 as proposed in paragraphs 22 to 24.
Reason: To ensure that the Access York Phase 1 project continues to progress satisfactorily and to maximise the potential for DfT funding. Background Major Scheme Bid Process
5. DfT placed the Major Scheme Bid process on hold for most schemes, including Access York Phase 1, in June 2010, effectively withdrawing the Programme Entry status previously obtained in March 2010.
6. Further information became available from DfT at the end of October 2010, as part of the Comprehensive Spending Review (CSR), and the key points are as set out below.
7. An EoI was required by early January 2011 and this document needed to substantially reflect what will follow later, in the B&FFB to be submitted by or before autumn 2011.
8. The process, between January 2011 and autumn 2011 is as follows: • submit additional detailed value for money evidence not available previously. • submit views from Local Enterprise Partnerships and other interested parties, particularly on wider strategic factors that may not be captured in value for money assessments. • submit the best and final funding bid to DfT (DfT wants this to maximize value for money and increase the local contribution where possible).
9. Decisions will be made by the DfT by the end of 2011, which would re-activate the Programme Entry status for successful schemes and allow them to proceed, with DfT funding in 2012/13.
10. The terms under which the Major Schemes will be funded will be changed with the risk layer concept being removed. This will mean that the DfT will provide a maximum fixed contribution and Local Authorities will have to carry more risk.
11. Preparatory costs will be expended at risk but will only be funded by the DfT if the scheme is progressed. Removal of preparatory costs from the scheme total would potentially make it more attractive in the bidding process.
Expression of Interest 12. The EoI was completed and submitted to the DfT by the 4 January 2011 deadline.
13. The DfT did not issue revised technical guidance prior to 4 January 2011, as indicated, and the EoI was therefore submitted without any comments on this awaited guidance. This was agreed with DfT in advance. 14. The DfT made it clear that nothing in the EoI will be binding until the B&FFB is submitted in the autumn of 2011.
15. The EoI’s main significance for DfT is to give some indication of where the scheme has got to and what is intended as part of the B&FFB process. For CYC it is an opportunity to demonstrate commitment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for City Strategy at York and we tell you when its next papers are published, before the meeting rather than after it.
Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.