City Strategy Capital Programme - 2011/12 Budget Report
ApprovedExecutive3 papers
Decision Session - Executive Member for City Strategy approved this item on Tuesday 1 March 2011. Below is the council's own wording, with the papers it was decided on.
That the Executive Member for City Strategy approves the scheme allocations detailed in Annex 1 to the officer report. REASON: To implement the council’s transport strategy identified in York’s third Local Transport Plan (LTP) and deliver schemes identified in the council’s Capital Programme. That the Executive Member for City Strategy approves the scheme allocations detailed in Annex 1 to the officer report. 1. REASON: To implement the council’s transport strategy identified in York’s third Local Transport Plan (LTP) and deliver schemes identified in the council’s Capital Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for City Strategy
Decision Session 1 March 2011 – Executive Member for City Strategy
Report of the Director of City Strategy City Strategy Capital Programme – 2011/12 Budget Report Report Summary 1. This report sets out the funding sources for the City Strategy Capital Programme and the proposed schemes to be delivered in 2011/12. The report covers the Integrated Transport allocation, the City Walls restoration allocation, and the Property Capital Programme. Other capital schemes in the City Strategy Directorate such as the Accommodation Review and the Community Stadium projects are presented in separate reports.
Recommendations 2. The Executive Member is requested to:
• note the funding pressures on the Transport Capital Programme. • approve the scheme allocations indicated in Annex 1.
Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan (LTP) and deliver schemes identified in the council’s Capital Programme.
Background 3. Subject to approval by Full Council on 24 February 2011, the City Strategy Capital Programme budget for 2011/12 is anticipated to be £4,128k, which is made up of two main sections: Planning & Transport (£1,999k), which includes Integrated Transport & City Walls schemes, and Property (£2,129k). The Planning & Transport budget includes £1,549k of Local Transport Plan (LTP) funding, and £300k funding from developer contributions.
4. Throughout the second Local Transport Plan period (2006/07 to 2010/11), the LTP Integrated Transport annual funding decreased from £4,478k in 2006/07 to £2,986k at the start of 2010/11, as part of a revised formula based approach. 5. Following the in-year budget cuts announced in June 2010, the LTP Integrated Transport allocation for 2010/11 was reduced further to £2,236k. The total Integrated Transport budget at the start of 2010/11 was £6,910k including Regional Funding Allocation (RFA) supplement, Cycling City Grant, Road Safety Grant and Developer Contributions. Following an initial review of budget allocations in June 2010, the government reduced the LTP and RFA elements and deleted the Road Safety Grant. The final Monitor 2 2010/11 Integrated Transport budget was therefore reduced to £5,804k.
6. The LTP Integrated Transport funding available for future years is significantly lower than previous allocations, as indicated in the following table. The Structural Maintenance LTP budgets are also provided for comparison.
7. The full City Strategy Capital Programme also includes funding from council resources for maintenance of the City Walls, and the Property Capital Programme, which is also funded from council resources.
8. The funding allocated to the 2011/12 Integrated Transport Capital Programme and the comparable 2010/11 Integrated Transport Capital Programme at Monitor 2 (December 2010) is shown in the following table.
Integrated Transport Budget 2010/11 Funding 2011/12 (M2) £000s £000s LTP Settlement 2,236 1,549 Regional Funding Allocation 1,680 - Developer Contributions 650 300 Cycling City Grant 1,055 - CYC Resources 60 60 Other Grant Funding 123 - Total Budget 5,804 1,909
9. The lower funding levels means that the scope of improvements possible to deliver is significantly reduced unless alternative funding sources can be identified. The government have reduced the number of funding streams available for transport schemes from 26 to 4:
• Block funding for highways maintenance (capital) • Block funding for Integrated Transport schemes (capital). • A local sustainable transport fund (capital and revenue) • Major schemes (capital)
10. The block funding elements for maintenance and Integrated Transport schemes are distributed on a formula basis, whereas the Local Sustainable Transport Fund and Major Scheme funding are allocated on a bid basis.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for City Strategy at York and we tell you when its next papers are published, before the meeting rather than after it.
Low Poppleton Lane Road Closure PetitionThat the Executive Member for City Strategy confirms the current provision for the No. 10 bus service on Low Poppleto...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.