Resolved
That the report be noted. Reason: To ensure Members are updated on the council’s approach to business continuity and the current position.
Audit and Governance Committee noted this item on Wednesday 11 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. Reason: To ensure Members are updated on the council’s approach to business continuity and the current position.
1. This reports sets out the council’s approach to business continuity and the current position of the council with regards to identifying those service areas which provide critical services and progress towards the development of business continuity plans for these critical service areas. 2. The report covers two key areas:
The council’s overall approach to business continuity;
The directorate / service position;
3. The statutory duty for business continuity is placed on a local authority by the Civil Contingencies Act 2004, said duty is to have in place robust and resilient contingency plans to ensure the authority’s resources and staff are equipped to deal with a crisis situation effectively, while continuing to provide the usual day-to-day services of the Council.
4. In February 2014 Audit & Governance Committee received a report setting out an overview of the council approach and resilience in terms of emergency planning & business continuity. The report highlighted that the authority has a number of detailed and extensive emergency and business continuity plans which support the long term resilience of the city both in times of emergency and during the recovery stage. Key plans are:
The Emergency Handbook; Rest Centre Plan; Flood Plan; River Ouse Emergency Plan; (deals with incidents on the river) City Centre Evacuation Plan; Various internal Business Continuity Plans.
5. The report also set out that following the accommodation move to West Offices and the integration of a number of functions it was agreed to review the council’s approach to business continuity and where appropriate strengthening the approach. Committee asked for an update on this review in 12 months time.
The council’s overall approach to business continuity 6. All directorates have carried out Business Impact Assessments (BIA’s) to identify their critical functions and subsequently developed Business Continuity Plans (BCP’s). The aim of this approach is to:
Understand what functions are carried out and whether those functions are ‘critical’;
Clearly establish where responsibility for business continuity functions sit, i.e. service / directorate or corporate;
7. To ensure that there was a corporate approach, and importantly a consistency across all business continuity plans, it was agreed that the emergency planning team would review the templates, streamline them making plans focused and concise. This work was undertaken with key representatives from each directorate alongside external peer challenge. New templates for both BIA’s and BCP’s were devised and put in place. 8. In 2014 an audit of the council’s approach to business continuity was undertaken by Veritau. The purpose of this audit was to provide assurance to management that procedures and controls within the system will ensure that:
Risks and threats to critical services have been identified and assessed;
Business continuity plans have been produced and approved to ensure key services can be continue to be provided in an emergency;
There is an agreed process for invoking the council's business continuity plans when emergencies occur; Testing has been done on business continuity plans and staff have been given training as to how they should be implemented;
Business continuity plans have been communicated to relevant staff and published where appropriate.
9. In areas where the work had not yet been completed to reflect the council’s move to the West Offices, the audit reviewed the work that had already been done together with the proposed plans to complete outstanding tasks.
10. Key findings of the audit were:
That good progress was being made in refreshing the council’s approach to business continuity and in updating the individual plans to reflect the move to West Offices and other recent changes.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 7 pages | Download |
PDF |
Business ContinuityReport | 5 pages | DownloadRead as text |
Follow Audit and Governance Committee at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Oct 2026 | Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... | Decided | Open |
| 21 Oct 2026 | Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... | Approved | Open |
| 21 Oct 2026 | Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... | Noted | Open |
| 21 Oct 2026 | Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... | Noted | Open |
| 21 Oct 2026 | Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.