(i) That the report be noted. (ii) That Option 1-‘Purchase of Land for Askham Bar and Poppleton Bar before Expiry of Land Options’ be approved which includes; · Purchase of land for the Askham Bar site in accordance with the conditional agreement. · Purchase of Phase 1 land for the Poppleton Bar site in accordance with the conditional agreement. · Payment of the deposit for Phase 2 land for the Poppleton Bar site in accordance with the conditional agreement. · Authorisation of the Director of CBSS to reprofile the capital plan in accordance with the revised payment ... view the full minutes text for item 118.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Staffing Matters & Urgency Committee 19 March 2012
Report of the Director of City Strategy
Access York Park & Ride Land Purchase Summary 1. This report recommends that the Committee approves the purchase of land at Poppleton Bar and Askham Bar to enable the proposed construction of the sites to progress in accordance with the delivery programme.
2. Options for the purchase of the land expire on 31 March 2012 which allowed significant slippage in the original programme. Owing to the delays in the project caused by the government’s suspension of the Major Scheme programme and unwillingness of the landowners to extend the options under the original conditions it is considered advantageous to purchase the land now. The Council’s capital plan will need to be reprofiled to accommodate this change. Background 3. Expanding the Park & Ride network is a key Council Plan priority under the ‘Get York Moving’ banner. The full Access York Phase 1 project involves:
• The construction of 3 new Park & Ride sites at Askham Bar, Poppleton Bar and Clifton Moor. • A major upgrade to the A59/A1237 Outer Ring Road roundabout. • Associated bus priority measures.
4. The original programme following approval by the Department for Transport (DfT) in March 2010 was for the sites to be operational by the summer of 2012 (construction start in spring 2011). 5. Following suspension of the Major Scheme programme by the government in June 2010 a Best and Final Bid was submitted in September 2011. The overall scope of the project to be delivered in the first phase has been reduced to 2 sites (Poppleton Bar and Askham Bar). This revised project was approved by the DfT in November 2011. Alternative ways to fund the delivery of the Clifton Moor site are being investigated. Land Purchase 6. All of the sites require land to be purchased. Securing land was identified as a key risk at the commencement of the project. To reduce the risk and provide cost certainty options (conditional agreements) to purchase the land were agreed with the landowners. Non-returnable deposits were paid against the land purchase cost in return for the option to purchase extending for approximately 3 years to 31 March 2012. At the time that the options were agreed it was anticipated that the land would be purchased in early 2011 meaning that approximately 1 year of programme slippage could be accommodated. 7. Approximately 70% of the cost of the project including land is funded by the DfT providing the scheme receives full approval from the DfT. Until full approval has been obtained (only possible to submit for approval after tenders for construction have been received) all costs are considered to be expended at the risk of the council.
8. The DfT have confirmed that it would not be possible to submit the project for Full Approval without the price of the land being confirmed and the purchase mechanism identified. Askham Bar
9. The majority of the car park area for the new Askham Bar site is to be constructed on the former Sim Hills landfill tip which is owned by the council. A local landowner owns the remainder of the site. A small area of land required for the bus only exit near to the existing Park & Ride site has already been purchased. The option for the land runs out on 31 March 2012.
Poppleton Bar 10. A local landowner owns the land required for both phases of the proposed Poppleton Bar Park & Ride site. Separate options for each phase of the project were agreed in 2009 (phase 1 - 600 spaces, phase 2 – a further 650 spaces). The option for phase 1 runs out on 31 March 2012. If the option fee for the 2nd phase is paid by 31 March 2012 then the option for this land would be extended until 31 March 2017.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of Press and Public (5.32pm)That the press and public be excluded from the meeting during the consideration of Annex 1 to Agenda Item 7 on the gr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.