Six Month Update on Major Developments in York

Noted Scrutiny 1 paper

Economic Development and Transport Policy and Scrutiny Committee noted this item on Wednesday 11 March 2015. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

(i) That the restructuring of the major projects be noted. (ii) That the ongoing work being undertaken in order to deliver the various initiatives and developments as a matter of priority for the Council be acknowledged. Reason: To provide the Committee with a regular update on developments in the city.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Economic Development and Transport Policy and Scrutiny Committee, 8 pages

Summary

1. This report provides Members with an overview and update in relation to the major development projects in the city at this time.

Background

2. Since the national economic downturn and more recent improvement, Officers have continued to keep an open dialogue with developers in York in order to consider how approved but stalled sites may come forward without any significant lessening of overall planning aims in terms of mixed and balanced communities.

3. A number of longstanding approved development proposals have now commenced including Terry’s, the hotel at Walmgate and further phases of Hungate, as well as new sites such as the new student accommodation at the Press site and on Lawrence Street.

4. Officers have agreed changes of use (employment to residential), changes in type and size, layout, design and density as well as reductions in affordable housing requirements and Section 106 financial contributions, where justified by viability assessments. These revisions illustrate the commitment to support the delivery of good quality new development in the city.

5. Reports to Corporate Management Team (CMT), ECDOSC and Audit and Governance Committee, between November 2014 and January 2015, explained that major projects are to be streamlined to focus resources on eight potential key projects, identified as:-

1. York Central and Station Gateway 2. Community Stadium 3. York Outer Ring Road 4. Guildhall 5. Biovale 6. Public Realm Renewal 7. Southern Gateway 8. Fund of Funds

6. Each of the projects is or will be subject of a Project Initiation Document (PID) which will set out key outputs, targets and milestones for delivery.

York Central and Station Gateway

7. A Member Steering Group has been established, and meets in March. A Cabinet report with a range of key decisions, including financing from the Local Enterprise Partnership (LEP) West Yorkshire Transport Fund (WY+TF), is being prepared for the Summer of this year.

8. A Memorandum of Understanding, setting out high level terms of engagement between the City Council and Network Rail (NWR), has been agreed.

9. Detailed funding terms are being negotiated with Leeds LEP in terms of the £1.65m Local Growth Fund (LGF) flood resilience allocation and work to scope, design and cost the capital project will complete in March 2015, with project implementation from Q2 2015/16. Options to explore complementary EA grant are also being pursued.

10. Officers are working towards an autumn submission of a gateway 1 report for £27m WY+TF funding. Housing Zone shortlisting has been secured, and a ‘competitive clarification’ process entered into with Homes and Communities Agency (HCA).

11. Master plan led viability assessment has been undertaken for the site and officers will shortly commission work on a planning framework jointly with Network Rail, to facilitate phased site release, with a view to a start on first residential phase 2015/16 and commercial quarter in 2016/17. 12. A land assembly strategy is well underway, which is a key precondition of success.

13. Traffic surveys to inform the next stages of work and option assessment/ refinement will be undertaken in March of this year. Complementary Commercial Station Facility Improvement Funding will be sought to deliver works internal to station building (with CYC fronting any bid in order to comply with funding requirements), and synergies with HS2 investment will be explored through the HS2 Growth Plan currently being produced by the Council.

Community Stadium

14. The core project objectives are to provide a new Community Stadium within a new leisure facility complex on the grounds of the existing Huntington stadium/ Waterworld swimming pool.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Six Month Update on Major Developments in YorkReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. Six Month Update on Major Developments in YorkThis decision
  2. Dispensation of the Six Month Rule for City of York Councillors and Attendance at MeetingsDecided
  3. Healthwatch York: Performance Monitoring / Six Monthly ReviewNoted
  4. Six Monthly Quality Monitoring Report - Residential, Nursing and Homecare Services.Noted
  5. Six-monthly Quality Monitoring Report - Residential, Nursing & Homecare ServicesNoted
  6. Six-Monthly Review of One Planet York StrategyAgreed

More from York Economic Development and Transport Policy and Scrutiny Committee

All decisions
MeetingDecisionOutcome
10 May 2017 MinutesThat the minutes of the meeting of 8 March 2017 be approved as a correct record and then signed by the Chair, subject... Approved Open
10 May 2017 Report of York Civic Trust - Proposed Transport PolicyThat the report be noted. Reason: To update Members on the findings from York Civic Trust workshops focusing on a fut... Noted Open
10 May 2017 Annual Report from Make it YorkThat Members note the report. Reason: To ensure that Members are aware of the progress of Make it York. Noted Open
10 May 2017 Six Monthly Report on Major ProjectsThat Members note the report. Reason: To update Members on the present position in relation to major projects in the ... Noted Open
10 May 2017 Economic Strategy UpdateThat Members note the report. Reason: To enable the delivery of the Economic Strategy, and priority actions and outco... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies