Six Monthly Update Report on Major Development Schemes in York

Noted Scrutiny 1 paper

Economic Development and Transport Policy and Scrutiny Committee noted this item on Tuesday 25 March 2014. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

That the report be noted. Reason: In order to provide the Committee with a regular update on developments in the city.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Economic Development and Transport Policy and Scrutiny Committee

Economic & City Development Overview & 25 March 2014 Scrutiny Committee

Report of the Assistant Director for Development Services, Planning & Regeneration

Six Monthly Update Report on Major Development Schemes in York

Summary 1. This report provides Members with an overview and update in relation to the major development and planning proposals in the city at this time.

Background 2. Since the national economic downturn and credit crunch of 4 years ago CYC Officers, led by the new Regeneration Team (previously Major Development Projects & Initiatives), have continued to keep an open dialogue with developers in York in order to consider how approved but stalled sites may come forward without any significant lessening of overall planning aims in terms of mixed and balanced communities, sustainability and quality in design.

3. Officers have agreed changes of use (employment to residential), changes in types and size, layout, design and density as well as reductions in affordable housing numbers and Section 106 financial contributions. These revisions to approved and comprehensively consulted approvals illustrate the determination of the City Council to support the delivery of good quality new development in the city.

The Development Sites

Terry’s

4. New owners Henry Boot and David Wilson Homes were announced in April 2013 following Savills report on bids. CYC Officers have worked diligently with the developer team in order to consider revisions and an ambitious timetable for Phase 1 of the originally approved masterplan (residential on the northern part of the site). Lowering of the affordable housing element of the scheme from 30% to 25% was approved at Planning Committee in October 2012, and to 20% this year following re- running of the Dynamic Model.

5. The planning application for the first phase (85 new homes and a local convenience store) on the northern half of the site was approved by CYC Planning Committee 19th December 2013. Work on site has begun, with the first homes expected to go on sale in the summer of 2014.

6. Pre-application discussions are now focusing on the commercial elements of the original scheme, and a CYC Project Team has been set up to work with the developers in order to consider proposed revisions to the approved plan. Expressions of interest in office and other business uses are said to be low, and the developers are proposing more residential throughout the site.

Nestle

7. Following feedback that the commercial/ employment element of this mixed use scheme was not receiving a great deal of interest, CYC planners have considered where revisions can be made, especially in terms of increasing the commercially more appetising residential offer on site. Agents for Nestle have remarketed the site and are now working with developers and the CYC Regeneration team in order to bring forward development in 2014.

Hungate

8. Led by CYC Regeneration a series of very productive pre application project meetings has taken place in order to progress (1) Phase 2 reserved matters revisions, and (2) revisions to the mix of uses and layout/ design in the approved Masterplan. The Project Group includes developer and architect representatives as well as a cross-directorate team of CYC Officers.

9. Viability work and affordable housing negotiations have progressed in parallel and with the resolution of these discussions the planning application for Phase 2 was approved by Planning Committee on 20th February 2014.

10. The approved development comprises 195 apartments, 31 of which will be affordable to local people in housing need, and some A3 retail use at ground floor level. The apartments overlook the River Foss to the south and new areas of public space to the north and west.

11. The development sits next to 172 apartments already occupied in Phase 1 and, with the new Hiscox offices being built this year and St John’s University student apartments already occupied, the full regeneration of the Hungate area is taking shape.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Six Monthly Update Report on Major Development Schemes in YorkReport 93 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
AS
Councillor Anna SemlyenChair, present
NB
Councillor Neil BarnesCommittee Member, present
SB
Councillor Stephen BurtonCommittee Member, present
IC
Councillor Ian CuthbertsonCommittee Member, present
AD
Councillor Andy D'AgorneCommittee Member, present
JR
Councillor Joseph RichesCommittee Member, present
JW
Councillor Joe WattVice-Chair, apologies, sent representative
CS
Councillor Chris StewardSubstitute, present as substitute

On this subject at York

Search all
  1. Six Monthly Update Report on Major Development Schemes in YorkThis decision
  2. Healthwatch York: Performance Monitoring / Six Monthly ReviewNoted
  3. Six Monthly Quality Monitoring Report - Residential, Nursing and Homecare Services.Noted
  4. Six-monthly Quality Monitoring Report - Residential, Nursing & Homecare ServicesNoted
  5. Six-Monthly Review of One Planet York StrategyAgreed
  6. Healthwatch York Six-Monthly ReviewNoted

More from York Economic Development and Transport Policy and Scrutiny Committee

All decisions
MeetingDecisionOutcome
10 May 2017 MinutesThat the minutes of the meeting of 8 March 2017 be approved as a correct record and then signed by the Chair, subject... Approved Open
10 May 2017 Report of York Civic Trust - Proposed Transport PolicyThat the report be noted. Reason: To update Members on the findings from York Civic Trust workshops focusing on a fut... Noted Open
10 May 2017 Annual Report from Make it YorkThat Members note the report. Reason: To ensure that Members are aware of the progress of Make it York. Noted Open
10 May 2017 Six Monthly Report on Major ProjectsThat Members note the report. Reason: To update Members on the present position in relation to major projects in the ... Noted Open
10 May 2017 Economic Strategy UpdateThat Members note the report. Reason: To enable the delivery of the Economic Strategy, and priority actions and outco... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies