That the application be approved subject to the conditions listed in the report. Reason: The site is brown field site in a sustainable location near to local shops, amenities and public transport links and it would, in principle, be suitable for redevelopment for housing purposes. It is noted that the Environment Agency accepts the submitted modelling demonstrating that the site is in fact at a low risk of flooding. The proposal would deliver affordable homes (built to Code Level 4) of the type needed within the City. In design terms, the scheme would be contemporary and it is considered that it would be of innovative design adding interest to the streetscene . There would be no adverse effect on highway safety and no significant adverse effects upon the amenity of surrounding residents. Because the City Council can not enter into a Section 106 Agreement with itself, a letter has been provided by the Head of Housing Services confirming that the a contribution of £ 7,524 towards amenity space and sports facilities in the locality will be made.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Date: 7 August 2014 Ward: Dringhouses and Woodthorpe Team: Major and Parish: Dringhouses/Woodthorpe Commercial Team Planning Panel
Reference: 14/01191/FUL Application at: Garage Court Site at Chaloners Road York For: Residential development to include 6no. apartments and 2no. houses with associated parking and landscaping By: City Of York Council Application Type: Full Application Target Date: 17 July 2014 Recommendation: Approve
1.0PROPOSAL
1.1The site is a garage site situated between existing two storey residential properties on Chaloners Road. It contains 15 no. garages set back within the site behind a grassed and tarmac forecourt. The rear of the site and the northern boundary are overgrown and there is an electricity sub station in the north east corner. The site is situated in a residential area and is bounded to the rear by Hogg's Pond.
1.2The proposal seeks to demolish the garages and erect a residential development containing 2 no. two bed houses and 6 no. 2 bed apartments. The application is made by Housing Services and the apartments would all be for social rent (although Housing Services do not know if they will form part of the downsizing provision for the over 55s as yet). 6 no. car parking spaces would be provided. Amenity space would be provided to the rear; including gardens for the houses and shared amenity space for the apartments. The sub station would be relocated to the front (south west) corner of the site.
1.3Consultation was undertaken at a Public Information Event on 16th April, prior to the application being submitted. There was general support for the scheme and comments made on the loss of the tarmac area for overspill parking and a reduction in roof height of the proposal. Attendees were advised that comments could be made through the formal planning process.
1.4The site is not allocated in the City of York Development Control Local Plan. The proposal represents a housing windfall and Policy H4a applies. The site falls within Flood Zone 3.
Application Reference Number: 14/01191/FUL Item No: 4f Page 1 of 15 1.5 A revised site plan has been submitted showing the sub station set back slightly within the site, so that the door would not open onto the footpath.
1.6The application is reported to Sub-committee as the City Council is the applicant and an objection has been received.
2.0POLICY CONTEXT
2.1Development Plan Allocation:
Air safeguarding GMS Constraints: Air Field safeguarding 0175 Floodzone 2 GMS Constraints: Flood zone 2 Floodzone 3 GMS Constraints: Flood zone 3
2.2Policies:
CYGP1 Design CYGP3 Planning against crime CYGP4A Sustainability CYGP9 Landscaping CYH4A Housing Windfalls CYT4 Cycle parking standards CYED4 Developer contributions towards Educational facilities CYL1C Provision of New Open Space in Development CGP15A Development and Flood Risk
3.0CONSULTATIONS
INTERNAL CONSULTATIONS
Highways Network Management
3.1No objections. We do not expect a material increase in traffic generation following the change of use. Car parking for 6 off street spaces will be provided as part of the scheme. In addition there is unrestricted parking on the carriageway fronting the development for 3 cars. Car parking satisfies CYC's Annex E standards. Cycle parking has not been fully detailed, but may be conditioned.
3.2Parking for the substation maintenance vehicles will be accommodated on the public highway verge due to the infrequent nature of the access to the sub station. We require the developer to provide permanent reinforcement of the highway verge fronting the new sub station to protect the grass and tree. Details of the reinforcement/tree protection will need to be conditioned and to the satisfaction of our landscape architect due to the proximity of the street tree.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.