CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Staffing Matters and Urgency Committee, Monday 2 April 2012 at 1.00pm

Urgent Item: Hungate Haymarket Car Park Site

Noted Committee 1 paper

Staffing Matters and Urgency Committee noted this item on Monday 2 April 2012. Below is the council's own wording, with the papers it was decided on.

Item125

Resolved

(i) That the report be noted. (ii) That the additional archaeological excavation works at £112k be approved. (iii) That the capital receipt be used to fund the capital expenditure. (iv) That the capital expenditure be included in the capital programme in the year 2013/14. (v) That the company that completes the work would fund the expenditure until 2013/14. (vi) That if the capital receipt is not realised at an amount to cover the expenditure, then it be noted that potential additional borrowing may be required, subject to a review of the overall capital programme. (vii) That the finance costs as a result of the timing differences between the archaeological investigation costs incurred and the sale of the capital receipt be funded from property services revenue budget. REASON: To enable the archaeological investigative work on the site to proceed in the most cost effective manner.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Staffing Matters and Urgency Committee

Staffing & Urgency Committee 2 April 2012

Report of the Cabinet Member for Corporate Services

Hungate Haymarket Car Park Site

Summary 1. This report seeks urgent member approval to proceed with additional archaeological excavation works at Hungate Haymarket car-park site at a cost of £112k.

2. At Cabinet on 6 December 2011 members approved the current phase of archaeological investigation work at the Hungate site, with the funding of the work being from the future capital receipt at a cost of £115k.

3. The current phase of work is due to complete on 30 March 2012 and therefore the most cost effective option is to proceed with the additional works straight away.

4. The original capital receipt to be realised from the Hungate site is allocated to fund the capital programme. The current phase of investigation works at £115k are proposed to enhance the future value of the receipt to be realised. In addition, the archaeological excavation works at £112k are unavoidable costs that need to be incurred in order to maintain / increase the value of the capital receipt to be realised. Background

5. The current phase of archaeological work at the Haymarket car- park has revealed an unexpectedly high density and height of burials which will pose a problem for future development of the site.

6. The current phase of work, at £115k, has been designed to map the extent of, but not remove, human remains associated with the medieval cemetery of All Saints Peaseholme Green. The excavation has demonstrated that these remains are widespread and lie very close to the modern ground surface. 7. It is likely that any future sale and/or development of this site would be “de-risked” if the excavation works were carried out and it would be more cost effective if City of York commissions the excavation of these human remains to follow straight on from the current phase of work.

7. This excavation will be an additional cost of £112k in the best case scenario (a) and (b) below. This has been estimated to be

(a) £66.5k to excavate the human remains which is a direct cost attributable to bringing the site into a condition to be operational and associated archaeological deposits

(b) a further mutually exclusive sum of up to £45k for the associated archaeological deposits to be deposited at the archive with the Yorkshire Museum which would be a planning requirement and therefore an unavoidable cost.

(c) If the work is not done now then the site will be covered up with an estimated additional cost of £10k to uncover it at a future date.

8. The current phase of work will end on 30th March 2012 and therefore to achieve the most cost effective option it is most appropriate to proceed now.

9. This additional capital expenditure of £112k will be included in the capital programme in the year 2013/14 which is also when the capital receipt is scheduled to be realised.

10. The company to complete the works will fund the additional costs until 31 March 2014 or until the site is sold whichever comes first. If the site is not sold prior to the Council incurring the capital expenditure then prudential borrowing will be used and Property Service’s revenue budget will incur the associated finance costs.

11. When the site is sold, if the amount realised is not sufficient to cover the level assumed in the capital programme, (which includes the original amount, plus the £115k approved at cabinet 6/12/11 and the £112k for the excavation works in this report) then there will be a shortfall in the capital programme. This will need to be considered in the future and potentially additional borrowing may be required. 12. It should be noted that the realisable value of the Hungate Site will be considered alongside the ongoing capital receipt schedule reviews done at regular intervals and included in capital programme quarterly monitoring reports to cabinet.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Urgent Item: Hungate Haymarket Car Park SiteReport 69 KB DownloadRead as text

At this meeting

Whole meeting
121Exclusion of Press and PublicDecided 122MinutesApproved 124RedundancyNoted
125Urgent Item: Hungate Haymarket Car Park SiteThis decision

Who was there

6 of 6 attended
JA
Councillor James AlexanderChair, present
TS
Councillor Tracey Simpson-LaingSubstitute, present as substitute
JG
Councillor Julie GunnellCommittee Member, present
SF
Councillor Sandy FraserCommittee Member, apologies, sent representative
CR
Councillor Carol RuncimanCommittee Member, present
IG
Councillor Ian GilliesCommittee Member, present

More from York Staffing Matters and Urgency Committee

All decisions
MeetingDecisionOutcome
29 Jun 2026 Exclusion of Press and Public (5.32pm)That the press and public be excluded from the meeting during the consideration of Annex 1 to Agenda Item 7 on the gr... Decided Open
29 Jun 2026 Minutes (5.34pm)That the minutes of the Staffing Matters and Urgency Committee held on 26 January 2026 be approved and then signed by... Approved Open
29 Jun 2026 Workforce Profile as at Quarter 4 2025/26 (5.35pm)That the Staffing Matters and Urgency Committee noted: i. The workforce profile provided in the report and Annex 1 ii... Noted Open
29 Jun 2026 Redundancy, Pension and Exit Discretions Expenditure (5.58pm)That the Staffing Matters and Urgency Committee noted the expenditure and cases that had been approved. Reason: To pr... Noted Open
29 Jun 2026 Work Plan (6.03pm)That members considered the work plan for the municipal year 2026-2027. Reason: To ensure the Committee maintains a p... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies