( i ) Officers be authorised to agree the provisions of the legal agreement and complete the document. (ii) The conditions as amended be imposed on the permission. REASON: In order that permission can be granted subject to the legal agreement and the schedule of conditions as detailed in the committee report.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1.1The application for the mixed use redevelopment of the former Terry’s Factory site was approved by the Council's Planning Committee on 3rd February 2010, subject to the completion of a legal agreement under section 106 of the Town and Country Planning Act. The Heads of Terms for the agreement were agreed at the meeting. This report seeks to update Members on the position with the draft agreement which the new site owners wish to complete quickly to allow the planning permission to be issued and development to commence on site (following submission and approval of reserved matters). It also seeks to update and reassure Members in respect of any relevant change in planning policy and the site circumstances since the application was considered at Committee. 1.2 The Heads of Terms for the agreement as Minuted were:- i) Affordable housing at 82 units, being 30.3% of the total, (32 x 2 bed flats, 7 x 2 bed houses, 10 x 3 bed houses) for affordable rent together with units (22 x 2 bed flats, 1 x 2 bed house and 10 x 3 bed houses) for discounted sale or affordable housing provision at 37% subject to Application Reference Number: 12/02104/PREAPP Item No: 5 Page 1 of 32 receipt of Social Housing Grant or other public subsidy (distribution approximately pro rata). ii) A contribution towards local education provision of £1,166,881
iii) A contribution towards off site public open space facilities of £160,249
iv) Funding to be agreed between the Local Planning Authority, acting through the Chair and Vice Chair, and the Developer to allow for the detailed design, site supervision and construction of the following highway mitigation measures: • The introduction of traffic signals at the junction of Knavesmire Road with Tadcaster Road and Mount Vale. • The introduction of UTC control and CCTV equipment at the St. Helens Road/Tadcaster Road junction. • The introduction of a signal controlled toucan (cycle and pedestrian) facility on Bishopthorpe Rd between the main entrance and the car park/ Sustrans route to the river. • The provision of a new zebra crossing on Campleshon Road adjacent to Knavesmire Primary School. • Signalling changes at the junction of Bishopthorpe Road and Scarcroft Road aimed at improving capacity for traffic flow. • Improvements to the pedestrian/cycle route (Sustrans Route 65) between Bishopthorpe Road and the riverside path, including alterations on Bishopthorpe Road itself. Measures to include localised widening, smoothing of gradient and provision of street lighting. • Additional cycle route signs, as agreed, to be erected along the route between the development site and heading north through the South Bank district. • The introduction of an additional 26 spaces at the new Askham Bar Park and Ride site.
v) Funding to be agreed between the Local Planning Authority, the Racecourse Operator and the Developer to provide a highways/landscaping scheme to connect the Racecourse and the application site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.