Decision Session - Executive Member for Children Young People and Education noted this item on Tuesday 11 October 2011. Below is the council's own wording, with the papers it was decided on.
( i ) That the progress made against service plan improvement actions and performance measures be noted. (ii) That the revised timescale for completion of action that is in progress but where the original estimated timescale has slipped (as detailed in paragraphs 6 and 9 of the report) be approved. REASON: To ensure that the Cabinet Member is informed of financial performance, progress against service plan improvement actions and performance measures. ( i ) That the progress made against service plan improvement actions and performance measures be noted. (ii) That the revised timescale for completion of action that is in progress but where the original estimated timescale has slipped (as detailed in paragraphs 6 and 9 of the report) be approved. REASON: To ensure that the Cabinet Member is informed of financial performance, progress against service plan improvement actions and performance measures.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Children Young People and Education
Cabinet Member Decision Session: 11th October 2011 Education, Children & Young People’s Services
Report of the Assistant Director – Communities and Culture
Quarter 1 April – June 2011, Finance and Performance update
Summary 1. The purpose of this report is to provide the Cabinet Member for Education, Children & Young People with an update on financial performance, progress against service plan improvement actions and performance measures. The Status Card for quarter 1 actions is attached at Appendix 1 and the status for performance measures is at paragraph 9.
Financial Performance 2. Leisure and Culture is forecast to achieve £369k against an in year budget savings target of £410k. Savings are being achieved through service reviews and improvements. The £41k shortfall from the savings target is due to additional one off costs incurred during the restructure of the music service. Full year savings will be achieved in 2012/13.
3. The approved 2011/12 revenue budget for Leisure and Culture is summarised as follows:
Net Forecast Forecast Budget Variation Variation £’000 £’000 % Arts and Heritage - no significant variances 2,350 +0 +0.00 Arts and Culture Education - full year savings not met due to one off redundancy costs. Note that there is a full year saving of £75k achieved through the restructure.
277 +187 +67.51
1 Net Forecast Forecast Budget Variation Variation £’000 £’000 % Adult and Community Education - 2011/12 savings targets were deducted from base budget, assuming a net nil service. The forecast is based on achievement on a net nil position. -41 +0 +0.00 Equalities - no significant variances 128 +0 +0.00 Libraries and Archives - Shortfall on income targets 2,993 +34 +1.14 Leisure Support - no significant variances 33 +0 +0.00 Neighbourhood Management Unit - no significant variances. Any unachieved savings as a result of the staff restructure part year effect will be offset by under spends on vacant posts. 2,299 +0 +0.00 Sport and Active Leisure - A shortfall in budgeted rental income for Waterworld. The full year effect of a previous year's budget saving on rents and rates is greater than the actual level of saving achieved. This is offset by under spends in other areas. 2,356 -45 -1.91 Young People and Play - no significant variances 326 +0 +0.00 Total (Leisure & Culture portfolio) 10,721 +176 +1.64
Service Plan Actions and Performance Indicator Headlines 4. As part of Communities and Culture’s commitment to deliver excellent services the service set a very challenging service improvement plan for 20011/12, with 72 actions to be completed during 2011/ 2012, 18 of which coming under the portfolio for Education, Children and Young People’s Services.
2 Quarter 1 Service Plan Action update
5. For quarter 1 - 4 Service Plan actions were due to be completed by June 2011 of which 3 have been completed within the timescale with 1 action where the estimated timescale for completion has passed. This action is expected to be completed by March 2012. There are no actions where the deadline has passed and work has not commenced.
.
3 6. Outlined below is the action where the estimated timescale has slipped.
Action Comments In conjunction with York Cares The Head of Libraries is now on devise new modules to extend the the steering group and is Children’s University programme developing a Library module. Also including Libraries & Archive and work is underway to enable Shine Sport & Active Leisure. C&C facilities providers to become accredited gain accreditation to become leaning destinations learning destinations
7. Completed Actions within quarter 1 :
• Support has been provided to the campaigns of the Youth Council to assist in the promotion of Shine including the young people's festival and Café. The Youth festival took place 16 July 2011 at Rowntrees Park.
• Adult Learners Week has been celebrated and plans are underway for next year
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Children Young People and Education at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.