(i) That the results of the audit and fraud work undertaken in 2010/11 be noted. (ii) That the opinion of the Head of Internal Audit on the adequacy and effectiveness of the council’s internal control environment be noted. (iii) That the significant control weaknesses identified during the year which are relevant to the preparation of the Annual Governance Statement be noted. REASONS: (i) To enable Members to consider the implications of audit and counter fraud findings. (ii) To enable Members to consider the opinion of the Head of Internal Audit. (iii) To enable the Annual Governance Statement to be prepared.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Summary 1 This report summarises the outcome of audit and fraud work undertaken in 2010/11 and provides an opinion on the overall adequacy and effectiveness of the council’s internal control arrangements.
Background 2 The work of internal audit is governed by the Accounts and Audit (England) Regulations 2011 and the CIPFA Code of Practice for Internal Audit in Local Government (2006). In accordance with the code of practice, the Head of Internal Audit is required to report to those charged with governance on the findings of audit work, provide an annual opinion on the council’s control environment and identify any issues relevant to the preparation of the Annual Governance Statement.
3 Since 1 April 2009, the council’s internal audit, counter fraud and information governance services have been provided by Veritau Limited, a company jointly owned by the City of York Council and North Yorkshire County Council.
4 Audit work was undertaken across the council’s services and activities in accordance with an internal audit plan, which was approved by this Committee in April 2010.
2010/11 Internal Audit, Counter Fraud & Information Governance Work 5 The results of completed audit work have been reported to service managers and relevant chief officers during the course of the year. In addition, summaries of all finalised audit reports have been presented to this committee as part of regular monitoring reports. Details of audits finalised since the last report to this committee in April 2011 are included at Annex 2.
6 Overall, internal audit delivered 95.3% of the 2010/11 internal audit plan by 30 April 2011 (against a target of 93%). The service also achieved a positive customer satisfaction rating of 100% (against a target of 95%), and agreed actions to address 100% of high priority issues identified through audit work (against a target of 90%).
7 All of the actions agreed with services as a result of internal audit work are followed up to ensure that the underlying control weaknesses are addressed. The results of follow up work are summarised twice yearly for this committee (the last report was in April). While overall progress in implementing agreed actions remains good, one specific area does require further attention to ensure agreed actions are undertaken within realistic timescales..
8 Counter fraud work was undertaken in accordance with the approved plan. A summary of the work completed during the year was presented to this committee as part of the last audit and fraud monitoring report on 19 April 2011. Service developments in relation to counter fraud work included the following.
• The successful completion of a pilot project to investigate housing related fraud. A total of 93 cases were referred to the team for review. Investigation work resulted in five properties being recovered from tenants. Work is now ongoing to establish longer term arrangements for the investigation of housing fraud.
• The introduction of new fraud risk assessment arrangements to improve the targeting of counter fraud resources. This has resulted in a number of new counter fraud initiatives and other specific work, for example social care charging.
9 In March 2010, the Executive approved a strategy for improving Information Governance arrangements based on developing the council’s information governance policy framework and applying a quality assurance scheme devised by central government, known as the “Maturity Model”. In accordance with the Strategy, the Corporate Information Governance group (CIGG) has begun work, chaired by the council’s Senior Information Risk Owner (SIRO) – the director of Customer and Business Support Services, Ian Floyd. CIGG is attended by an information governance champion from each directorate as well as representatives from Veritau’s Information Governance team (IGT).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna...
Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.