City of York Council

Covenant of Mayors SEAP Submission and Sustainable Development Update

Approved Executive 6 papers

Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 12 April 2011. Below is the council's own wording, with the papers it was decided on.

Item195

Resolved

(i) That the draft SEAP at Annex 2 be approved. REASON: To enable the Council to submit the SEAP to the EU Covenant of Mayors team. (ii) That the significant actions required to deliver a 20% reduction in city-wide CO 2 emissions by 2020 be noted. REASON: To understand the scale of action required to achieve this reduction. (iii) That the proposed revisions to the Sustainable Development Board, and the formation of a renewable energy generation task and finish group, as set out in Annex 3, be approved. REASON: To ensure that the Council can take an enhanced leadership role installing and promoting renewable energy internally and across the City. (iv) That the risks of delivering the SEAP, specifically the risk of delivering such challenging city-wide targets that rely on limited existing staff and partnership working to achieve them. REASON: To highlight the ambition and challenge ahead in meeting the SEAP and CCFAP, where co-ordination of action and delivery of projects is on a city-wide scale. (i) That the draft SEAP at Annex 2 be approved. 1 REASON: To enable the Council to submit the SEAP to the EU Covenant of Mayors team. (ii) That the significant actions required to deliver a 20% reduction in city-wide CO 2 emissions by 2020 be noted. REASON: To understand the scale of action required to achieve this reduction. (iii) That the proposed revisions to the Sustainable Development Board, and the formation of a renewable energy generation task and finish group, as set out in Annex 3, be approved. 2 REASON: To ensure that the Council can take an enhanced leadership role installing and promoting renewable energy internally and across the City. (iv) That the risks of delivering the SEAP, specifically the risk of delivering such challenging city-wide targets that rely on limited existing staff and partnership working to achieve them. REASON: To highlight the ambition and challenge ahead in meeting the SEAP and CCFAP, where co-ordination of action and delivery of projects is on a city-wide scale.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Summary

1. The purpose of this report is to outline City of York’s commitments to the EU Covenant of Mayors (CoM) campaign and seeks approval of the Sustainable Energy Action Plan, a core requirement of the CoM campaign. The report also provides a brief update on other sustainability work being carried across CYC / York.

Background

2. The City of York is committed to tackling climate change and to reducing city-wide carbon emissions. This commitment was formalised in 2008 through the Sustainable City Chapter of the Sustainable Community Strategy. This committed the city to the creation of a climate change strategy and to reduce York’s carbon footprint.

3. The city is also committed to delivering 3 separate city-wide carbon reduction targets:

1. a 20 per cent reduction in CO2 emissions by 2020 (Covenant of Mayors http://www.eumayors.eu/;

2. a 40 per cent reduction in CO2 emissions by 2020 (Friends of the Earth ‘Get Serious About CO2’ Campaign www.foe.co.uk/community/campaigns/climate/get_serious_2018 7.html

3. an 80 per cent reduction in greenhouse gas emissions by 2050 (UK Climate Change Act/ Climate Change Framework for York 2010-2015).

Specific targets

Achieving a 20% reduction in city – wide carbon emissions

4. To further support the objective to tackle climate change locally, a full Council resolution was passed on 3rd December 2009 committing City of York to the CoM campaign, the agreement was formally signed on 5th January 2010.

5. Annex 1 provides an full account of the various CoM requirements that York must now meet.

6. A requirements as a signatory to the CoM campaign is to produce a Sustainable Energy Action Plan (SEAP) for York. This SEAP is required to set out how to deliver at least a 20% reduction in carbon dioxide (CO2) emissions by 2020 (based on a 2005 baseline year).

Other targets – achieving a 40% reduction by 2020 and 80% reduction by 2050

7. In addition to this commitment to tackle climate change through the CoM commitment and the Sustainable Community Strategy, the City of York developed a consultation draft Climate Change Framework (CCF) and Climate Change Action Plan (CCAP). For the purpose of this report these two documents will be collectively abbreviated to CCFAP). These documents were approved by the Executive on 19th October 2010 and are available from. www.york.gov.uk/environment/sustainability/climatechange/2fr amework/).

8. The Framework is the overarching ambition of York to accelerate actions to reduce carbon emissions across the city. It illustrates the actions already on-going across York and highlights the key areas the city needs to begin to drive forward in order to eventually reach the national Climate Change Act1 (2008) 80% reduction in CO2 emissions by 2050. The Framework is to be used by the organisations across the city, including the council and WoW (Without Walls) partnership, to focus and drive forward coordinated action to tackle climate change.

9. The Action Plan for York is a combination of specific action plans. The plans are broken into mitigation actions, actions that will reduce emissions from across York, and adaptation actions, action that will help the city to prepare and adapt to climate change. The Action Plan is the delivery mechanism to achieving the Framework and the 10 key areas it aims to tackle.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CoM and Sustainable Development UpdateAppendix 1 67 KB Download
PDF
CoM and Sustainable Development UpdateAppendix 2a 362 KB Download
PDF
CoM and Sustainable Development UpdateAppendix 2b 112 KB Download
PDF
CoM and Sustainable Development UpdateAppendix 3 104 KB Download
PDF
CoM and Sustainable Development UpdateAppendix 4 217 KB Download
PDF
Covenant of Mayors SEAP Submission and Sustainable Development UpdateReport 151 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
AW
Councillor Andrew WallerChair, present
NA
Councillor Nigel AyreCommittee Member, present
SG
Councillor Steve GallowayCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
JM
Councillor Jonathan MorleyCommittee Member, present
AR
Councillor Ann ReidCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AD
Councillor Andy D'AgorneAttendee, in attendance

On this subject at York

Search all
  1. Covenant of Mayors SEAP Submission and Sustainable Development UpdateThis decision
  2. Renewing City of York Council's Pledge to Covenant of MayorsAgreed
  3. Refreshing York's Commitment to the Covenant of Mayors for Climate & EnergyDecided

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies