That the Cabinet Member recommend to Cabinet that the following be approved 1 : · The schemes to be developed from within the available resources of the approved capital programme, as detailed in the report. · The proposal to modernise and develop Knavesmire Primary School to enable the school to provide two forms of entry, meeting the local demand for places at the school. · The revised schemes and funding of the capital programme, as detailed in Annex A of the report. REASON: To enable the effective management and monitoring of the capital programme. That the Cabinet Member recommend to Cabinet that the following be approved 1 : · The schemes to be developed from within the available resources of the approved capital programme, as detailed in the report. · The proposal to modernise and develop Knavesmire Primary School to enable the school to provide two forms of entry, meeting the local demand for places at the school. · The revised schemes and funding of the capital programme, as detailed in Annex A of the report. REASON: To enable the effective management and monitoring of the capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Children Young People and Education
Decision Session – Cabinet Member for 13 December 2011 Education, Children and Young People’s Services
Report of the Director of Adults, Children and Education
Education, Children and Young People’s Capital Programme Update: 2011/12 – 2013/14
Summary 1. The purpose of this report is to: • inform the Cabinet Member of recent progress on major schemes within the Education, Children and Young People’s Capital Programme • inform the Cabinet Member of new schemes proposed for 2012/13, and of revisions to the programme
Background 2. The current approved Children’s Services Capital programme shows gross capital expenditure of £15.412m in 2011/12. This is detailed in Annex A.
Consultation 3. All of the schemes considered in this report have been, or will be, subject to extensive consultation with governing bodies, key partner agencies, local councillors and residents in the locality of the individual schemes during development.
Analysis 4. Progress reports on each of the schemes are contained in the following paragraphs. Devolved Formula Capital (Scheme Budget 2011/12 - £475k)
5. This funding is made available to schools and the full amount of £475k has been devolved in 2011/12. The funding made available from the DfE through this route has been reduced by approximately 80% compared to 2010/11 levels. Decision making on this devolved funding continues to be delegated to school governing bodies.
Targeted Capital Fund (14-19, SEN and Disabilities Provision) (Remaining Scheme Budget - £3,428k)
6. The remaining budget under this heading has been allocated as previously reported to a small number of significant schemes. These include the extension and refurbishment of Applefields School, significant works at Canon Lee School including the provision of an all-weather pitch and refurbishment work at the old Clifton Without Junior building which Canon Lee School will be taking over, and refurbishment works at Clifton Green Primary. The following paragraphs contain further details for each of these schemes.
Applefields Special School (Scheme budget - £1,500k)
7. This scheme is designed to improve the accommodation and facilities for students at Applefields Special School. Demand for places at the school remains strong and the school continues to be oversubscribed. In addition the increased complexity of needs of students results in further demands on physical space through their use of more specialist equipment. The current accommodation therefore does not fully meet the needs of the students and staff and the scheme will seek to provide more flexible accommodation. The main work is the building of an extension at the rear of the existing school comprising of two classrooms, a drama/dining hall and a multi sensory room. Contractors commenced on site in August 2011 and this phase of the work is expected to be completed by March 2012, the second phase of the work is expected to complete in May 2012. As part of this work two existing temporary classrooms will be removed from the site. Canon Lee School (All Weather Pitch) (Scheme budget - £470k)
8. The project to install an all weather pitch at Canon Lee School is now almost complete. It is expected that this facility will be available for use in early 2012.
Canon Lee School (refurbishment of Clifton Without Junior School building) (Scheme Budget - £325k)
9. Following the movement of Clifton Without Junior School pupils to the new Clifton with Rawcliffe Primary School, Canon Lee School will be utilising the old junior school site. Refurbishment works are required to these buildings prior to the school moving in. At present this work is scheduled to begin in January 2012 following the handover of the building, and is currently targeted for completion by April 2012, in time for use in the summer term. The school have contributed £40k of their devolved formula capital towards this project.
Clifton Green Primary School (Scheme budget £150k)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Children Young People and Education at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.