That the application be approved subject to the conditions listed in the report. REASON: In the opinion of the Local Planning Authority the proposal, subject to the conditions listed above, would not cause undue harm to interests of acknowledged importance, with particular reference to provision of a campus at Heslington East, provision of student housing, sustainability, visual impact, flood risk, landscaping, and transport issues. The application therefore complies with policies GP1, GP4a, T4, ED9, ED10, GP9 and GP15a of the City of York Local Plan Deposit Draft.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Date: 17 January 2013 Ward: Heslington Team: Major and Parish: Heslington Parish Commercial Team Council
Reference: 12/03617/REMM Application at: Proposed University Campus Lying Between Field Lane And Low Lane A64 Trunk Road And Hull Road York For: Reserved matters details of student residences in 8no.buildings (620 bedrooms and Dean's flat) with social hub building, cycle parking and landscaping granted under outline permissions 04/01700/OUT and 08/00005/OUT By: University Of York And Evans Advisory Ltd Application Type: Major Reserved Matters Application (13w) Target Date: 27 February 2013 Recommendation: Approve
1.0PROPOSAL
1.1Reserved matters application for the erection of a new college (provisionally known as College 9) at Heslington East campus. The proposals would provide living accommodation for the college dean, five tutors and 615 students. The proposal is part of Cluster 2 of the Heslington East campus for the University of York. The campus was granted outline planning permission by the Secretary of State in June 2007 (04/01700/OUT) and varied in 2008 (08/00005/OUT).
1.2The application would provide approximately 15,800sqm of floorspace on a site of 4.34ha. The works mainly comprise (a) five 4 and 5-storey residential blocks (buildings A to E) comprising 44 12-bed flats and one 8-bed flat (b) four 3-storey residential terrace blocks (buildings F, G and H) comprising seven 12-bed houses (c) a 2-storey nucleus building comprising college reception, provost office, common rooms, launderette, meeting room and storage space (d) cycle parking for 310 residents' cycles and 20 visitors' cycles (e) an electricity sub-station (f) six accessible parking spaces (g) refuse/recycling facilities and (h) landscaping. Main materials would be red brickwork, timber cladding and large areas of glazing. Roofs would have either a profiled metal or single ply membrane finish.
1.3This would be the third residential college at the campus (following Goodricke and Langwith) and the ninth at the University of York.
2.1Development Plan Allocation City Boundary York City Boundary 0001
DC Area Teams East Area (1) 0003
2.2Policies:
CYGP1 -Design
CYGP4A -Sustainability
CYGP9 -Landscaping
CGP15A -Development and Flood Risk
CYED9 - University of York New Campus
CYED10 - Student Housing
CYT- Cycle parking standards
3.0CONSULTATIONS
INTERNAL
3.1Highway Network Management - The total number of residents' cycle parking spaces is in accordance with the agreed level of provision (1 space per 2 bedrooms) but they are unevenly distributed across the college: too many in the north, too few in the south. Whilst this represents poor design it is not sufficient to warrant a formal objection.
3.2Environment, Conservation and Sustainable Development (Landscape) - Whilst the college would be further to the east than shown on the approved masterplan - and would thereby interfere with the proposed green wedge - the width of the green wedge would be maintained. No objections.
3.3Major Projects (Renaissance) - No objections. Include suitable conditions.
3.4Flood Risk Management - No objections. Add standard drainage condition.
3.5Environmental Protection Unit - No objections. Environmental issues are covered by various conditions of the outline consent.
3.6Heslington Forum including Heslington Parish Council - The application does not include a statement of community involvement. However, in accordance with the established protocol, the proposals were presented to the community forum on 3 December 2013. No formal representations have been made by forum organisations.
3.7Police Architectural Liaison - No concerns. The proposal will provide a safe and accessible environment where crime and disorder, and the fear of crime, do not undermine quality of life or community cohesion.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies