Resolved
That the report be noted. Reason: To enable Members to understand the key issues and the response to the recommendations to secure improvements in control arrangements around sickness absence.
Audit and Governance Committee noted this item on Wednesday 10 December 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. Reason: To enable Members to understand the key issues and the response to the recommendations to secure improvements in control arrangements around sickness absence.
1. As requested by this Committee at its meeting held on 25 June 2014, this report outlines the plans in place and actions undertaken in light of the concerns raised within the Annual Governance Statement relating to sickness absence management across the council. It covers the response to the recent audit report which gave a ‘Limited Assurance’ rating to compliance to with the council’s policies in place.
The council’s policies and practice for sickness absence
2. In March 2013 Corporate and Scrutiny Management Committee concluded a review of the council’s sickness absence policy and its recommendations for improvement were approved by Cabinet in May 2013. The recommendations made in that report were enshrined within the revised policies finalised in October 2013 that the council has in place today.
3. Members are asked to note that whilst sickness returns from managers are input into the council’s Human Resources (HR) system, iTrent, and that Management Information is available for managers, direct input is not yet available. The iTrent project has focussed on payroll implementation for the council and its payroll customers, people manager, employee self service, time and expenses claims, performance management and recruitment. Resources for the project are currently being reviewed to identify the resources and timescales needed to implement the absence management module next which is a complex implementation covering all forms of leave arrangements in the council. Internal Audit Findings
4. It was against the revised policies that an audit was undertaken this year and a report finalised in July 2014, the outcomes were reported to this Committee in 2014 and the report can be found at Annex A.
5. The report states:
‘A number of weaknesses have been identified during the audit. They all relate to weaknesses and inconsistencies in practice between managers across the council rather than any inaccuracy of processing within the HR Business Centre. The most significant weakness is that not all sickness absence is being recorded on iTrent and therefore any management information produced is currently understating the amount of sickness absence across the council.’
Response to the Internal Audit Report
6. See below for the recommendations and actions undertaken since the production of the audit report:
a) Instances of sickness are not all being included on iTrent
Action:
Sickness statistics are now produced regularly and taken to the Council and Directorate Management Teams along with details of submission of sickness returns. Any discrepancies suggesting inaccurate recording are discussed with them. Internal Audit will carry out follow up audits and continue to be involved with the implementation of new iTrent modules to ensure that issues related to completeness and accuracy of recording are taken into account.
b) Self certification forms are not always being completed for instances of sickness.
Action:
Training is and will continue to be provided through the Workforce Development Unit (see details below) and regular emails are issued to all managers reminding of the importance of accurate recording and compliance with the attendance management policy and procedures, together with reports back to Council Management Team. Training has been strengthened also to support the advice given in induction procedures.
c) Appropriate action is not taken when trigger points are reached
Action:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Absence Management Update ReportReport | 7 pages | DownloadRead as text |
PDF |
AnnexAppendix | 7 pages | Download |
Follow Audit and Governance Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Oct 2026 | Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... | Decided | Open |
| 21 Oct 2026 | Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... | Approved | Open |
| 21 Oct 2026 | Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... | Noted | Open |
| 21 Oct 2026 | Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... | Noted | Open |
| 21 Oct 2026 | Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.