Decision Session - Executive Member for Environment and Climate Emergency approved this item on Monday 4 April 2016. Below is the council's own wording, with the papers it was decided on.
That the updated contaminated land strategy be approved and a review be undertaken at least every five years. Reason: This will fulfil the council’s legal duties to update the contaminated land strategy and to inspect potentially contaminated sites. That the updated contaminated land strategy be approved and a review be undertaken at least every five years. Reason: This will fulfil the council’s legal duties to update the contaminated land strategy and to inspect potentially contaminated sites.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Environment and Climate Emergency, 7 pages
Summary
1. The purpose of this report is to seek approval by the Executive Member for the adoption and publication of the updated Contaminated Land Strategy.
Recommendations
2. The Executive Member is asked to:
Approve Option 1 - To approve the updated contaminated land strategy and undertake a review at least every five years.
Reason: This will fulfil the council’s legal duties to update the contaminated land strategy and to inspect potentially contaminated sites.
Background
3. The UK has a legacy of historic land contamination derived from past industrial activities and waste disposal practices. Land contamination, if not addressed can be hazardous to human health and the environment.
4. Local authorities have a statutory duty to implement and enforce contaminated land legislation (Part 2A of the Environmental Protection Act 1990), to create a clean and safe environment for all.
5. Local authorities must outline their approach to the identification and remediation of contaminated land in their area via a written strategy. City of York Council’s initial contaminated land strategy was published in July 2001 with subsequent updates in 2005 and 2010. Legislation
6. Part 2A of the Environmental Protection Act 1990 defines contaminated land as:
‘any land which appears to the local authority in whose area it is situated to be in such a condition, by reason of substances in, on or under the land, that;
a) significant harm is being caused or there is a significant possibility of such harm being caused; or b) significant pollution of the water environment is being caused or there is a significant possibility of such pollution being caused.’
7. Local authorities are required to inspect their areas for contaminated land and secure the cleanup of any sites which pose unacceptable risks to human health and/or the environment.
8. Statutory Guidance, published by the Department for Environment Food & Rural Affairs (DEFRA) in April 2012, established a legal framework for dealing with contaminated land and must be strictly followed by the council.
9. Part 2A works alongside planning rules to help ensure that land is made suitable for use following redevelopment.
Contaminated Land Strategy (2016)
10. The contaminated land strategy has been updated to incorporate recent changes in legislation and guidance and to provide an update on progress made to date.
11. In York 3,690 potentially contaminated sites have been identified and prioritised; detailed inspections of these sites should be undertaken in priority order.
12. Of the 3,690 potentially contaminated sites, 88 sites have been categorised as Category A (high priority), where there is a high risk of an unacceptable impact on people or the environment:
13 of the Category A sites have been inspected under Part 2A and 9 of these required Phase 2 investigations; 20 of the Category A sites have already been, or will soon be, investigated through the planning regime (including Heworth Green gasworks, York Central and British Sugar); 49 of the Category A sites are currently in use as industrial / commercial premises and no further action is required at present; and 6 of the Category A sites have not yet been inspected.
13. Part 2A inspections are very expensive and can cost tens of thousands of pounds; historically these have been funded by DEFRA’s contaminated land capital grants programme; however, the contaminated land capital grants programme was withdrawn in April 2014 and no budget has been allocated to undertake contaminated land investigations of the remaining 6 Category A sites (high priority) or any of the Category B sites (high to medium priority).
14. In order to protect people and the environment from harm, contaminated land sites must be dealt with as and when they arise.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Environment and Climate Emergency at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.